|
Regional Seminar Proceedings 1993
Project Background
With financial assistance from DANIDA and SIDA, the Government
of Zimbabwe, through the Department of State Roads of the Ministry
of Transport, commenced in 1991 a road rehabilitation programme
using labour-based methods and local resources. A first pilot site
started in 1991 with technical assistance provided by a Danish consultancy
firm, COWIconsult. Under this project, demonstration sites have
been implemented, management procedures and administrative systems
have been developed and tested and staff trained. This project was
positively evaluated in 1993 and it has been proposed to expand
and institutionalize these activities during a six year period starting
mid 1994. SIDA and DANIDA will continue to provide financial and
technical support, with 35% of the invest costs for the works being
provided by the Government of Zimbabwe.
Design Standards
The design of these roads complies with the design standards used
by the Department of State Roads for low-volume all-weather gravel
roads. Figure 3.1 shows the cross section of the roads being constructed
by the labour-based programme.
The roads originally dirt tracks which are now upgraded to a 6
m carriage way with a 15 cm gravel layer. The roads alignment runs
through tribal communal lands in slightly rolling and rocky terrain.
Before the rehabilitation works, access was restricted to the dry
season, with approximately 20 vehicles per day. The average daily
traffic on the completed road section has been registered at 50
- 70 vehicles per day.
Work Methods
The projects are executed using labour-based construction methods
complemented with light equipment for compaction and hauling of
gravel and water. All earthworks are carried out by manual labour.
Excavation of gravel, drainage, camber formation and installation
of culverts is done by hand. Gravel is transported by tractor drawn
trailers but loaded, unloaded and spread by labour. Compaction is
carried out by Bomag pedestrian rollers. Gravel sources have been
located in the vicinity of the road alignment.
DANIDA Project
The DANIDA assisted project started out with the upgrading of 28.7
km of Road 185 in Mudzi and Mutoko District. These works were completed
in August 1993, the project commenced construction on Road 278 and
has so far completed 21.2 km.
The work has been carried out by extensive use of labour combined
with a fleet of light equipment. Operating at full strength, the
project has employed around 400 labourers, divided into two teams.
Each team has 5 supervisors, with ne being in charge overall per
team. This construction unit has experienced a maximum output of
4 - 4,5 km gravelled per month during the last half of 1992 and
the beginning of 1993.
The equipment pool consists of the following:
6 tractors MF 390
12 Tinto non-tipping trailers 3 m3
4 Bomag pedestrian rollers 950 kg
2 water bowsers 4500 l (Tinto)
2 water bowsers 1000 l (Tinto)
2 Honda water pumps
2 generators 11 & 5 kVA)
1 tipper truck (to be replaced by a 5 tonne flat bed truck)
2 Toyota Hilux single cab
2 Honda motor bikes
Table 3.1 and figure 3.2 and 3.3 summarize the costs and labour
productivity achieved so far on this project.
| Road No. |
Prod. km
|
work days
|
Wd/km
|
Cost
|
Cost/km
|
| 185 |
28.72
|
99,084
|
3,450
|
2,572,264
|
89,564
|
| 278 |
21.2
|
54,883
|
2,589
|
1,311,633
|
61,869
|
| Total |
49.92
|
153,967
|
3,084
|
3,883,897
|
77,802
|
Table 3.1 Production and Cost Data (Zimbabwean Dollars)
Major Constraints
Long and expensive water haulage during the dry season, particularly
May to November 1992.
Inadequate cement supplies for drainage works.
Considerable down time on the tractors and trailers as the equipment
got older. This is mainly related to the hitch, fuel injectors,
rims and tires on the tractors, and lacking A-frame on the trailers
causing the trailer axle to become loose, and cracking o the bucket.
Figure 3.2
Figure 3.3
Senior staff salaries for engineers, and partly superintendents
and stores assistants.
Staff housing and office units. These are costed instead on a monthly
hire charge basis.
Expatriate staff salaries and accommodation, and supervision vehicle
costs.
Miscellaneous costs such as classroom rental, photocopier, computer,
etc.
Labour Statistics
Each of the road construction projects has provided temporary employment
to approximately 1300 unskilled workers recruited from the nearby
villages, of which on average 25% were women. The duration of their
employment has varied, with approximately 50% recruited for a minimum
period of three months. Table 3.2 summarizes the total numbers employed
and their gender distribution.
| Road No. |
Men
|
Women
|
Total to date
|
| 185 |
1065
|
76%
|
327
|
23%
|
1,392
|
| 278 |
906
|
73%
|
336
|
27%
|
1.242
|
Table 3.2 Employment Data
90% of the works carried out by the unskilled labour has been organized
as task work. The daily wage rate for casual unskilled labour is
currently 8.73 Z$/day (US$ 1.34).
With financial assistance from SIDA and with technical assistance
provided by the Swedish consulting firm SWEROAD, rehabilitation
works commenced in April 1993 on the 18 km Mutoko -Nyamazuwe section
of Road 185. Currently this project is progressing with a monthly
production of 4 km executed by two teams of 200 labourers. Each
team is assisted by an equipment fleet consisting of 3 tractors
and 6 trailers, 1 water bowser and 2 rollers (1500 kg). Average
number of work days is currently 2269 wd/km. The project is expected
to be completed by November 1993 at a final cost of 70 000 Z$/km
(11 500 US$/km).
|