|
Regional Seminar Proceedings 1990
SESSION 6
SITE VISIT
THE USE OF LIGHT EQUIPMENT IN ROAD REHABILITATION
6.1 GRADING DEMONSTRATION
RRM Mbeya are using a double axle towed grade manufactured by Arthur
Garden in Zimbabwe. The grader is towed by a 75hp tractor. It is
used for removing corrugations on earth roads or returning gravel
from the shoulders to the carriageway, on gravelled roads.
When in operation the grader uses 5 passes on each side of the
carriageway with a maximum cut of 10cm. It can cover a distance
of 2km of road per day. The team working with the grader consists
of the tractor driver, one or two grader operators and two labourers.
The job of the labourers is to remove stones and grass from the
centre of the road once the grader has passed. They are assisted
by the maintenance lengthmen on the road who also ensure that all
drains are kept open during grading. RRM Mbeya would hope to grade
each road, under maintenance, 2 or 3 times per day.
During the small demonstration the depth cut by the grader was
much less than the maximum of 10cm, therefore this figure depends
very much on ground conditions.
6.1.1 THE FOLLOWING DISCUSSION RESULTED FROM THE GRADING DEMONSTRATION
Questions were raised which could be tested in the future.
- Would it be possible to have a group of labourers working behind
the grader raking the soil into shape and therefore reducing the
number of passes of the grader.
- Could the tractor be used for grading, then in the latter part
of the day tow a roller to compact the loose soild of gravel which
has been brought back onto the carriageway by the grading operation?
There are fears that the road surface can be damaged by traffic
when rain falls on an uncompacted newly graded road.
The possibility of using the towed graders for heavy grading was
generally not recommended by the participants. Arthur Garden also
produces a single axle towed grader which would be easier to manoeuvre
but needs to be carefully teamed up with the correct tractor.
6.1.2 EXPERIENCES FROM DIFFERENT CONTRIES
In Mozambique they have been using a light tractor towed blade
for very light grading. The advantage of this blade is the ease
of transportation from site to site. RRM Tanga are also doing some
work with a blade attached to the tractor. In Botswana the normal
maintenance set up is one tractor, one trailer, one towed blade
plus 10 men. In Zimbabwe one overseer, 20 men with one tractor,
one trailer and one blade are responsible for the maintenance of
300 km of road.
6.1.3 GENERAL
Training of grade operators is important for the correct results
on the road and for the care of the grader itself. In Mbeya the
operators spent 2 days in the classroom followed by 3 months training
in the field. They are issued with tools to carry out routine checks
on the graders including the frequent tightening of bolts as they
have a tendency to work loose. Blades must be regularly replaced
to ensure a good cutting edge.
6.1.4 CONCLUSION
It is vital to team the correct power and weight of tractor with
the correct weight and size of grader. A light tractor will not
be able to pull a heavy grader trying to make a deep cut. Any purchase
of grader should be carefully considered in terms of the job it
is required to do and then the most suitable tractor for towing.
If a project is confined to the use of a particular tractor then
this must have a bearing on the choice of towed grader. More information
on grader/tractor compatibility is available from EMP/INFRA, ILO
Geneva.
6.2 REHABILITATION AND GRAVELLING ROAD SITE
The road visited which was under rehabilitation, was a loop road
and therefore work was started at both ends. The first group started
in May 1989 and the second in September 1989. Thirteen kilometres
have been rehabilitated, gravelled and compacted. The productivity
is 1800 mandays per km (md/km) for road construction and 1300 md/km
for gravelling. There is no shortage of labour and rehabilitation
can progress at the rate of 1 to 1.5 km per month however gravelling
was progressing at a rate of 0.8 km per month. At the time of the
site visit rehabilitation had stopped and the labour force were
concerntrating on excavation of gravel.
Graders had not been used on this site as there was a plentiful
supply of labourers and a good quality finish to the road surface.
The visit to this site afforded the opportunity to look at the
rollers and trailers in use at RRM Mbeya.
6.2.1 COMPACTING ROLLERS
Two types of rollers were on site. The first was the pneumatic
tyred towing roller with the top tray which could be filled with
earth for extra weight and the second was a towing vibrating roller.
The pneumatic tyred roller is performing well in most soil conditions
however on the road site visited there were areas where the vibrating
roller was more effective.
An alternative discussed for use on labour-based sites was the
pedestrian roller which would be suitable for the speed of progress
on labour-based sites.
RRM Mbeya have also done compaction trials using an ox-drawn deadweight
roller. Using the sand replacement test the ox-drawn roller gave
85% compaction inmoist conditions dropping to 65% in dryer conditions.
Compaction took place after every step of rehabilitation thus the
maximum thickness to be compacted was 10cm. In Kenya they found
that a manually pulled roller gave as good results as the animal
drawn and was an easier option than engaging animals. Botswana do
not use compaction equipment but rely on traffic compaction, however
they have a much longer dry season that in Southern Tanzania. In
Rukwa traffic compaction only had been used but this may only be
possible on lightly trafficked roads. The Kenyan Minor Roads Programme
are not using compaction equipment but rely on vehicles despite
the much higher traffic flows. Various reports from TRRL have shown
good results can be obtained from traffic-only compaction, however
this has been based on low traffic RARP roads in Kenya. Lesotho
has found compaction, using 1.25 tonne vibrating rollers, to be
essential under all circumstances because of poor soil types.
It was noted that projects should be very careful in deciding their
compaction requirements at an early stage, based on both traffic
and soil conditions in their particular circumstances. Traffic only
compaction is not always satisfactory, but mechanical compaction
represents a major initial recurrent investment.
6.2.2 TRAILERS
Two types of trailer were looked at and discussed. The first was
the Kenyan trailer and the second a recently purchased trailer from
Tinto Industries Harare. Both trailers were non-tippping. The Kenyan
trailer has had a lot of design problems and has had to have extensive
repairs carried out in the workshop. This trailer is very heavy
when loaded (4.5 cu.m.) and the axle location places a large proportion
of the weight on the tractor. However the most popular feature of
this trailer is the low loading height. Until a major redesign has
been carried out this trailer would not be recommended because of
the damage to the tractors and the need for constant repairs.
The Tinto trailer has a good basic design combined with good quality
workmanship. There were some weaknesses in the bolted connecion
for the drawbar so RRM added welds in their own workshop. They are
also not entirely satisfied with the opening mechanism for the side
doors (which are to facilitate unloading) but have approached the
manufacturers to reassess the design of these features. The one
disadvantage is that the loading height is greater that that of
the Kenyan trailer. The Tinto trailer had only been is use for two
months at the time of the site visit and therefore a futher report
should be made aftr a longer period of service.
6.3 ACTION TO BE TAKEN
A request was made that all project staff should carry out tests
if they are using compaction equipment. This would give figures
for the future discussions on compaction methods and remove the
present subjectivity when discussing animal drawn versus tractor
towed etc.
NOTE:Tractor and Trailer combinations are also discussed in Section
5 of this report under the heading of "Haulage of Materials".
|