|
Regional Seminar Papers 1997
Road construction and maintenance
Rehabilitating
and Maintaining Surfaced Roads
A O Bergh, P J Hendricks and I Cassiem, Division of Roads and
Transport Technology, CSIR, Pretoria
Introduction
The South African Department of Transport (SADOT) has recently
published a series of manuals prepared by the Division of Roads
and Transport Technology of the CSIR which are designed to teach
student trainees the art of maintaining and upgrading streets using
labour-based methods. The manuals were based on a pilot project
undertaken in Phuthaditjhaba in the North-Eastern Free State where
various maintenance and upgrading techniques were tested as part
of a community training program.
This paper will focus on the labour-based upgrading methodologies
used in Phuthaditjhaba and fully described in manual 7 of the series.
The manual describes techniques that can be used to upgrade existing
gravel streets, using the existing structure as a subbase, where
traffic volumes are below 500 vehicles per day, with less than 10%
of these being heavy trucks.
Geometrics
Generally speaking, the roadworks in townships have been constructed
to grade and crossfall and the houses are normally constructed in
a straight line. A number of methods can be used to establish the
centre line of an existing street, including using:
- boundary beacons;
- the fence lines/boundary lines if uniformly constructed, as
shown in Figure 1. However, fence lines are not always correct
, thus making this method unreliable and inaccurate;
- the houses, if these are set out in straight lines;
- the best line that can be established from the electricity poles;
- the best line that can be established from the existing gravel
road, taking into account the fronts of the houses.

Figure 1: Establishing the street centre line
Once the centre line has been established, using ranging rods,
the edge of the street can established by placing steel pegs at
10m intervals, 400 mm above the existing ground.
In the pilot project, the pegs were placed on the edge of the topside
of the crossfall of the street, in order to construct an open drain
on the topside of the crossfall. To reduce the earthworks to a minimum,
a "rolling grade" was established by tying a white sisal string
line to the tops of the steel pegs. This "line" was adjusted by
eye by lowering or raising the pegs to give a smooth rolling grade
line.
Once the rolling grade line had been established, reference pegs
were placed exactly 400 mm below the top of the adjusted steel pegs
(rolling grade line). See Figure 2.
Figure2: Establishing rolling grade

Drainage
For township drainage it is essential that, prior to surfacing
the road, the main stormwater spinal drainage is in place. In this
case, the outfall main stormwater drainage was in place.
It was decided to use an open drainage system as this obviated
the problem of blocked stormwater drains in townships.
Steel templates were placed every 2m, care being taken to place
these templates accurately, as the top of the open drainage system
on the edge of the road would form a reference line for construction
and preparation of the subgrade.
Concrete was cast in alternate bays using light reinforced mesh
only on the leg of the side drain closest to the road. Originally,
the concrete was mixed by hand as part of the training, but to expedite
the work, a small concrete mixer was used on the latter part of
the works.
On relatively flat slopes, the levels, as set out above, were checked
with a dumpy level to ensure that sufficient fall had been obtained.
It is recommended that where very flat slopes are encountered, this
check be instituted.
Construction of Subbase
By selecting the appropriate crossfall, which can vary between
2% and approximately 2.8%, the amount of earthworks to be done with
hand labour can be determined, using the final concrete level of
the drain as reference points along the length of the road.
The top of the finished side drain served as a datum for establishing
the levels of the opposite edge, which were obtained by transferring
this level with a spirit level and a straight edge. The subgrade
was levelled off to the required levels using picks and shovels.
Wheelbarrows were used to cart the material to the fill areas. The
subgrade/subbase was well compacted by the traffic prior to construction,
but a BOMAG 65 pedestrian roller was used to compact the final earthworks
and fill areas.
To expedite this work, the surface was well watered the previous
day with a garden hose attached to the standpipe at one of the houses.
It was also possible to stockpile some of the gravel obtained in
the excavation for use at a later stage in the emulsion treated
base.
It was most important to ensure that the levels of the subbase
were as accurately constructed as possible, since that assisted
with the laying of the steel shutters when the emulsion treated
base was placed.
There were one or two minor areas which were clayey. These were
treated by hand and compacted in situ.
Material Selection and Design
The in situ material was checked by carrying out a dynamic
cone penetrometer (DCP) survey of the four streets involved. It
was established that the cover corresponding to the in situ
California Bearing Rations (CBR's) obtained from the DCPs was generally
greater than that required in the old National Road 7,000lb. design
curves. It was therefore decided to use a 100 mm thick base as this
would be perfectly adequate for the type of traffic anticipated
on these lightly trafficked streets.
From an economy point of view, it was necessary to use whatever
local materials were available. The local material that was readily
available at the time was a decomposed dolerite material.
The streets were also gravelled with decomposed dolerite. Tests
were done, not only on the gravel on the streets, but also on gravel
from the quarries, with a view to using this material with emulsion.
As the plasticity indices (PIs) of the gravel were all in excess
of 10 (to 15), it was necessary to treat the material not only with
emulsion, but with lime before application of the emulsion.
The amount of emulsion used was 2% of anionic stable grade emulsion,
1% of cement and 1% lime. The lime, cement and gravel were first
mixed dry by hand, after which the diluted emulsion was applied.
The densities obtained in the field were in the order of 97% Mod.
AASHTO density, which were obtained with a 65 BOMAG pedestrian roller.
The CBRs of the materials tested in the laboratory varied from
106 at 93.8% compaction to 290 at a compaction of 99.3%.
Method of Construction
Layout
Each street, with a road width of 3.5m, was split into half-widths
of 1.75m.
The reason for this is that when very coarse material is used,
it is onerous for labour to screed the material. The concrete side
drain formed one continuous level to which the emulsion treated
base had to be placed, the level on the other side being controlled
by steel shuttering formed of 100x150 mm angle iron.
Materials
The emulsion used was anionic stable grade 60% bitumen emulsion,
delivered to the site in 210 litre drums. The drums were rolled
off the delivery truck onto steel or timber ramps to prevent any
breakages and undue breaking of the emulsion in the drum. The drums
were rolled backwards and forwards to ensure proper mixing of the
emulsion before they were used, as the drums had been stockpiled
on site, which causes the bitumen in the emulsion to settle to the
bottom of the drum.
The drums were placed on a steel frame such as the one illustrated
in Figure 3 and were fitted with a ball valve. The height of the
steel frame was high enough to accommodate the measuring cylinders.
Figure 3: Stand for drums of emulsion and typical
measuring drums
The ball valve allowed the control of emulsion into the measuring
containers and to ensure a clean and neat operation with minimum
wastage.
Blending
The quantities of cement and lime required per batch were measured
with the measuring containers (see Figure 3). The ETB was mixed
by hand and, in the latter part of the project, with a concrete
mixer. The aggregate was delivered on site with a large amount of
oversize and was then stockpiled as close as possible to the working
area. The grading of the material was very coarse and to overcome
this problem, coal forks were used from which the alternative tynes
had been removed. This enabled the labour units to remove the coarse
material, leaving relatively fine material for the work. The gravel
was firstly mixed with cement and lime, followed by the diluted
emulsion, up to 1:10, i.e. 1 part emulsion to 10 parts of water.
The initial proportion of emulsion to water was 1:3 or 1:4. This
was then checked to determine whether the water should be increased
or reduced. The amount of water in the gravel was also taken into
account as this affected the degree of dilution. The amount of liquid
that was added to the mix was approximately 1 - 1.5% over the optimum
moisture content required for the Mod. AASHTO density which had
been obtained from the laboratory tests.
Measuring containers were essential to maintain accurate work for
both aggregate and emulsion. The 25 litre cans were fitted with
handles which made them user friendly. The 10 litre cans were used
to measure the quantities of cement and lime.
Placing of ETB
The maximum depth of ETB that can be effectively compacted with
the BOMAG 65 is 75 mm. As the thickness of the ETB layer was 100
mm, it was therefore necessary to place the ETB in two layers.
The first layer of ETB was placed level with the shuttering and
the top of the drain. (i.e. for 100mm base). Steel squeegees
were used for levelling the mixed ETB as the rakes tended to cause
the mix to segregate, which is not desirable, whereas steel squeegees
distribute the material uniformly without segregation.
The second layer of ETB was placed level with the top of the gauges,
which had been placed on top of the shuttering and drain. These
ensured the uniformity of the constructed level of the final base.
The steel screed was used to obtain the final levels of the ETB
uniformly between the steel shuttering and the top of the side drain
or that of the inside edge of the concrete gutter.
The surface was dampened with a light application of water to prevent
it drying out prior to compaction. Normally four to six passes with
the BOMAG 65 were required over the uncompacted material.
The emulsion treated base was placed in the box and screeded to
the level of the top of the concrete and the top of the steel shuttering.
Steel squeegees were used to spread the material ahead of the screed.
Once some 8m of length of road had been placed, the pedestrian roller
was used for compacting this material.
Once the first layer had been compacted, second layer of ETB was
applied, using 25 x 25 mm box sections on top of the concrete and
the steel shuttering. This was compacted with the BOMAG pedestrian
roller, until the material had been compacted to the level of the
concrete and steel shuttering, the box sections having been removed
from the concrete and steel shuttering.
Before the second application of ETB was placed, the surface was
treated with diluted emulsion in the ratio of 1 to 10, and on completion
of the second layer, the surface was again treated with diluted
emulsion in the ratio of 1 to 10 emulsion to water.
Advantages of Using the Emulsion Treated Base
There are several advantages to using emulsion treated base, apart
from the strength that is obtained with the process:
- As the work is done with hand labour, there is usually an extended
period of time which elapses before the road is surfaced. The
emulsion treated base is capable of carrying this traffic without
surfacing for extended periods.
These streets were open to traffic for up to three to four months
before surfacing was applied, without any damage of consequence
to the surface.
- There is no deterioration as far as cracking of the base is
concerned.
- The problems experienced when priming a base and waiting for
it to cure and stopping the public from using the uncured primed
base are obviated when an ETB is used, even if the surface has
to be treated with diluted emulsion after extended periods of
being used by traffic.
- Should the surface be damaged mechanically, the base will not
deteriorate and form potholes, as is the case with other unstabilised
material or even crusher run material.
Surfacing
The object of this pilot scheme was to establish which surfacing
would be the most economical and appropriate to apply by labour-based
methods. Four types of surfacing were placed on four different streets,
namely :
- a single seal
- a double seal
- a Cape seal, and
- a slurry seal.
In all cases where binder was sprayed on the road, a motorised
hand sprayer as shown in Figure 4 was used.

Figure 4: Motorised hand sprayer
Before any spraying could be done, it was necessary to establish
the delivery rate of the spray pump. The rate of application of
the binder was then controlled to within 10% using an enlarged manually-operated
clock, controlled by the second hand of a wrist watch. The use of
emulsion ensured that any errors in the quantities of the residual
binder sprayed were reduced by some 35 to 40%.
- Single seal
Students were instructed in how to use the ALD method for establishing
the application rates of both binder and aggregate by using the
pan and cylinder method for establishing the ALD and in the use
of graphs to establish their prospective application rates for binder
and aggregate. A 65% cationic bitumen emulsion and a 9.7mm aggregate
were used for this single seal. Generally a maximum of 0.7 litres
to 0.8litres of emulsion can be sprayed before the binder tends
to flow. For this reason, a tack coat was applied at 0.7litres/m²
and the aggregate neatly spread in a single layer by hand from small
accurately measured heaps, spotted along the shoulder of the street.
The surface was rolled and the balance of the binder sprayed as
a penetration spray. Protective screens as shown in Figure 5 were
used to ensure a neat edge line of the surface both for tack and
penetration sprays. The final result was a sound and uniform surface,
with no whip-off of aggregate.

Figure 5: Protective screens
The measuring containers (half drums) were used for spotting the
aggregate along the constructed base to ensure accurate application
rates of aggregate.
A manually operated clock was used in conjunction with the spray
machine to apply the binder at required rates. The discharge rate
of the spray machine was determined, the area to be covered with
the binder was demarcated and the required time to cover such a
section was then calculated. The spray operator had to finish that
section in the required time. The chips were then applied by hand
using shovels. The BOMAG roller, Figure 6, was used to roll the
chips into the binder.

Figure 6: BOMAG 76 roller
- Double seal
A double seal was constructed as above using a 13mm and a 6.7mm
aggregate with cationic emulsion. To ensure minimum whip-off of
aggregate the 13mm aggregate was choked with 6.7mm aggregate to
obtain a tightly knitted surface before the penetration spray was
applied. The 6.7mm aggregate was uniformly applied in a single layer
and well rolled before a final fogspray was applied. The quantity
of binder required after application of the tack coat was split
between the penetration spray and the fogspray. The final result
was sound and the seal was found to be suited to labour-based application
if well controlled. A double seal is probably the most difficult
seal to apply efficiently with hand labour as much of its success
depends on experience in the efficient use of rollers.
- Cape seal
The Cape seal consisted of a 13 mm aggregate applied in a similar
manner as in the single seal, using a cationic emulsion as the binder
in the tack coat and penetration sprays. A slurry seal was applied
which filled all the voids in the 13 mm single seal. This was dragged
with a hessian drag and rolled. The final result was sound and uniform
and the seal was found to be user-friendly for labour-based work.
A Cape seal is a strong, tough seal and could well be used on bus
routes and on more heavily trafficked roads.
- Slurry seal
10mm slurry (wet) was applied, using a medium-graded aggregate
and a stable grade anionic emulsion.10 mm steel guide rails were
used to ensure consistent application of the 10 mm slurry.
Any high spots on the base were rectified by hand chipping to ensure
that the required thickness of slurry was obtained. The final result
was sound and uniform and the process was found to be user-friendly
for labour-intensive work. Before the slurry was applied, the surface
was cleaned and treated with diluted emulsion in the ratio of 1
part of emulsion to 10 of water.
In all cases where binder was sprayed on the road, a motorised
hand sprayer was used.
Before any spraying could be done, it was necessary to establish
the delivery rate of the spray pump. The rate of application of
the binder was then controlled to within 10% using an enlarged manually-operated
clock, controlled by the second hand of a wrist watch. By using
emulsion, any errors in nett residual binder sprayed were reduced
by some 35 to 40%.
Acknowledgements
A number of participants from the public and private sector contributed
financially, either directly or indirectly, to the pilot project
and to the production of the manuals. These included:
- The Division of Roads and Transport Technology, CSIR;
- The SADOT Technology Transfer Centre;
- The Phuthaditjhaba Town Council;
- The Free State Roads and Public Works Department;
- Blue Circle Cement;
- A.J. Broom Road Products (Pty.) Ltd.;
- Quickfix Manufacturing;
- The Southern African Bitumen and Tar association (SABITA);
- TOSAS;
- V.I. Instruments.
Their support and encouragement is gratefully acknowledged.
Highway
Maintenance Management
Eng. B. K. Yanney, [BSc(Eng)Lon, MSc, CEng, MICE, MZweIE], Department
of Civil Engineering, University of Zimbabwe, Harare, Zimbabwe
Summary
The paper emphasises the importance of timely and scrupulous maintenance
of highways and discusses some of direct consequences of failure
to follow the normal maintenance procedure. The paper analyses typical
routine and recurrent maintenance activities and shows how the critical
path method can be used to model such projects.
Introduction
Every construction project has distinct stages which collectively
constitute the project cycle. Some of these stages are identification,
designing, tendering, construction, commissioning and maintenance.
At the identification stage, the field technical personnel collect
and study details of prospective projects and come up with projects
which are economically viable. Therefore, projects with high benefit/cost
ratios are short listed for designs to be produced. The projects
then go for tender, when successful contractors enter into contract
to execute them. The completed project is finally commissioned for
use. At the commissioning stage, the future performance of the project
is evaluated and the strategy for maintenance and repair is considered.
Each phase of the project cycle is important. If, for example, the
construction process has not been properly supervised and sub-standard
materials have been used, the project may not last its design life
no matter how good the subsequent maintenance strategy. The Overseas
Unit of Transport and Road Research Laboratory has (1981) classified
the three main functions of highway maintenance as follows:
- To reduce the rate of deterioration and thus prolong its life.
- To lower the costs of operating vehicles on the road by providing
good running surfaces.
Highway maintenance therefore basically serves to improve the flow
of traffic, conserves the assets represented by the roads, promotes
the safety and comfort of road users, and preserves the aesthetic
appearance of the roads. Failure to carry out regular maintenance
of the road results not only in premature deterioration of the facilities,
accident rates are also likely to increase drastically.
Maintenance Activities
Maintenance activities consist of routine, recurrent and periodic
activities. Routine maintenance activities are those operations
that will be required whatever the engineering characteristics of
the road or the density of traffic it carries. Routine maintenance
activities include grass-cutting, drain clearing, re-cutting ditches,
culvert maintenance, bridge maintenance and road signs maintenance.
The recurrent activities may be carried out at intervals throughout
the year; the frequency depends upon the volume of traffic using
the highway. Some typical recurrent activities are pothole patching,
surface repairs, edge repairs, sealing cracks and road surface marking.
Periodic maintenance activities may include regravelling (for unpaved
roads) and surface dressing/resealing (for paved roads). These activities
are needed after intervals of several years.
Robinson (1988) has given suitable definitions for some common
terms such as upgrading, stage construction and rehabilitation.
Upgrading aims at providing additional capacity when a road is nearing
the end of its design life or because there has been an unforeseen
change in use of the road. Typical examples of upgrading projects
are the paving of gravel roads, the provision of strengthening overlays
for paved roads and the widening of roads. Stage construction consists
of planned improvements to the initial pavement standards of a road
at pre-determined stages throughout the project life. Stage construction
differs from upgrading in that any later improvements are planned
from the onset. Rehabilitation is needed if the road has deteriorated
beyond the condition at which overlaying is a satisfactory engineering
alternative. This is the normal result where the road has not received
sufficient maintenance. Reconstruction to provide a new alignment
should be considered as an upgrading project.
Economics of Maintenance activities
Roads will continue to deteriorate with time, even with adequate
maintenance, until the design has elapsed, when the need for strengthening
overlay or reconstruction becomes necessary. The need for efficient
and regular maintenance operations become obvious if the data contained
in Table 1 is critically examined:
Table 1: Cost of maintenance activities
|
Maintenance activity
|
Cost US$/km
|
|
|
Paved
|
Unpaved
|
|
Routine and recurrent maintenance
|
500
|
1,000
|
|
Periodic reseal (after 5 years)
|
12,000
|
--
|
|
Overlay (after 10 years)
|
42,000
|
--
|
|
Regravelling
|
--
|
8,000
|
|
Reconstruction
|
175,000
|
45,000
|
|
Annual maintenance cost (undiscounted apportioned over
10 years)
|
6,000
|
2,500
|
|
New construction
|
250,000
|
120,000
|
Source: Faiz and Harral (1987)
If the required routine and recurrent maintenance activities are
not carried out, drainage will be ineffective and surface defects
will worsen, thereby resulting in water penetrating into the pavement
structure. For a paved road, the consequences of the neglected maintenance
activity will prematurely cause the need for a periodic maintenance
which (from Table 1) will cost approximately 24 times more than
the normal routine/recurrent maintenance operation. If the periodic
maintenance activity is also delayed, a major upgrading activity
(overlay) which is about three times more expensive than the periodic
maintenance operation, soon becomes necessary. In the case of most
developing countries, the problem is twofold: while the maintenance
funds are insufficient, the bulk of the funds is diverted and spent
instead on new construction. Maintenance operations cannot therefore
be stretched to cover all the road networks.
Maintenance Management Procedure
A typical maintenance management procedure may consist of the following
process (Robinson 1986, Robinson 1988): (i) inventory, (ii) inspection,
(iii) maintenance needs, (iv) costing, (v) priorities, (vi) execution
and (vii) monitoring. The inventory process establishes the basic
reference for planning and carrying out maintenance and inspections.
Since funds are not sufficient to cover all the road networks, it
is necessary to establish priorities in order to determine which
should be undertaken and which should be deferred.
The road should be inspected during the dry season and also during
the wet season. The main purpose of the inspection is to identify
the causes of defects so that maintenance operations can be planned
to remedy them. The frequency and extent of carriageway and shoulder
maintenance are closely related to the nature and volume of traffic
on the road. A knowledge of traffic loadings will not only indicate
which roads are likely to deteriorate most quickly but will also
assist in establishing priorities. Therefore traffic counts should
be undertaken to provide an estimate of annual average daily traffic
(ADT).
Direct Labour/Contract Works
Maintenance activities must be properly planned so that they can
be completed on schedule. Critical path method provides one method
for modelling projects. The method may be outlined as follows:
- Determine sequence of operations and activities that may be
executed simultaneously, e.g., materials ordered must arrive before
repair activities can start.
- Determine the duration of activities. By using performance standards
(Overseas Road Note 1, Table 8) and suitable allocation of resources
e.g., labour, equipment etc., the duration of each activity can
be determined.
- `Forward Pass' determines the Earliest Event Times while
- `Backward Pass' determines the Latest Event Times. (see Figure
1.)
- The `floats' have been determined and tabulated in Table 1.
Float indicates the range within which the start and finish times
of an activity may vary without affecting the completion time
of the project.
References
Robinson R. 1988. A view of road maintenance economics policy
and management in developing countries. TRRL Research Report
145, Transport and Road Research Laboratory, Crowthorne
Transport and Road Research Laboratory (1983). Maintenance management
for District Engineers. Overseas Road Note 1, Transport and
Road Research Laboratory, Crowthorne.
Transport and Road Research Laboratory (1985). Maintenance techniques
for District Engineers.'(Second Edition). Overseas Road Note
2, Transport and Road Research Laboratory, Crowthorne.
Yanney, B. K. 1990. Techniques for maintenance cost estimation.
Paper delivered at a course on Mass Transportation Planning and
Management organised by the Nigerian Institute of Transport Technology,
N.I.T.T. in Zaria, September, 1990.
Table 1: Analysis of network diagram: Highway maintenance
|
|
|
Earliest event times
|
Latest event times
|
Floats
|
|
|
Activity
|
Duration
(days)
|
Start
|
Finish
|
Start
|
Finish
|
Total
|
Free
|
Remarks
|
|
1 - 3
|
14
|
0
|
14
|
0
|
14
|
0
|
0
|
Critical
|
|
3 - 5
|
7
|
14
|
21
|
14
|
21
|
0
|
0
|
Critical
|
|
5 - 7
|
7
|
21
|
28
|
21
|
28
|
0
|
0
|
Critical
|
|
7 - 10
|
15
|
28
|
43
|
28
|
43
|
0
|
0
|
Critical
|
|
10 - 11
|
10
|
43
|
53
|
43
|
53
|
0
|
0
|
Critical
|
|
11 - 12
|
7
|
53
|
60
|
53
|
60
|
0
|
0
|
Critical
|
|
1 - 2
|
10
|
0
|
10
|
0
|
14
|
4
|
4
|
Non
Critical
|
|
2 - 6
|
10
|
10
|
20
|
18
|
28
|
8
|
4
|
Non
Critical
|
|
1 - 4
|
10
|
0
|
10
|
11
|
21
|
11
|
11
|
Non Critical
|
|
4 - 8
|
14
|
10
|
24
|
21
|
35
|
11
|
0
|
Non Critical
|
|
8 - 9
|
8
|
24
|
32
|
35
|
43
|
11
|
0
|
Non Critical
|
Notes:
- Total Float = Latest Date - Earliest Date - Job Duration
(event B) (event A) (activity A-B)
- Free Float = Latest Date - Latest Date - Job Duration
(event B) (event A) (activity A-B)
- Critical activities have no float while non-critical activities
have floats.
Management
of Some Selected Labour-based Highway Construction Activities
Eng. B. K. Yanney, Department of Civil Engineering, University
Of Zimbabwe, Harare, Zimbabwe
Summary
The is paper discusses some of the ideal conditions which make
a labour-based method of construction an acceptable option. A typical
highway construction project is analysed in order to determine its
component activities and their sequential relationships. The activities
are then critically examined; those which may be executed by plant-intensive
operations are separated from those which are best executed by labour-based
methods under the local conditions. Simple methods of developing
and analysing network diagrams are illustrated. Examples of methods
of applying labour constants for construction activities are given.
The need for using realistic labour constants is emphasised.
Introduction
Highway construction activities tend to be highly plant-intensive.
Plant-intensive methods of construction can be effectively controlled
so as to increase the outputs in order to reduce the project construction
duration. Plant requirements for a highway project depend upon the
size, type and location of the project. While a number of items
of sophisticated equipment will be needed for the construction of
an urban motorway, or an airport with a rigid pavement, very little
equipment will be required for the construction of a secondary or
feeder road, which will normally be designed to meet the requirements
of low-volume roads in most developing countries. Labour-based methods
of construction can still be introduced to reduce further the level
of plant requirement. Most developing countries face severe shortages
of foreign exchange, which is needed for the importation of construction
equipment.
At the same time, unemployment is a major national issue. It is
therefore safe to conclude that a possible solution to these problems
would be to train some of the rural folk (who constitute over 60%
of the population in most cases) to participate in labour-based
construction activities. While conserving scarce foreign exchange,
the problem of unemployment will also be redressed.
Planning, organising, directing, co-ordinating and controlling
are some of the most important management functions. At the planning
stage, the project manager literally breaks the project up into
minute details in an attempt to identify all the activities that
must be executed in order to complete the project. The sequence
of operations and the inter-relationships between activities must
also be determined. The `directing' function is concerned with training
sub-ordinates to carry out assigned tasks, supervising their work
and guiding their efforts. Workers must
be motivated individually and as groups to utilise their creative
efforts in achieving specified objectives. The manager co-ordinates
by ensuring that all facilities and individuals sustain and reinforce
each other. This requires an efficient system of communication so
that each department and section is aware of its role and the assistance
to be expected from others. Control involves a constant review of
the programme of work in order to check on actual achievements and
to rectify if necessary any deviations by applying the necessary
corrective measures.
The manager arranges regular site meetings to be attended by all
senior supervisory staff and sectional leaders. At such meetings,
the quantity surveyor submits a report on the monthly measurements
of work executed. The project accountant also submits the site cost
sheet with a summary of how much has been spent by each section
on plant, labour, materials and other incidental expenses (e.g.
petty cash). Under such circumstances, a meaningful discussion of
unsatisfactory progress and over-expenditure will be made at the
regular site meetings.
The programme of work is one of the manager's most important tools
for controlling the progress of work. It must therefore be prepared
with great caution. If possible most of the senior section leaders
must be involved in its preparation at the very onset. Scheduling
is an important stage in the preparation of a working programme.
It is a process of fitting the working plan to a time format indicating
the start and finish of each activity. At the scheduling stage of
a labour-based construction activity, the manager first provides
materials that will be needed (including tools if necessary) and
then proceeds to assign labour (e.g. labourers, masons, carpenters,
steel-benders etc.) needed to complete the activity within an acceptable
duration. The use of realistic labour constants is the key to successful
management of labour-based methods of construction. Where labour
constants are not available, works study, work measurements etc
may be used to provide the required data for a project in a specified
location.
Works Study
The main purpose of a works study is to discover what time and
effort can be saved and made available for other works. Such studies
enable existing abilities in an organisation to be matched more
carefully with the requirements of specified jobs so that faulty
relationships between individuals and work can be rectified. Work
measurement, another closely related technique, aims at establishing
the time for a qualified worker to carry out a specified job at
a defined level of performance. Work measurement helps in comparing
times for alternative methods, and allocation of labour to jobs
in proportion to the work involved so that an appropriate balance
of labour is maintained. The procedure for carrying out work measurement
may be outlined as follows:
- Select and define the work to be studied.
- Record all relevant facts of the present method by means of
charts diagrams and models.
- Examine the facts critically and in sequence.
- Develop the most effective method of doing the work.
- Maintain regular routine checks for the procedure under investigation
until it can be established as standard practice.
The Project Planning and Control Division of Ghana's State Construction
Corporation (SCC) adopted the works study principles outlined above
in establishing labour outputs which have now been approved by the
Executives and Workers' Union of the corporation. The labour output
document, first produced in 1970 and subsequently amended and approved
in 1977, forms the basis for assessing acceptable output from each
category of worker. It is also used for establishing taskwork and
payment of bonus or incentives.
Labour Constants
The labour constant is a figure which tells how many work-days
are spent per unit of work. For example, Appendix A (Table 1) shows
that one labourer will excavate 3.82 cubic metres in medium soil
per day of eight hours. The labour constant works out to:
1 work-day = 0.26 work-day per cu. m.
3.82 cu. m.
If, on the other hand, the excavation had been stony soil one labourer
would be expected to excavate only 1.91 cu. metres in the same period
and the labour constant would be:
1 work-day = 0.52 work-day per cu. m.
1.91 cu. m.
(Please note: The lower the output the higher, the labour constant).
Assume that the base of a culvert or the foundation of a bridge
is to be concreted. The following procedure has been found to be
effective:
- Determine the volume of concrete required from the drawings
and/or bill of quantities. Check from the specifications of to
ascertain the class of concrete. In this case, the recommended
mix of proportions by volume is 1:2:4 .
- Using, table 2 (Appendix A) determine the quantities of materials
needed for the concrete works. For example, if 35 cubic metres
of concrete (1:2:4 class) will be needed, then 224 bags of cement,
16 cu. metres of fine aggregates (sand) and 32 cubic metres of
coarse aggregates will be needed. These quantities may be increased
by about 5% to allow for waste.
- Provide a good concrete mixer and preferably one that can hold
one bag of cement and the aggregates. A stand-by mixer may be
arranged.
- Prepare gauge boxes, at least one for sand and two for the coarse
aggregates. Each gauge box must be designed such that its volume
is equal to the volume of one bag of cement. A gauge box of dimensions
300 mm x 300 mm x 390 mm i.e. volume 0.035 cu. metres will be
acceptable.
- The labour force for the concreting operation may consist of:
- one labourer (loading cement)
- two labourers (loading sand)
- four labourers (loading coarse aggregates)
- one mason (receiving concrete)
- two labourers (transporting concrete)
- one labourer (adding water)
- one concrete mixer operator
- one gang leader
The labour force for the concreting operation adds up then to 13.
Table 3 (Appendix A) shows that the average output for this activity
(item 2) is 2.7 cubic metres per worker. The expected output per
day is 13 x 2.7 = 35 cubic metres. Therefore, the concreting operation
can be finished in a day. The concreting operation may then be given
out to the selected workers as taskwork (sometimes referred to as
"finish and go") i.e. the piece of work is given out to the workers
to be completed in a day. The workers are free to go home any time
the work is completed. Output can be drastically improved if the
concrete mixer and the aggregates are brought as close as possible
to the culvert/bridges site. Batching concrete by volume presupposes
that the sand is dry. Wet or moist sand can bulk by about 20%. Therefore,
if moist sand is used, the volume of sand should be increased by
about 20% to allow for bulking. It may be desirable to carry out
a sand bulking test to determine the exact value. Quality control
measures must be enforced during labour-based concreting operations.
Slump tests must be carried out before commencement and during the
concreting process to ensure consistency of water/cement ratio.
Test cubes must be prepared during the concreting operations. In
this example, the gauge box is designed such that the mix proportions
by volume are:
- One bag of cement
- Two boxes of sand
- Four boxes of coarse aggregates
The supervisor must ensure that the exact quantities of fine and
coarse aggregates are added during each mixing operation. Workers
normally easily get carried away by enthusiasm during concrete works
under taskwork basis.
Arrow Diagram for Highway Construction Project
Major questions that must be answered before an attempt is made
to develop a network diagram for the highway construction project
are as follows:
- What are the activities that must be executed in order to complete
the project?
- How is each activity going to be executed?
- What resources must be allocated to each activity so that it
may be completed within an acceptable duration?
- What is the most acceptable sequence of operations?
The answer to question (1) calls for a complete breakdown of the
project into distinct activities. Some of the most popular activities
for a highway construction project consist of:
- Excavation for culverts and bridges.
- Formwork.
- Cutting, bending and fixing reinforcement.
- Concrete works (culverts and bridges).
- Earthmoving operations.
- Pavement construction and surfacing
To answer question (2) one has to examine the availability of local
labour and the type of highway design. In the case of the road bridge
with cantilever abutments on spread foundations, the excavation,
formwork, reinforcement placing, and concrete works may be planned
for execution by labour-based methods. Plant-intensive operations
in bridge construction may be restricted to piling works, and the
launching pre-cast, pre-stressed bridge beams. Earth-moving operations,
pavement construction and surfacing may also be executed by plant-intensive
methods. Surface dressing, which is very popular with low-cost roads,
can be planned for execution by labour-based methods.
Resource allocation is an important phase in the planning strategy.
The main resources to be utilised for construction are plant, labour,
materials and finance. Plant must be bought or rented for use only
when it is absolutely necessary. Indiscriminate use of plant could
wipe out the entire profit margin. The same goes for labour. Workers,
on recruitment, are the best friends of management. Relations turn
sour when the project is about to be completed and lay-offs become
imminent. Therefore, if possible, efforts must be made to retain
just enough workers to maintain steady progress on the project.
Local labour could then be brought in to complete some items of
work when the need arises. The sequence of operations must be carefully
examined. Although progress can be drastically improved by executing
simultaneously as many activities as possible, this strategy must
be attempted only when resources are adequate to meet the demand.
Analysis of Network Diagram
The network diagram for the highway construction project has been
developed and analysed as shown in Fig.1 (Appendix B). The normal
procedure for analysing networks has been followed viz.:
- The Earliest Event Times have been determined by the `Forward
Pass' method while the Latest Event Times have been determined
by the `Backward Pass' method.
- Critical activities are those activities whose Earliest Start
Times (EST) and Latest Start Times (LST) are the same or
the Earliest Finish Times (EFT) and Latest Finish Times (LFT)
are the same.
- Floats in all the activities have been calculated in Table 1
(Appendix B). Float indicates the range within which the start
and finish times of an activity may be delayed without affecting
the completion time of the activity.
- Eight out of the 15 activities are critical. The project manager
must therefore strive to ensure that these critical activities
receive utmost attention.
Conclusion
- Labour-based methods of construction should be encouraged. Therefore,
large construction corporations must sponsor studies in these
areas.
- The use of realistic labour constants, prior consultation with
workers, and motivation are some strategies which promote productivity.
- It is being argued that labour-based methods suffer from quality
deficiencies. Therefore quality measures must be strictly enforced.
Acknowledgements
The author would like to thank the Managing Director of Ghana's
State Construction Corporation for granting permission for the use
of the Corporation's Labour Output Document.
References
Yanney, B. K. 1988. Technique for maintenance cost estimation.
Paper delivered at course on Mass transportation planning and management
organised by the Nigerian Institute of Transport Technology N.I.T.T.
Zaria, Nigeria.
Yanney, B. K. 1989. Project programming. Paper delivered
at a workshop organised by Nigerian Institute of Transport Technology
N.I.T.T., Zaria, Nigeria.
Appendix A
Table 1: Labour output: Manual excavation, filling and compaction
|
Item
|
Description
|
Output 8 hrs/day
|
Unit
|
|
1
2
3
4
5
6
7
8
9
10
11
|
Excavation in soft soil
Excavation in sand
Excavation in medium soil
Excavation in hard laterite
Excavation in stony area
Backfilling
Backfilling and compacting
Trimming sides of foundations and trenches
Load material and cart away
Hard core filling (200 mm)
Hard core filling (150 mm)
|
5.35
9.17
3.82
2.68
1.91
8.41
4.20
18.28
3.20
5.94
9.14
|
C/M
"
"
"
"
"
"
L.M
"
"
"
|
Table 2: Materials required for one cubic metre of concrete
|
Mix proportions
|
Cement
|
Sand m3
|
Aggregates m3
|
|
Weight (kg)
|
No. of bags
|
|
|
|
1:1:2
1:1½:3
1:2:4
1:2½:5
1:3:6
1:4:8
|
530
410
320
260
225
170
|
10.6
8.2
6.4
5.2
4.5
3.4
|
0.34
0.43
0.45
0.46
0.47
0.48
|
0.74
0.86
0.90
0.92
0.94
0.92
|
Source: Labour output document of SCC Ghana
Table 3: Labour output: Concrete works
|
Item
|
Description
|
Output
8 hrs
|
Unit m3
|
|
1
2
3
4
5
6
7
8
9
10
11
12
13
14
|
Casting plan in-situ blinding
Casting concrete in foundation 1 m - 2 m deep
Casting concrete in foundation 2 m - 3 m deep
Casting concrete in beams
Casting concrete in column base
Casting concrete in columns
Casting concrete in ground floor slab
Casting concrete in other floors
Casting concrete in beams at floor level
Casting concrete walls in ground floor
Casting concrete in lintels
Casting concrete in staircase
Casting concrete in roof slab (with hoist)
Casting concrete in roof slab (without hoist)
|
2.7
2.7
2.7
2.3
3.8
3.1
3.4
2.3
1.9
2.3
3.8
1.5
1.9
1.1
|
m3
"
"
"
"
"
"
"
"
"
"
"
"
|
Note
(a) Output is for each worker for 8 hours
(b) Workers for the compacting operation include
- Workers feeding concrete mixer
- Concrete mixer operator
- Dumper operator
- Other workers laying and compacting concrete.
Source: Labour output document of SCC, Ghana
Appendix B
Analysis of network diagram: Highway Construction Project
Table 1
|
|
Earliest times
|
Latest times
|
Floats
|
|
|
Activity
|
Duration
(days)
|
Start
(EST)
|
Finish
(EFT)
|
Start
(LST)
|
Finish
(LFT)
|
Total
|
Free
|
Remarks
|
|
1 - 2
|
14
|
0
|
14
|
0
|
14
|
0
|
0
|
Critical
|
|
2 - 3
|
9
|
14
|
23
|
14
|
23
|
0
|
0
|
Critical
|
|
3 - 5
|
13
|
23
|
36
|
23
|
36
|
0
|
0
|
Critical
|
|
5 - 8
|
29
|
36
|
65
|
36
|
65
|
0
|
0
|
Critical
|
|
8 - 11
|
14
|
65
|
79
|
65
|
79
|
0
|
0
|
Critical
|
|
11 - 12
|
14
|
79
|
93
|
79
|
93
|
0
|
0
|
Critical
|
|
12 - 13
|
15
|
93
|
108
|
93
|
108
|
0
|
0
|
Critical
|
|
13 - 14
|
14
|
108
|
122
|
108
|
122
|
0
|
0
|
Critical
|
|
2 - 4
|
8
|
14
|
22
|
28
|
36
|
14
|
14
|
Non Critical
|
|
3 - 7
|
5
|
23
|
36
|
62
|
67
|
39
|
39
|
Non Critical
|
|
7 - 9
|
5
|
36
|
41
|
67
|
72
|
31
|
0
|
Non Critical
|
|
9 - 11
|
7
|
41
|
79
|
72
|
79
|
31
|
0
|
Non Critical
|
|
3 - 6
|
50
|
23
|
73
|
24
|
74
|
1
|
1
|
Non Critical
|
|
6 - 10
|
14
|
73
|
87
|
74
|
88
|
1
|
0
|
Non Critical
|
|
10 - 13
|
20
|
87
|
108
|
88
|
108
|
1
|
0
|
Non Critical
|
Notes:
- EST = Earliest Start Time; LST = Latest Start Time
- EFT = Earliest Finish Time; LFT = Latest Finish Time
- Total float is the maximum time an activity can be delayed without
affecting the completion time of the project.
- Free float is the excess of available time over the activity
duration assuming that the activity under consideration and all
succeeding activities start at the earliest possible time.
|