|
Regional Seminar Proceedings 1990
SESSION 2 - LOW COST STRUCTURES
2. DISCUSSION ON LOW COST STRUCTURES
LOCAL RESOURCE ALTERNATIVES TO HIGH SPECIFICATION MATERIALS
2.1 DRIFTS
There is only a slight difference in cost between culverts and
drifts. Drifts are slightly cheaper and they have the advantage
that in most cases the road can be kept open during construction.
The approaches to drifts are important as they can cause damage
to vehicles and give the road users a low opinion of drifts if they
are too steep. A recommended slope for approaches would be 5 %.
The importance of properly constructed aprons, especially the down
stream protection, should always be emphasised. Some guidance is
needed on the size and depth of the upstream and downstream protection.
2.2 AVAILABILITY OF SKILLED PERSONNEL
Availability of skilled personnel to construct dry stone masonry
structures and cement bound stone arches. How can you train masons
who are inexperienced in building dry stone masonry structures?
In nepal untrained workers worked with experienced masons until
they had acquired sufficient skills to work independently. It would
be possible for ILO to arrange short term consultancies for a skilled
mason to give demonstrations and train local workers in building
with stone. This training could be either in dry stone work or in
more complicated cement bound masonry such as stone arch bridges.
Another source of information on low cost structures and stone
arch bridges would be Indian Government publications and/or Indian
University texts.
2.3 BURNT BRICKS
Burnt bricks may be used in place of stone where stone is not locally
available. However care must be taken with the quality of the bricks
and the implications for deforestation for the burning of the bricks.
2.4 TOOLS FOR MASONRY WORKS
In most cases road construction programmes have used the locally
available tools. There is a listing of masonry dressing tools in
the "ILO Tools Manual" if tools were to be procured by a project.
2.5 STONE PITCHING ON RARRIAGEWAYS
Stone pitching has been used successfully in different countires,
to assist on steep sections of road. If cobbles or setts are to
be used they must be placed properly to be effective and durable.
2.6 TIMBER ALTERNATIVES
The use of timber for bridges is a wide topic and would have to
be tackled as a separate issue.
In Makete, Tanzania the roads project has successfully used timber
for constructing culverts, at the cost of US$25 per culvert, with
a life expectancy of five years.
Using timber for a large number of structures may pose a problem
for future repair or replacement of decks as where previously there
may have been a plentiful supply of timber deforestation may drastically
reduced supplies.
2.7 UNREINFORCED CONCRETE PIPES
None of the participants reported problems with performance of
the unreinforced concrete pipes, however, there were a few reports
of breakages during transportation and breakages due to poor backfilling
of the culverts on site.
Culverts can either be produced in casting yard or adjacent to
the road site. Having a casting yard close to the engineers office
may allow closer supervision and greater quality control. A casting
area at site may reduce the need for transport if located close
to the sources of sand, gravelor stone for aggregate. In addition
the delivery distance for the finished culverts would be reduced.
Quality could perhaps suffer from less frequent supervision and
less skilled staff. There are arguments for both options but the
expense of transport should be carefully considered when deciding
on the location for casting unreinforced culverts.
Dissatisfaction was expressed over the quality of the concrete
pipe coulds. Some participants were of the opinion that those moulds
being produced at present should be used, despite some problems,
whereas other participants felt there should be a continued search
for better quality moulds.
The Zambia project has ordered moulds from Malawi but they have
not been tried out yet. Kenya and Tanzania projects are using locally
produced moulds.
There are two criterion for producing better quality moulds:- a
good design, and good quality control during manufacture. An incentive
to ensure quality control during manufacture would be the placing
of large orders rather than small orders for six or eight moulds
only.
2.8 ALTERNATIVE STRUCTURE
As a general principle all road structures should be designed and
costed with alternatives. The decision on which type of structure
is to be built will therefore be based on an economic comparison
of each proposal.
2.9 AGREED PLANS FOR ACTION, LOW COST STRUCTURES
| WHAT |
WHY |
WHO |
HOW |
| Masonry Trainer/Guidelines (identify and prepare) |
Increased use of local resources through technical information
and costing |
Regional Adviser
Experts |
Inputs from Experts Consultations |
| Culvert Moulds proven sources |
Reliable moulds |
Regional Adviser/RRM (Tanzania) |
Inputs from projects |
|