Decision on the third item on the agenda: Building questions: Headquarters building renovation project
Decision on the third item on the agenda: Building questions: Headquarters building renovation project
(a) approved the proposal not to construct a temporary prefabricated building for use as “swing space” during the renovation of the headquarters building, provided the project remains within the original budget and schedule;
(b) requested the Office to submit to the 315th Session (June 2012) of the Governing Body a further progress report on the project;
(c) requested the Director-General to commence action to appoint a full-time professional project manager for the duration of the project, and to report on this to the Governing Body, at its 315th Session (June 2012).