|
Regional Seminar Proceedings 1990
SESSION 3 - ALIGNMENT CONTROL
3. DISCUSSION ON ALIGNMENT CONTROL
MORE SCIENCE AT SITE
3.1 DEFINITIONS
For the purpose of the discussion the method outlined in this paper
and other similar methods will be termed as the profile method,
also the mehtod using slots to create a level platform from which
to excavate the drains and create the camber, will be termed as
the slot method.
3.2 PROFILE METHOD
The method proposed in this paper was wholeheartedly supported
by the participating experts from Botswana and Zambia (who were
using this method). In Zambia the project had slightly modified
the approach but found it to be successful in a variety of terrain
including steep terrain. Other participants found level control
for drainage also very important in rolling or flat terrain.
Using this method engineering advice on site should only be necessary
in difficult areas after the foremen have been trained to carry
out the design/setting out functions.
Casual labourers are good at ensuring the correct shape of road
cross-section during construction but the lingitudinal control is
not there unless there is 100 to 200 metres set out and properly
adjusted for level at one time in advance of the work. In comparison
the levelling of slots tends not to be carried out over long sections
of road therefore making it difficult to produce a good vertical
alignment.
Fears were also expressed that the large number of profiles needed
for setting out in the profile mehtod would interfere with the increased
traffic levels expected in Minor roads in Kenya and Regional roads
in Tanzania. Those using the profile method said that the profiles
once aligned could be replaced by pegs and string lines thus reducing
any interference with the traffic.
3.3 METHODS USED BY DIFFERENT PROJECTS
Mbeya has employed a method which uses slots plus mobile profile
for vertical alignment. Tanga is using the slotting method as is
Mozambique. Rukea has used the slotting method but has proposed
to try the profile method on the next road to be rehabilitated.
Kenya are continuing with the slotting method which they find is
perfectly adequate on green field sites. However in the coming year
they will be assessing alternatives as some problems have arisen
when upgrading badly eroded roads or roads in restricted areas such
as those adjacent to fields with high value crops. They will be
producing a technical manuals from their findings.
3.4 SLOTS METHOD
The slot method has proven very successful for the rural Access
Roads Programme in Kenay, but there are reservations about its suitability
for the Minor Roads Programme. It was argued that some of the difficulties
in producing a good finish to the road were problems with management
rather than at site level and therefore a change in method would
not solve these problems.
One of the advantages of the slot method is the ease with which
the foremen can calculate the task rates for the casual laboureres
once they have created their level platform. Using the profile method
the volume of work will be constantly varying. In Zambia, the project
has issued tables to the foremen so they can read off the quantities
and task rates for a given depth of excavation thus easing this
problem.
3.5 LIGHT GRADING OF THE ROAD SURFACE PRIOR TO GRAVELLING
When dealing with the question of the quality of the road surface
finish, there was a suggestion that light grading could smooth the
surface of an earth road befor ethe placing of gravel. The argument
for carrying out this work was a better finish to the road and a
saving in the quantity of gravel used. The arguments against were
that if people know a grader is coming they will take less tourble
to ensure a good standard of finish by hand. The grader is an additional
cost and may not be sustainable and will not remove large ruts.
3.6 GUIDELINES
It was proposed that John Marshall and Walter Illi look at the
different methods used in various projects and perpare general guidelines
on the methods for producing an acceptable road alignment with functioning
drainage. They were asked also to co-operate with Gary Taylor who
will be carrying out a similar study in Kenya. The suggestion was
made that those projects using the profile method should not be
too rigid in their recommendations as the method was developing
all the time.
3.7 TRAINING
Trainers should have clear guidelines stating what the engineers
need from trained foremen and supervisors. There is a need for an
urgent decision on method and training, in Tanzania, before the
Ministry of Communication and Works start their large training programme.
3.8 AGREED PLANS FOR ACTION, CONTROL OF ALIGNMENT
| WHAT |
WHY |
WHO |
HOW |
| Revised level control guidelines |
Improved and sustainable road Standards |
John Marshall/Walter Illi |
Information from current projects/site Implementation(RRM
will support) setting out manuals from each project. |
|