|
Regional Seminar Papers 1997
Equipping contractors and projects
Choice
of Haulage Equipment for Labour-based Road works
Bruno Illi and Walter Illi, Norconsult, P. O. Box 48176, Nairobi,
Kenya. Email: norcon@form-net.com
Introduction
Discussions on the most suitable type of haulage equipment are
perhaps as old as labour-based rural roads programmes themselves.
The extent of possible options ranges from moving material on head-baskets,
wheelbarrows, animal drawn carts, tractor/trailer combinations to
the haulage of gravel by flatbed or tipper trucks. It is felt that
these debates are often based on personal beliefs rather than on
actual facts valid for specific and current project situation.
This paper therefore highlights factors to be considered when selecting
haulage equipment based on sound economic reasoning. Particular
emphasis is given to issues for which circumstances might have changed
over the years. Conclusions made are based on present conditions
and are applicable to a number of African countries including Uganda,
Tanzania, Kenya and Zambia.
Haulage as a Component of Total Construction
Costs
Although a project might be "labour-based", equipment-based material
haulage is often the most expensive component of the total construction
costs. The pie charts in Figure 2.1 illustrate typical expenditure
patterns for sample roads from the Zambian Feeder Roads Project
(FRP), Eastern Province, and some re-gravelling projects completed
under the SIDA funded Minor Roads Project (MRP) contractor training
programme in Central Province, Kenya.
Figure 2.1: Construction cost components

The diagrams clearly indicate the importance of the haulage component
in the final costs of labour-based road works. In addition, drainage
structures and compaction will also involve some haulage equipment,
in particular for transporting construction materials to site (culverts,
cement, sand, aggregates, etc.) and for watering. The cost breakdown
is based on contract documents prepared by Norconsult for the two
projects. This analysis was simplified by the fact that Bills of
Quantities were initially set up as bills summarising items according
to their common input requirements as follows:
- Labour
- Equipment
- Materials
Table 2.1 provides further background information on road standards,
equipment type, organisational set up and quantity of work for key
items.
Table 2.1: Background data for sample projects
|
|
Unit
|
FRP, Eastern Province Zambia
|
MRP, Kenya
|
|
Number of contracts
|
No.
|
8
|
7
|
|
Total length of sample roads
|
km
|
43.2
|
24.6
|
|
Average width of carriageway
|
m
|
4.80
|
4.70
|
|
Earthwork quantities
|
m3 / km (in situ)
|
370
|
50
|
|
Side drain quantities
|
m3 / km (in situ)
|
710
|
350
|
|
Number of culvert lines installed
|
(lines / km)
|
1.7
|
4.1
|
|
Gavel volume
|
m3 / km (loose)
|
520
|
800
|
|
Total gravel haulage
|
m3 x km (loose)
|
38,300
|
206,300
|
|
Average gravel haulage distance
|
km
|
1.7
|
10.5
|
|
Contract award
|
|
fixed rate
|
selected tender
|
|
Haulage equipment
|
|
tractor / trailer
|
trucks
|
|
Equipment leased through project:
|
60 hp tractors
|
2
|
none
|
|
|
trailers 2.8 m3
|
3
|
none
|
|
Annual interest rate
|
|
12% (project)
|
25% (market)
|
|
Average total construction costs
|
US$ / km
|
8,700
|
17,900
|
|
Average exchange rate
|
Local cur/US$
|
1,300
|
58
|
|
Price level
|
year
|
1997
|
1995/6
|
History of Equipment Choice for Labour-based
Rural Road works
Calculation of equipment hire rates
Many labour-based projects use a tractor-trailer combination to
haul material, since this is considered to be the cheapest and most
appropriate technology. Entire generations of labour-based practitioners,
planners and project designers have raised little objection to this
approach as it is very much in line with common donor policies.
These conclusions were predicated from a number of publications
and studies which were conducted on the topic in the mid seventies/early
eighties. The World Bank Guide for Labor-based Construction Programs,
first published in 1983, gave some valuable information on the issue.
Appendix G of the report provided a comprehensive method of calculating
costs and can be considered to be one of the best guidelines available
at the time.
The assumptions and work models employed by this method are recapitulated
in brief below:
- Equipment cost calculation was done using methods developed
for heavy earth moving plant. The procedure was based on a table
format which contained a number of predetermined calculation factors.
The final results were expressed as a "direct rate" or hourly
usage charge and did not differentiate between fixed and operating
cost. The method could be easily applied manually and did not
require computer access.
- Depreciation, capital recovery, maintenance, repairs, fuel,
lubricants, tyres, salvage value, road license and insurance were
the components considered in establishing the rates.
- Assumptions, among others, included economic life expressed
in 10,000 hours of total service, entire operating lives of 8-10
years depending on item and 1,000 - 1,250 hours average yearly
availability.
- Overhead cost, sales taxes, VAT and profits on the other hand
were not included in the World Bank cost calculation model.
- Most labour-based projects at that time were undertaken through
government departments, parastatals or specially created force
account units. Equipment owned and operated by governments directly,
tends to be under-utilised, which subsequently results in high
usage charges. Contributory factors to this low productivity could
be one or several of the following:
- Equipment stays idle due to cash flow problems or bureaucratic
procurement procedures resulting in fuel shortage, lack of spares,
tyres etc;
- Poorly equipped, staffed and managed government workshops provide
inadequate repair and maintenance services;
- Low civil service salaries result in poor staff motivation and
quality of work;
- Multipurpose equipment, e.g. tipper and flatbed trucks are diverted
to activities other than their intended use on labour-based projects.
The application of the World Bank calculation method resulted in
hourly usage rates as shown in Table 3.1.
Table 3.1: Hourly usage rates (Price level 1976)
|
Equipment
|
Specifications
|
Usage rate US$/hour
|
|
Flatbed truck
Tipper truck
Tractor
Tractor
Tipping trailer
Tipping trailer
|
6 m3 loading capacity
6 m3 loading capacity
35 hp
50 hp
1 m3 loading capacity
3.5 m3 loading capacity
|
5.3
6.9
2.3
3.1
0.5
0.6
|
Calculation of haulage rates
Hourly usage rates alone are not sufficient for cost comparisons
between different types of equipment. To achieve this, haulage rates
are calculated by use of the following formula:
Haulage Rate = A x B (US$/m2 x km)
C x D x E
Whereby:
A = Hourly usage rate (US$ / hr)
B = Number of working hours per day (hr/day)
C = Average haulage distance (km)
D = Loading capacity (m3/trip)
E = Number of trips per day (trips/day)
However, haulage rate is not a constant value. Transportation of
gravel over a distance of 1.0 km in 10 trips of 5 m3
each will be more expensive than if 5 m3 are to be moved
in one trip over a distance of 10 km even though the total haulage
of 50 m3xkm would in both cases be the same. For the
latter, only one loading/unloading operation will be required while
for the short 1.0 km distance the material is to be loaded/unloaded
ten times, thus necessitating much longer equipment waiting periods.
Haulage rates presented in Figure 3.3.1 are calculated using the
hire rates at price levels from 1976 as indicated in Table 3.1,
and on productivity assumptions and daily target trips given in
Table 3.2.1. and Table 3.2.2 below.
Table 3.2.1: Equipment productivity assumption
|
Equipment
|
Loading
time
(min)
|
Haulage
speed
(km/hr)
|
Off-loading
time
(min)
|
Return
speed
(km/hr)
|
Working
hours
(hr/day)
|
|
Flatbed truck
Tipper truck
Tractor 35 hp
Tractor 50 hp
|
30
36
5 a)
5 a)
|
35
35
17.5
20
|
20
5
5
5
|
45
45
22.5
25
|
7
7
7
7
|
It is assumed that tractors are equipped with two tipping trailers,
so the time requirement only involves the change of trailers.
Table 3.2.2: Daily target trips
|
Equipment
|
Daily target trips according to haulage distance
|
|
Distance (km)
|
<1
|
1-2
|
2-3
|
3-4
|
4-5
|
5-6
|
6-7
|
7-8
|
8-9
|
9-10
|
|
Flatbed truck
Tipper truck
Tractor 35 hp
Tractor 50 hp
|
8
10
32
33
|
8
9
22
23
|
7
9
17
18
|
7
8
13
15
|
7
8
11
12
|
6
7
10
11
|
6
7
9
9
|
6
7
8
8
|
6
6
7
8
|
5
6
6
7
|
|
Cycle time =
|
loading +
|
haul distance +
|
off-loading +
|
haul distance
|
|
|
haul speed
|
|
return speed
|
|
Daily target trips =
|
daily working hours
|
|
cycle time
|
Cost comparison of haulage rates between trucks and tractor / trailer
combinations at 1976 price levels
Haulage rates were then calculated using the information and assumptions
presented under sections 3.1 and 3.2. Comparison between different
types of equipment is best illustrated in the format of a line diagram.
Figure 3.3.1 provides haulage rates for flatbed trucks, tippers,
35hp and 50hp tractor/tipping-trailer combinations for haulage
distances between < 1 and 10 km.
Figure 3.3.1: Haulage rates for distances < 1 to 10 km at 1976
price levels

The diagram, prepared on 1976 price levels and assumptions, confirms
the following:
- The most economical option for material haulage up to a distance
of about 5 km appeared to be a combination of one 50 hp tractor
and two tipping trailers of 3.5 m3 loading capacity;
- No significant differences between haulage rates for tipper
and flatbed trucks could be observed;
- Combinations of one 35 hp tractor and two 1.0 m3 tipping
trailers were not economical;
- There was never a justifiable economical advantage of the tractor
/ trailer approach over trucks for haulage distances longer than
5 km.
Present Situation
New developments have undoubtedly taken place in the two decades
since the previously mentioned studies were carried out. It should
therefore be acceptable to look critically at various aspects of
haulage equipment choice in order to find solutions which will include
experiences from the past and reflect present situations in technical
and economical terms.
Haulage equipment technology
Uniform standard specifications of tractor/trailer combinations
suitable for labour-based roadworks do not exist. Information collected
from various projects, however, shows that the most common type
of equipment could be described as follow:
- 55-80 hp 2WD diesel engine powered agricultural tractors. A
few projects are also using 4WD tractors with engines as large
as 90 hp. The majority of models are fitted with hydraulic power
steering, braking and hitching systems;
- Single axle non-tipping trailers of less than 3.0 m3
loading capacity. Tyres mostly of size used for 7-tonne
trucks with a few models of balloon type or twin wheels;
- Purpose made gravel trailer designs including special heavy
duty towing eyes and hitching systems;
- Flatbed or tipper trucks according to ordinary country specification.
Loading capacity ranges from 5-6 m3 depending on make.
This summary reveals some significant differences from the assumptions
made in the early studies in terms of:
- Higher powered tractor engines;
- More sophisticated tractor technologies;
- Smaller trailer size;
- Non- viability of tipping trailer systems;
- Lifetime of some trailer models shorter than anticipated;
- Need for purpose built trailer designs and hitching methods.
The reason for use of larger engine size tractors is not clearly
established. It might be that the previously familiar 45 to 50 hp
machines were not powerful enough for the intended purpose, which
subsequently resulted in high running costs due to frequent breakdowns.
However, it is also to be considered that small engine sized agricultural
equipment has become increasingly rare on local markets. A number
of reputable tractor manufacturers offer their smallest models equipped
with engines of 60 hp or more.
The need for limitation of trailer loading capacity to 3.0 m3,
non-viability of tipping systems and requirement for special gravel
trailer designs, including necessity for heavy duty pick up hitches,
were all realised through more or less expensive trial and error
processes.
In particular, it has to be emphasised that all attempts at utilising
standard agricultural trailers have failed. Heavy duty gravel trailers
are manufactured in local workshops and their procurement entails:
- Engineering design;
- Manufacture, testing and approval of prototype trailer;
- Preparation of detailed drawings and tender specifications;
- Quality control during mass production; and
- Final inspection and approval.
Procurement of gravel trailers is a time consuming undertaking
compared with an "off the shelf" purchase of a truck or tractor.
In most cases, these activities are the responsibility of highly
qualified project staff. Acquisition of a small batch of trailers
can amount to a substantial proportion of the actual manufacturing
price. Expenses for procurement services are normally not added
to the purchase price and therefore not reflected in the cost comparison
between different haulage approaches.
Market environments
Economic viability of tractor / trailer haulage will always depend
on availability and price levels for conventional road transport
vehicles in a particular country. In the past, the alternatives
were often restricted through low competition among truck suppliers.
As recently as the mid eighties, a few manufacturers were holding
more or less a monopoly in many countries. In an increasingly liberalised
economy, these conditions are in the process of changing significantly.
These developments are best illustrated by comparison between equipment
procurement cost per m3 of haulage capacity in 1976 and
1997. Indicative figures from Kenya, Zambia and the World Bank Guide
reveal that costs for tractor/trailers have risen by 350%, while
the price increase for trucks has only been about 260%.
In addition, it is essential that a comparison is made of the true
value of the equipment. In many countries, different levels of import
duties and sales taxes are applied for tractor/trailers and trucks.
In 1995, for instance, the Ugandan Government charged 35% for trucks,
while the rate for tractors was as low as 2% because the latter
were classified as agricultural implements. Today, however, the
contractors in the Uganda Transport Rehabilitation Project/Feeder
Roads Component (UTRP/FRC) project will have to pay uniform rates
of about 24% for all types of equipment. Choice of technology based
on distorted market situations might not be sustainable and will
have negative long term effects.
Use of equipment for operations other than the intended gravel
haulage activities is another often brought up issue in the discussion
about the choice of technology. General lack of road transport capacities
is a common problem many government organisations are facing. Suitability
of equipment for multipurpose road transportation might therefore
not be desirable in a force account environment as it can easily
lead to vehicle misuse.
It is questionable as to whether the same criteria should be applied
to the private sector. Employment of small scale contractors at
their full capacity is a situation no client can ever guarantee.
It might therefore be a matter of the contractors' economic survival
to have alternative equipment utilisation opportunities in the event
of discontinuity in labour-based roadworks.
Pricing method
During project work planning, review of equipment procurement tenders
and preparation of contract documents, Norconsult was repeatedly
faced with the task of establishing accurate equipment costing figures.
Calculation methods had to consider that:
- pricing was to be done for a real market situation without equipment
leasing support;
- projects were carried out during periods of exceptionally high
currency exchange rate fluctuations.
The need for an efficient calculation procedure, allowing constant
updating of price levels, was therefore evident. It was also realised
that the objective could only be achieved by use of appropriate
computer spreadsheet programs. The chosen approach was based on
a separate estimation of fixed and operating costs:
|
Fixed cost:
|
Operating cost:
|
|
Interest
|
Fuel
|
|
Depreciation
|
Lubricants
|
|
Road license and insurance
|
Maintenance and repairs
|
|
Drivers' salary
|
Tyres
|
A key element in establishing reliable costing procedures is the
identification and definition of parameters. Tractors are commonly
equipped with hour clock meters while the mileage on trucks is normally
measured in km. It is therefore essential to formulate all required
inputs in the respective units for easy transfer from information
provided by the manufacturer or which is to be collected from utilisation
reports. In addition, we opted to express the productivity performance
in relation to actual cycle times by assumption of:
- Loading time (or changing time for tractor / trailer combinations);
- Travel speed of loaded haulage equipment from quarry to dumping
place;
- Off-loading time;
- Return speed of empty haulage equipment from dumping place to
quarry.
The required data are to be logged in a single input entry sheet.
An example of the chosen format appears in Table 4.3.1. Figures
and prices contained in the sheet do not refer to a particular project,
but they could be considered as a realistic guideline of assumptions
for counties including Uganda, Tanzania, Zambia and to some extent
also Kenya.

Cost comparison of haulage rates between trucks and tractor / trailer
Combinations at 1997 price levels
The data in Table 4.3.1 were the used in the preparation of an
updated line diagram for haulage rates at current price levels as
presented in Figure 4.4.1
Figure 4.4.1 Haulage rates for distances < 1 to 12 km at 1997
price level

Compared with the results presented in Figure 3.3.1, the updated
diagram reveals a clear shift of competitiveness from tractor /
trailers towards tipper and flatbed trucks.
Annual haulage capacities
The planner of a labour-based roadworks programme will, apart from
selecting the most suitable type of haulage equipment, also have
to decide on the size of required fleet. It is obvious that this
conclusion will depend to a great extent on haulage distances prevailing
in the project area. Figure 4.5.1 provides annual haulage capacities
per piece of equipment based on the assumptions presented in the
data log sheet in Table 4.3.1.
Figure 4.5.1: Annual haulage (in m3 / year )

Conclusions and Recommendations
The above analyses of developments in haulage technologies for
labour-based road works have been drawn together below to form a
number of conclusions and recommendations for future project planning:
- Analysis of technical options, work organisation and development
of price levels over the past 20 years reveals that some significant
changes have taken place over this period. Additional conditions
might also vary from country to country. An independent assessment
of the prevailing situation is considered an essential task to
be undertaken during the project planning stage and should include:
- Equipment investment cost(broken down in initial charges,
shipment and clearing, taxes and duty);
- Basic prices relevant for the establishment of equipment operating
costs e.g., fuel, lubricants and tyres;
- Assessment of expected haulage distances to be established
through gravel surveys in case information on material availability
in area is inadequate;
- Comparison of haulage rates between different types priced
on actual project conditions.
- Use of computer spreadsheet programmes for calculation of haulage
rates is recommended and is best achieved by separation of the
three main cost components:
- Fixed cost;
- Operating cost;
- Overhead and profit.
- Calculation should be based on actual equipment running times
according to haulage distance rather than on estimated annual
average utilisation. Cost parameters are to be expressed in a
format which allows easy reference to manufacturers' technical
data and performance reports.
- Conclusions made on choice of haulage equipment may reflect
the present situation in Uganda, Tanzania, Kenya and Zambia and
can be summarised in brief as follows:
- Early studies indicated an economic viability of material
haulage by tractor / tipping trailer combinations up to a haulage
distance of about 5 - 6 km;
- Review of costing methods and assumptions considering developments
over the last 20 years revealed almost equal costs for haulage
by trucks and tractor / non-tipping trailer combinations over
distances < 2.5 km, while trucks appear to be 50% more economical
for transports over a distance of more than 12 km;
- There is little evidence of successful use of tipping trailers.
The method is therefore considered as not viable.
- The highest possible output per equipment unit is achievable
by 7 - 8 tonne tipper trucks. Performance of flatbed or tractor
/ non-tipping trailer combinations ranges from 40% to 80% of the
tipper capacities.
Abbreviations
|
MRP
|
Minor Roads Programme
|
|
FRP
|
Feeder Roads Project
|
|
SIDA
|
Swedish International Development Co-operation Agency
|
|
UTRP/FRC
|
Uganda Transport Rehabilitation Project / Feeder Roads Component
|
References
Norconsult . 1997. Road rehabilitation and gravelling by labour-based
contractors: Contract document Volume I. Ministry of Local Government
& Housing, Zambia
Norconsult . 1997. Road rehabilitation and gravelling by labour-based
contractors: Contract document Volume II. Ministry of Local
Government & Housing, Zambia, 1997;
Coukis, Basil. 1983. Labor-based construction programs: A practical
guide for planning and management. World Bank
Norconsult . 1997. Road rehabilitation and gravelling by labour-based
contractors: Pricing guidelines. Ministry of Local Government
& Housing, Zambia
Equipment
for the DNEP/DFID Feeder Roads Project, Mozambique
R N Geddes, (Project Advisor, DNEP/DFID Feeder Roads Project,
Zambézia, Mozambique
Synopsis
This paper provides a general account of the equipment ordered
for the DNEP/DFID Feeder Roads Project in Zambézia Province,
Mozambique, and comments on the adequacy and performance of specific
items in the early stages of the project. An outline is provided
of the procurement process, and the measures taken for clearing
the equipment through Mozambique customs. Specific details of the
tractor/trailer combinations, and the choice of compaction equipment,
are discussed.
The objectives of the project include the rehabilitation of tertiary
roads in Zambézia Province, in order to improve the economic
and social prosperity of the local population, and the development
of capacity in the local road construction industry. Implementation
of the works is by emergent, small-scale local contractors who are
receiving training within the project.
The project is relatively equipment intensive compared with other
labour-based projects, and equipment costs account for about 25%
of the cost of the rehabilitated roads. The bulk of the equipment
has been provided for gravelling operations and for compaction.
This is appropriate considering the amount of gravelling that will
be required, and the generally poor quality of the in situ
soils. Adequate compaction at the roadbed preparation and formation
stages is essential.
An important aspect of the motivation and development of the contractors
is the opportunity to own equipment, and the project provides for
the transfer of ownership to the contractors.
The paper focuses on the primary equipment supplied for use on
the sites and does not include details of hand tools, mechanical
workshop tools, survey equipment, radios, computers, office supplies
and equipment, carpentry tools, air-conditioners and stand-by generators
also supplied to the project.
The description of faults and inadequacies of some items is not
meant as criticism of the suppliers, since the equipment is not
necessary specifically designed for use in labour-based road construction
in remote areas of Africa. The comments are provided to assist those
specifying equipment for similar projects in the future to predict
and avoid similar problems.
Background to the Project
The purpose of the DNEP/DFID Feeder Roads Project is to rehabilitate
approximately 800km of existing classified feeder roads in Zambézia
Province, Mozambique, in order to improve the economic and social
well being of the local population. The project is being implemented
by the Mozambique National Directorate of Roads and Bridges (DNEP)
through DEP Zambézia, the Provincial Department of Roads
and Bridges. Support to DNEP and DEP for the management of the project
is being provided by consultants.
The project is being funded by the British Government, through
the Department for International Development (DFID), for the purchase
of equipment, materials, works execution and payment to consultants.
In addition, DFID are funding upgrading of accommodation, some road
maintenance (within the project period) and UK/regional training.
The Government of Mozambique contribution includes the payment of
import duties, DEP supervision of the works, offices and housing
for the Consultants, and in-country training.
The project is part of DNEP's Feeder Roads Programme, which in
turn is part of the World Bank-supported Roads and Coastal Shipping
Project (ROCS) which seeks to ultimately rehabilitate the bulk of
the road network in Mozambique.
An important objective of the project is to develop local capacity
for the implementation of rehabilitation and maintenance works by
local private contractors using labour-based methods. To this extent,
the project is unique within the Feeder Roads Programme, which traditionally
operates direct labour brigades through the provincial ECMEPs (state
owned Enterprise for the Construction and Maintenance of Roads and
Bridges).
Preparations for the implementation of the project started in September
1995 in order to facilitate the commencement of site operations
after the 1995-1996 rains. The project completion date is 15 September
2000.
The selection of contractors to participate in the project was
made by the DNEP on the basis of recommendations from the Provincial
Directorate of Works (DPOPH). The criteria used to select the contractors
included: experience in construction; the calibre of staff employed;
equipment already owned; financial status and perceived entrepreneurial
ability.
By the end of July 1997, approximately 60 kilometres of road had
been rehabilitated to all-weather standard and 40 kilometres were
under routine maintenance. Six contractors are currently working
independently on different sites in Mocuba and Ilé districts
under the supervision of the Provincial Department of Roads and
Bridges (DEP), and with continued support from the consultants.
The roads are being rehabilitated to all-weather standard and significant
lengths are being gravelled due to the poor quality of the in
situ soils, which are fine grained and, in sandy areas, highly
erodible. In non-sandy areas, spot-gravelling is being carried out
on steep slopes and on stretches of particularly high plasticity.
It is anticipated that up to 50% of the total length of road rehabilitated
will require gravelling.
The Equipment List
The list of equipment prepared for the project was based on the
standard equipment list for the Feeder Roads Programme brigades.
Details of the principal items and comments on their performance
and suitability are given in Appendix A.
The quantity of items required was calculated on the assumption
that some contractors would develop larger operations than others,
and would therefore require, and be able to afford, more equipment.
The full purchase price of the equipment, including transport and
import duties, was used in the derivation of rental and hire-purchase
rates. Since these costs are significant, representing about one-quarter
of the average monthly turn-over, the contractors are discouraged
from having idle or under-utilised plant on site.
The contractors will be encouraged to purchase equipment in accordance
with their management capacity in order to avoid over-capitalisation
through the purchase of assets that may be surplus to their requirements.
Future work opportunities, beyond the end of the project , will
likely be confined to routine maintenance contracts.
Items of equipment that are not purchased by contractors will be
kept centrally and will be available for hire for the duration of
the project. At the end of the project, DNEP will either dispose
of the surplus equipment or continue to make it available for hire.
The unit rates used for the valuation of the contractor's work
are derived using the full purchase price of the equipment. The
contractors are therefore in a position to seek alternative, and
possibly cheaper sources of equipment. This approach is being encouraged
as it promotes self-reliance and allows the contractors to maximise
their profitability. One contractor has already purchased a new
tractor/trailer combination from the local Massey Ferguson agent,
and others are rehabilitating old tractors for deployment on site.
A 10 tonne flat-bed truck, owned by one of the contractors, has
been used in gravelling operations in tandem with tractor/trailer
combinations to boost output over long haul distances.
Procurement of Equipment
The procurement of equipment for use on the project is being done
by the consultants through an associated company. The payment of
import duty for the clearance of the goods is the responsibility
of the Government of Mozambique through the DNEP, who are the owners
of the equipment.
The equipment has been ordered in two main consignments in order
to reduce the risk of over-supply in the event that it would not
be possible to find enough contractors to participate in the project.
The equipment list was prepared by the consultants on the basis
of the requirements of the Project Appraisal and was approved by
DNEP and DFID in February 1996. The first orders were placed in
May 1996 and most of the equipment from the first consignment was
operational on site before the end of 1996. The preparation of documentation
for the importation of some items, such as the mechanic tools and
equipment, was delayed in Mozambique due to the large number of
items, and the complexity of the descriptions of the goods, which
had to be translated into Portuguese.
To date, all items for the first consignment have been received
in the port of Quelimane and have been cleared through customs for
use on site. The ordering and delivery of items from the second
consignment has commenced, in accordance with the site requirements,
and some items from the second consignment have been received.
The importation and clearance of the equipment has been initiated
and managed on behalf of DNEP by the consultant's project team based
in Quelimane. The key to the success of this involvement has been
the local recruitment of a Mozambican administrator with a thorough
knowledge of Quelimane, and some experience in dealing with the
various agencies involved in the process of importation. The decision
to manage the process at a local level has been critical to its
success, since most of the equipment has been delivered directly
to the port of Quelimane, some 1,600km from Maputo.
DNEP's involvement has included arrangements for the payment of
customs duties by the Ministry of Finance. DNEP's capacity for dealing
with large consignments of imported equipment is now well developed
following many years of experience, and the clearance of the goods
has been relatively trouble-free.
Project funds have been used for the payment for services provided
in Quelimane, such as the production of the import permits, port
charges, and the licensing and insuring of equipment following customs
clearance. This has been a considerable advantage in reducing delays
in the deployment of equipment on the sites.
Expenditure
The total expenditure on equipment to date is slightly less than
US$2,400,000, which represents about 74% of the budget provided.
A further US$300,000 has been committed in orders for the second
consignment. The equipment budget represents about one-quarter of
the total project budget.
Equipment Use and Maintenance
The equipment is owned by the DNEP who hire it to the contractors.
The hire rates have been calculated to reflect the true cost of
owning and operating equipment and include interest at a rate of
12% per annum. Payments are made by the contractors as deductions
from their monthly certificates.
The Project allows for the contractors to purchase items of equipment
in accordance with their requirements. DNEP are currently preparing
proposals to the Ministry of Finance for a hire purchase contract.
This will enable DNEP to transfer ownership to the contractors through
a series of hire purchase payments made over an appropriate time
period agreed by both parties.
Management of the equipment is the responsibility of the DEP Plant
Manager who is the counterpart to the consultant's Mechanical Technician.
The Plant Manager produces monthly invoices to each contractor for
equipment hired during the month.
Maintenance and repairs to the equipment are undertaken by mechanics
employed by the contractors with support and training from the consultant's
Mechanical Technician. Additional training is being provided by
DNEP through training courses held at the Training Centre in Chimoio.
Specific Comments About Tractor/Trailer Combinations
and Compaction
Tractor/trailer combinations
Labour-based works in Mozambique within the Feeder Roads Programme
(FRP) have been carried out using Massey Ferguson 240 (52HP) tractors
for several years and it was decided that MF240s should provide
the bulk of the tractors ordered for this project. FRP brigades
are also equipped with a four-wheel drive MF 390 (85 HP) tractor
which is used primarily to spread excavated material from the side-drains,
in the construction of the formation, using Arthur Garden towed
graders from Zimbabwe.
At the project inception, it was decided that spreading would be
done as an entirely labour-based activity, without the use of a
towed grader, so it was deemed unnecessary to provide 85 HP, four-wheel
drive tractors. Nevertheless, it was recognised that additional
power might be required for certain tasks: e.g. towing the water
bowsers out of deep river valleys, and MF275 (70HP) tractors were
included on the equipment list.
The tractor order is designed to equip each contractor with one
MF275 tractor and up to four MF240 tractors for large-scale gravelling
works. Contractors not undertaking gravelling find one MF275 tractor
to be adequate to deal with daily site transport requirements.
Experience to date indicates that the MF 240s have sufficient power
for most site activities, but severe problems have been experienced
on site with failure to the tow hitches.
The design of the 3mł Herculano trailer, with 20 inch wheels located
towards the rear of the trailer, results in the transfer of excessive
weight to the tractor and has resulted in the shearing of the bolts
fixing the tow-hitch to the tractor chassis. In some cases the tow-hitch
has broken. This problem is common to Feeder Roads Programme operations
in Mozambique.
The following measures are under consideration to remedy the situation:
- Modify the trailers to reduce their capacity and to move the
centre of gravity of the load further towards the rear of the
trailer.
- Move the trailer axle forward to reduce the load applied to
the tow hitch.
- Install heavy duty tow-hitches ("Natal Hitch").
- Provide smaller diameter wheels to reduce the inclination of
the trailer draw-bar onto the tractor tow-hitch.
- Encourage the contractors to provide easier access from the
borrow pits in order to reduce the dynamic stresses on the tow-hitches.
Compaction
The decision to use equipment for compaction was made at the time
of the project inception on the basis that equipment is generally
used for compaction by Feeder Roads Programme brigades, and in order
to achieve the planned output of rehabilitated road. The following
equipment has been supplied to facilitate this:
- Towed 2,275 litre water bowsers with spray-bars,
- Water pumps,
- Pedestrian rollers,
- Towed rollers,
- Additional tractors.
The decision to provide towed rollers was based on experience that
has shown pedestrian rollers to be unreliable in the long-term in
remote areas where service back-up facilities are not available.
It was anticipated that towed rollers would provide the contractors
with compaction capability well into the future, even if the vibrating
mechanisms on the rollers were no longer functional. The supply
of a pedestrian and a towed roller to the sites provides the contractors
with the capacity to undertake formation and gravelling works simultaneously.
The attainment of optimum moisture content is essential to ensure
that compaction is achieved. The water pumps and bowsers are therefore
a key factor in the site operations if maximum output is to be achieved
by the towed rollers. This is particularly important in the construction
of the road-bed and the formation.
The total cost of the equipment provided for the compaction will
be approximately US$650,000. The cost per kilometre of fully gravelled
road, in terms of the hire rates and operating costs, is about US$1,500.
The towed rollers are particularly expensive items.
IBIS, a Danish NGO operating in Zambézia, has been able
to achieve reasonable levels of compaction using hand-pulled dead-weight
rollers fabricated locally. Water is collected by tractor and trailer
in drums which are filled by hand with buckets from the nearest
river. The water is spread on the road with watering cans. This
method is clearly much cheaper than methods employing mechanical
equipment for watering and compaction but produces low output if
optimum moisture content is to be guaranteed. The roads rehabilitated
by IBIS are generally in areas of good soils, and relatively little
gravelling has been undertaken.
The alternative approach of simply allowing traffic to facilitate
compaction is not considered appropriate in Zambézia, because
the traffic levels on most tertiary roads are very low, particularly
during construction when the road may be impassable farther along.
Conclusion
The equipment specifications and quantities for the DNEP/DFID Feeder
Roads Project have been designed to enable the project to attain
its objectives in terms of output of rehabilitated road and the
development of capacity within the local road contractor industry.
The equipment specified is largely similar to equipment supplied
to brigades within the national Feeder Roads Programme, but the
quantities have been adjusted to meet the requirements of private
contractors.
The decision to utilise relatively large amounts of equipment on
the project is justified on the basis that high outputs of completed
road are required, and that there will be a high proportion of gravelling.
Bureaucratic delays in the ordering and delivery of equipment to
the sites have largely been overcome through prompt payment of import
duties by the DNEP, and proactive support by the consultants for
the management of the process. The availability of project funds
at a provincial level has been significant in facilitating the movement
of goods through Quelimane port and on to the sites.
The equipment is owned by DNEP who lease it to the contractors
at rates that reflect the full purchase price. The contractors will
ultimately have the opportunity to purchase items of equipment from
DNEP on the basis of a lease-hire agreement. The opportunity to
own equipment is a major motivator for the contractors, and provides
them with a means to invest in capital assets, which is essential
for the growth of a small business.
Most of the equipment has operated relatively trouble free in the
early phase of the project and the most significant problem faced
to date has been the failure of the tow hitches on the MF240 tractors,
which are inadequate to support the applied loading from the Herculano
trailers when fully laden with gravel. Various measures are under
consideration to remedy this situation. Modifications are also required
to the fuel filter configuration on the Lister engines supplied
with the Benford rollers.
Preventative maintenance systems are in place, and mechanics employed
by the contractors are undertaking the majority of the maintenance
and repairs under the supervision and control of the Mechanical
Technician employed by the Consultant.
It is anticipated that future studies of the equipment supplied
to the project will provide additional insights into the long term
durability of specific items. Interesting comparisons, such as the
differences in operation of the Herculano and Tinto trailers, will
be made. Further analysis will also detail the set of equipment
finally purchased by each contractor, and how this equipment contributes
to their business development.
Appendix A: Equipment
Specifications
|
Item
|
Description
|
Comments on performance
|
Approximate cost CIF Quelimane including
import duty
|
|
Tractors
|
Massey Ferguson MF240S
2 wheel-drive tractor
Perkins 3 cylinder A3/152S engine 52Horse
Power
|
Generally sufficient power for most tasks.
Unable to pull the towed roller up steep
gradients.
The tow hitch is inadequate for the loads
applied by the trailers, and virtually all have broken at
least once.
The indicator switches are of poor quality
and break easily.
A maximum of 6x27kg front weights should
be carried to prevent the weight frame from breaking.
The bolts fixing the tow hitch and front
weight frame should be tightened daily.
|
$18,300
|
|
|
Massey Ferguson MF275
2 wheel drive tractor
Perkins 4 cylinder A4-236 engine, 70Horse
Power
|
Sufficient power for all operations but is
unable to pull the towed roller up steep gradients.
The indicator switches are of poor quality
and break easily.
The oil bath air filters provided are easier
and cheaper to maintain than the paper element filters supplied
with the MF240s but may be less effective in cleaning the
air drawn into the engine.
|
$23,900
|
|
Trailers
|
Herculano heavy duty, non-tipping trailer
5 tonne (3mł) capacity, 20" wheels
|
The trailers are generally poorly finished.
The chassis is weak in the draw-bar area.
Reinforcement of trailer chassis is ongoing on site.
The jack stand mechanism is inadequate and
breaks easily.
Too much load is transferred to the tractor
resulting in broken tow hitches.
|
$4,200
|
|
|
Tinto heavy duty, non-tipping trailer
5 tonne (3mł) capacity, 20" wheels
|
Not yet operational on site.
|
$6,000
|
|
Towed fuel bowsers
|
3884 litre single axle bowser.
Steel tank with rotary discharge hand pump
complete with flow metre.
|
No specific problems have been encountered.
The jack is well designed and no failures
have been experienced.
|
$7,300
|
|
Towed water bowsers
|
2275 litre single axle bowser.
Steel tank, gravity fed dribble spray bar
|
It has been necessary to enlarge and increase
the number of holes in the spray bars.
|
$5,600
|
|
|
1137 litre single axle bowser.
Steel tank.
|
No specific problems have been encountered.
The jack is well designed and no failures
have been experienced.
|
$4,200
|
|
Towed rollers
|
PÖMA AH150 PTO driven vibratory roller
Total weight 2.8 tonnes
|
Little experience has been gained to date
since the rollers were recently supplied.
On steep gradients a 4-wheel-drive tractor
is required or the compaction must be done with the pedestrian
roller.
The drive shaft from the PTO must be maintained
(greased approximately every 3 hours of work).
|
$42,900
|
|
Pedestrian roller
|
Benford 2-75B double-drum pedestrian controlled
vibratory roller.
Lister/Petter TS1 single cylinder diesel
engine.
Operating weight 960kg, roll width 760mm
|
The engine configuration is apparently unable
to cope with vibration of the roller resulting in split fuel
tanks. This will be remedied by remounting the tanks on flexible
mountings.
The standard fuel filter mounted inside the
fuel tank is too small and breaks easily with vibration of
the roller, resulting in dirty fuel entering the injectors.
An alternative fuel filter configuration will be fitted by
the supplier's South African agent shortly.
Regular preventative maintenance to grease
the vibrating mechanisms is essential.
|
$9,500
|
|
Supervision vehicles
|
Land Rover Defender Pick-up.
300 Tdi engine, 380 gearbox.
|
The Land Rover Tdi pick-up is regarded as
the appropriate vehicle under the project conditions.
The full-time 4-wheel drive and coil spring
suspension provide relative comfort and safety.
Regular replacement of shock absorbers and
brake pads has been necessary due to very poor road conditions
and the poor quality of standard Land Rover spare parts supplied
(i.e. shock absorbers and brake pads).
Regular maintenance of items such as door
locks is essential.
|
$32,200
|
|
Cargo trucks
|
Leyland Daf Comet 12.13
7 tonne flat-bed truck
|
It is considered that the trucks specified
are probably too small and that a 10 tonne capacity truck
would provide better ground clearance and higher loads on
the poor roads.
The "Hiab" crane fitted to one flat-bed truck
has proved invaluable for loading goods.
The injector pump and injectors are very
sensitive to dirty fuel.
The tachometers supplied with the trucks
have proved invaluable to control the operation of the trucks.
|
$64,000
|
|
Self-propelled Diesel bowser
|
Leyland Daf Comet 12.13
7000 litre Whale diesel tanker
|
The bowser has been set up for European conditions
which in some circumstances has proved inappropriate: e.g.
the exhaust silencer is mounted underneath the engine at the
front of the vehicle, between the wheels, and is thus vulnerable
to damage from pot-holes.
The vehicle was not waxed or well prepared
for shipping and sea-air has caused corrosion in the electrical
system resulting in failure of the tachometer and the pump
safety switch. Corrosion has also occurred inside the tank
and to the seal around the measuring stick.
|
$81,000
|
|
Water pump
|
SLD Model SEP50 2"x 2" self-priming portable
pump.
Lister Petter ACI engine.
Max. capacity 500 litres per minute, max.
delivery head 16m.
|
No problems have been experienced.
|
$2,800
|
|
Motorcycles
|
Yamaha DT125-3TT3
|
Several minor accidents have occurred, mainly
due to the poor roads.
The size of the motorcycles is considered
appropriate but it may be preferable to provide a single seat
to prevent the carrying of a passenger. Damage has been caused
to the rear wheel rim when passing through deep pot-holes
on surfaced roads with a passenger.
|
$3,200
|
|
Concrete mixers
|
Winget 175T tilting drum 240/175 concrete
mixer.
Lister Petter LT1 diesel engine.
|
Damage has been caused through a Contractor
trying to tow the mixer behind a vehicle.
|
$4,200
|
|
Poker vibrators
|
FRP55 pendulum poker.
HD10 Lister Petter AC1 diesel engine.
|
No problems to date but little site experience
|
$2,000
|
|
Rock breaking equipment
|
Ingersol Rand portable compressor P130/WD/G.
Ingersol Rand Promaxx Breaker MX60.
Ingersol Rand JH40 Jackhammer.
|
No problems to date but little site experience
Specific training and supervision is required
of the operators
|
$21,800
|
Development
of an Approach to the Appraisal of Tools and Equipment for Labour-based
Technology in Road Works: Experience in Tanzania
Dr. P. F. C. Komba, Chief Engineer Rural Roads, Ministry of
Works, Tanzania and L. M. Kyombo, Senior Engineer, Appropriate Technology
Unit (ATU), Ministry of Works, Tanzania
Abstract
Labour based technology (LBT) in roads construction, rehabilitation
and maintenance has been practised in Tanzania for more than 18
years. Nearly half of the country has implemented LBT in road works
but acceptance and awareness levels are still low, despite of several
efforts to promote the technology. Development of the technology
at a national level has proved to have substantial social and economic
benefits. However, the expansion of this technology at a national
level should be accompanied by quantification of potential inputs
which include labour, tools and equipment at a sustainable level.
Efforts to promote of the technology in Tanzania have revealed
quite a number of deficiencies such as monitoring of quality of
tools and corresponding performance, cost analysis for tools and
equipment and monitoring of operational inputs and output levels
including their optimisation. Coupled with this, performance data
recording and keeping and co-ordination between implementers and
local tools manufacturers is required for quality improvement and
sustainability. Equipment consumes a significant portion (about
40%) of project costs but implementers have limited knowledge including
guidelines on selection and costing as well as, logical approach
towards optimisation of labour and equipment inputs for construction
output. The investigations conducted in Tanzania have revealed that
7 tonne tipper trucks deployed for haulage are a possible alternative
among common LBT haulage equipment.
The investigation has also developed logical relations on selection
criteria and costing approaches and has recommended these for use
as a basis for improvement of existing guidelines and establishment
of checklists. Further studies are needed on the establishment of
optimisation of labour and equipment operations to enhance competitive
performance of different types of equipment for haulage in labour
based technology.
Introduction
Background
Tanzania is one of the developing countries located in sub-Saharan
Africa. It is a large country covering an area of 883,749 km2
with an estimated population of 25.6 million, the majority live
in rural areas. The economy is based on agriculture with most of
the country's rural population subsisting on farming.
Like many other developing countries, Tanzania is faced with development
challenges, being poor and unable to afford full use of sophisticated
equipment ,it requires a more appropriate technology which will
make use of locally available and abundant resources to improve
the recorded income, social service delivery and provision of infrastructure
services such as roads. This is necessary to contribute to the improvement
of the rural economies and the quality of life.
Labour based technology involves the use of working systems that
optimise the labour content through a cost-effective combination
with the right tools and intermediate equipment. Efforts to promote
LBT in road works in Tanzania have been made for more than half
of the country and the technology is very much needed for quite
a bigger portion of the country. In execution of the Integrated
Roads Programme (IRP), the government decided to maximise the use
of local resources and hence encouraged an introduction and expansion
of the use of LBT wherever feasible. To promote the deployment of
LBT, an institution dealing with LBT issues was established in 1993,
referred to as the Appropriate Technology Unit (ATU). The unit is
responsible for provision of advisory role to roadworks implementers
targeting adoption of LBT on a large scale, appraisal of its feasibility,
sustainability and replicability in the Tanzanian local environment.
Key parameters being examined include institutional, managerial
and administration considerations; as well as, the cost-effectiveness
of the technology with emphasis that even if it might not be financially
competitive it may be justified on socio-economic grounds.
Labourers are considered as the main means of production in LBT
whereas to enable them to work efficiently and effectively, they
need to be provided with proper and adequate tools among other things.
The quality of tools is important for productivity as well as for
safety. Significant effort should be devoted to the selection of
the right tools in respect of the cost involved in order to safeguard
labourer productivity and working environment.
LBT deployment in road projects requires attention if efficiency
and a satisfactory final quality product are to be achieved. Intervention
of labour operations in some tasks such as haulage and placing of
road materials is required and provision of equipment of the right
type and size, with clear timing and performance, require tactful
organisation.
In Tanzania, studied projects executed using LBT, have revealed
that about 35% to 45% of total cost is spent on tools and equipment
as shown in Table 1.l.
Table 1.1: Labour-based technology roadworks project costs distribution
experienced in five regions in Tanzania
|
Activity
|
Region
|
|
|
Mbeya
|
M'goro
|
K'jaro
|
Tanga
|
Ruvuma
|
|
Labour + support staff
|
36.9%
|
39.2%
|
27.9%
|
38.1%
|
39.1%
|
|
Tools + equipment
|
36.3%
|
35.1%
|
44.4%
|
34.5%
|
36.1%
|
|
Materials + others
|
26.8%
|
25.7%
|
27.7%
|
27.3%
|
24.9%
|
Source: Kilagwa T.T., " M.Sc. Dissertation Report",
1996 pp. 117
In the selection of alternative strategies for road implementation,
planners need to have data on availability and utilisation of machines,
costs and achievable productivity. Project managers/implementers
need to keep data on the right type of tools and equipment in relation
to particular site conditions and environment. Together with that,
proper assessment of performance of labourers and equipment, including
analysis of constraints which affect their performance, is necessary.
The question of deployed tools and equipment appears to be simple,
however, their design and quality have big influence on project
costs. Selection/choice, costing and management of the same in the
application of Labour-based techniques are aspects which can assist
to ascertain products of appropriate and good quality. Also, they
contribute to actual projects unit costs of works, potentiality
of technology sustainability and determine profit margins of the
contractors involved in these works.
Objectives
This paper attempts to address four main objectives. Firstly, to
develop a general: logical framework on how to select and specify
tools; a logical sequential approach to costing requirements for
tools and equipment; and to evaluate management aspects with respect
to tools and equipment basing on the experience gained from projects
executed in Tanzania. Secondly, to evaluate the practice in the
use of tools and equipment in respect of selection and management.
Thirdly, to assess the impact of mixing labour and equipment operations
with the aim of attaining optimum level of labour and equipment
input for efficient construction output. Finally, to outline factors
that affect proper selection, costing and management of tools and
equipment in deploying LBT and suggest possible mitigation measures
basing on Tanzanian conditions.
Methodology
The findings in this paper are based on the observations and field
work done, which included literature review, site visits and interviews
on LBT in roadwork practice, tools and equipment deployed, their
standard, choice, costing and management aspects.
The study was restricted to observations on use of common general
list of tools and equipment for key rehabilitation and maintenance
activities. The list of activities, tools and equipment taken into
consideration are shown in Table 1.2.
Table 1.2: List of activities, tools and equipment considered
|
Activities
|
Tools
|
Equipment
|
|
Excavations of fill material and gravel
Road forming up
Ditching
Haulage of gravel and fill material
Loading of gravel and fill material
Spreading of gravel and fill material
Compaction
Vegetation Control
|
Pickaxe and mattock
Hoe, Forked Shovel and Spade
Rake and Spreader
Earth Rammer
Wheelbarrow
Slashers and grass cutters
|
Tipper truck (7tonne)
Towed grader
Water bowser
Tractor and Trailer
Roller
|
Based on practical experience, assumption of requirements for projects
planning inputs and outputs, a certain sequential approach has been
developed by the authors (Figure 1).Practitioners can utilise it
as a check list on how to develop logical data inputs required at
different implementation levels. Also, it can be the basis of control
and monitoring of inputs during implementation. Costing of inputs
such as, labour, tools, materials and equipment was one of the key
aspects covered in this approach.
Selection/Choice of Tools and Equipment
To a great extent, tools and simple or intermediate items of equipment
suitably selected for appropriate combination with labour, determine
the +quality that can be achieved.
In LBT planning and logistics, special emphasis should be put on
information on quantity and type of resources for different sites
and tasks. Tools, equipment and labour productivity and availability
contributes to the selection of optimum levels of combination between
labour and equipment operations.
Availability of good quality tools and proper handling, storage
and maintenance encourages good organisation of work. Skilful and
harder working labourers can be discouraged by tools of poor quality.
At the same time, any implement of road works by LBT needs to have
access to basic intermediate equipment as a prerequisite to achievement
of meaningful quality work.
Equipment can be made available through hiring or ownership and
the implementers require a proper management set up to control selection
and utility. Otherwise they will end up paying directly or indirectly
for equipment which was standing idle on the site.
Institutional and operational issues including training
Selection of tools and equipment is governed by issues grouped
into: institutional issues; operational issues and training.
Institutional issues are those that can be influenced by policy
and decision makers. They could be said to be the foundation of
all progress but are outside the control of field practitioners.
They include, local manufacturers' capacity and development, quality
assurance control, finance availability, procurement procedures
and policy. These could also be termed as external managerial factors.
Operational issues are those covering operations and they represent
those aspects of the project in full control of field practitioners,
such as engineers, project co-ordinators and supervisors who influence
practical aspects such as designs, specifications, procurement,
performance data, costing, appropriate mix of equipment and maintenance
of equipment.
Training issues are those covering works executor's performance.
Equipment operators and maintenance crew, workshops managers, users
of equipment and works supervisors should be trained to understand
the influence of availability and utilisation.
In order to establish proper and effective deployment of equipment
in LBT, the stated issues should be addressed accordingly and in
timely fashion. Failure to address any of them could lead to establishing
non sustainable technology.
Tools
In LBT, tools operated by labour are meant to produce more or less
the same results (for roads where it is applicable) as bulldozers
and graders do in equipment based technology (EBT). For sure their
selection should be in line with anticipated productivity of labourers
and specifications for tasks to be performed. Tools should be of
acceptable shape, size, weight, balance, strength, sharpness and
of good construction. They should be acceptable to the user and
suitable for the environment.
In Tanzania, tools in use (on studied projects) were selected based
on specifications stipulated in the standard guide by ILO. A technical
manual for labour-based roadworks in Tanzania is to be produced
by the Ministry of Works However, appropriate quality standards
together with specifications in respect of various conditions are
lacking among the implementers. Locally manufactured of tools targeted
the agricultural industry and are far too weak to withstand the
tough conditions of a road site. There are strong national and regional
preferences for particular types of tools, shapes of heads and handles
depending on environmental conditions, culture and availability.
The selected tools are governed by works category and type; soils
or material type, environmental conditions and availability.
The applicability of tools is governed by certain factors, such
as, type of work/activity, type of soil or material (including texture)
and working condition (such as weather). Therefore, it is impractical
to try and have a universally applicable list of tools for certain
purposes in Tanzania as the country has a wide range of conditions
which affect the choice/selection of the appropriate tools.
Equipment
Equipment deployed in LBT roadworks are an intermediate between
those used for heavy construction and standard agricultural implements
and so far there are few standard designs. The type of equipment
employed varies from project to project even similar projects but
located in different environment may employ different equipment.
The question of choosing equipment to be used goes together with
the mix of equipment operations with labour operations.
Equipment required for LBT should be able to withstand the adverse
conditions likely to be encountered, that is, it should perform
effectively over an acceptable working life. Also, it should be
easily maintained and managed with locally available skills.
Simple or intermediate equipment covers a very wide range of items
that can perform similar work although with a difference. Due to
geographical and economic conditions, which vary from country to
country, it is not easy to categorise and specify that one piece
or design of equipment that works well in one area will be successful
in another, this applies also for a very large country like Tanzania.
For the selection of equipment key factors include availability,
organisational set up, work and working conditions, reliability
and utilisation.
In the studied projects, equipment was deployed for haulage of
material for distances more than 300 m, and for watering and compaction.
For rocky and dry gravel excavation, deployment of labour was not
practical, hence equipment was deployed. Table 5.5 shows equipment
and related activities in practice.
Table 5.5: Summary of deployed equipment
|
Equipment
|
Activity
|
Condition
|
Remark
|
|
Tractor/trailer Combination
|
Haulage of gravel and fill material
|
0.3<d*<8
|
3 trailers for d*<3 and 2 trailers for d*>3, Output
fixed at 6 to 8 trips per 8hrs day
|
|
Tipper trucks
(7 tonnes)
|
Haulage of gravel
|
2<d*<15
|
Output fixed at 8 to 12 trips per 8hrs day
|
|
Tractor towed bowser
|
Watering
|
|
|
|
Rollers
|
Compaction
|
|
Size varying according to availability and product quality
|
|
Tractor towed grader
|
Light grading
|
|
|
d* denotes distance in km
Costing of Tools and Equipment
For all road projects, the target of the client (the owner), the
implementing agency (the contractor), and the user (the public),
is to have a product that fulfils the intended purpose at the minimum
possible construction and maintenance unit costs. Deployed tools
and equipment should be costed and charged accordingly in the project
, particularly when establishing cost estimates. The importance
of this aspect has to do with issues of replacement, sustainability
and continuity of projects. Once pieces of equipment cannot be replaced
(at the end of their economic life) from the internal resources
of the project, it implies that there exists a subsidy from other
programmes.
Budgeting and cost forecasting are often most conveniently carried
out by means of unit costs and unit rates. The unit rate for a task
is the cost of performing the task per unit of output, the unit
cost for a resource is the cost of the resource per unit of time,
the cost of the resource per unit of the resource.
For LBT, proper and reliable consideration in the determination
of requirements affects the entire project cost. Planners should
have as one of their basic planning tools, sound knowledge of technology
implementation methods including tools and equipment to be deployed.
Budgeting covers one of the key project management aspects. Usually
the project budget is divided into many items, major ones being:
|
|
Equipment
|
Tools
|
|
Materials
|
Supervision
|
Overheads and profit
|
Influence of tools, equipment and labour on costs is substantial.
Proper management of the same deserves emphasis, the implementer
needs to have a check list of tactics that may be used to reduce
costs.
A conceptual sequence for LBT works planning to attain costing
inputs was developed by authors and compared with practical experience.
The costing procedure is usually performed at the budgeting level,
close to the end of the entire planning process.
Figure 1: Flow chart for LBT work planning (conceptual only)

Costing of tools
Costing of tools relies on procurement set up, productivity outputs,
sources, and estimation abilities. General experience indicated
that the cost of tools was small compared to that of labour in roadworks
that employed LBT. When the works were carried out by force account
approach, labour was directly employed by the project executing
agency, that is, government administrations, who unfortunately overlooked
the importance of tools due to the assumed low costs involved. This
tendency was attributed to lack of incentives to examine entire
project costs and keep them low; together with ignorance of the
impact of tools of poor quality on productivity. Private contractors
worked on normal business principles, that is, project costs conscious
issues take the lead.
General practice in costing use of tools includes:
- initial cost (market price);
- replacement rate in respect of activities involved (i.e. life
span); and
- maintenance costs (where applicable).
Conceptual procedure for costing of tools to be deployed in the
project as developed by the authors basing on practical experience
is as outlined here below:-
- Determine the number of person days (pd) required per activity
that should deploy tools (irrespective of tool type)
pdi = b/a
a is the standardised or from general experience
task rate (units per person day)
b is number of total units of work to be performed
on activity (i).
- Determine the total number of person days (f), for all (s) activities
that should deploy tools (irrespective of tool type)
f =å pdi where,
i = 1,2,3,...,s (activities)
- Determine the cost of all tools to be deployed. Can be done
as described in step 6 of Figure 1. The obtained amount is (e).
- Determine the cost of tool person day (CTpd) assuming
activity person days is equal to tool person days.
CTpd = e/f
- Determine the cost of tools for each activity (CTi)
CTi = CTpd x b
Factors to be observed in application of this procedure include:
- Number of tools, which should accommodate possible losses, damages
and salvage;
- The assumption that types of tools need not be regarded separately
for simplicity;
- Cost should include all related logistics.
Costing of equipment
Although LBT emphasises an extensive use of labour rather than
equipment, a significant part of the costs and attention of project
implementers is devoted to the use of appropriate equipment. Use
of equipment on site is the most costly operation during the whole
roadworks execution period. Therefore it is of vital importance
to spend time planning equipment use carefully so as to know the
costs and ascertain all management aspects irrespective of the size
or type or mode of acquisition of the equipment.
No matter the technology, the key problem where equipment is involved
is effective and efficient management, availability and utilisation.
Whatever the approach, hiring or owning the equipment, the practitioner
should have access to the equipment at a reasonable price which
is determined or governed by sufficient supply.
In roadworks, rates to be charged against activities executed using
any piece of equipment in the project, should clearly reflect all
operating, investment and depreciation costs. This shall ensure
replacement from internal resources allowing the project to be sustainable.
In LBT for roadworks, the costing of equipment doesn't differ from
the practice adopted when deploying EBT. The issue remains vital
as it contributes to effectiveness, efficiency and competitive implementation
of the technology.
Based on experience from investigated projects, costing of equipment
requires establishment of:
- quantities of work to be performed;
- standardised (in local environment) output rate;
- cost of that equipment per unit time; and
- duration the equipment shall spend on site for the project.
Simplified conceptual steps and relations that may be followed
in costing equipment have been developed considering the above key
inputs. Major assumptions made include: operations do not require
deployment of different types of equipment with varying hire rates
and output rates implying different utilisation. The following steps
are proposed:-
- Determine activities (s) that shall deploy the same type of
equipment including quantities of work for each activity (qi)
and duration (di) basing on local conditions output
rates (ri).
di = qi/ri where i =
1, 2, 3, ...., s
- Determine cost of having the equipment per unit of time (n),
usually take prevailing market hire rates.
- Determine the cost of using the equipment on each activity (hi)
hi = di x n = qi/ri
x n
- Determine total cost of the equipment while in use on site (mi)
m = å hi
+ k
where k are other related costs such as mobilisation,
demobilisation contingencies and idle time.
- Determine the actual equipment cost per unit of time of effective
utilisation (w) and use it for costing and budgeting.
w = m/ di
Management of tools and equipment
Management is a process whereby managers create, direct, operate
and control complex organisation using human effort to achieve the
intended objectives. The project management may be defined as the
overall control of the process to optimise the major attributes
of the process, that is, quality, schedule and cost. The project
implementation starts with the planning phase where major decisions
are made concerning factors such as, project size and complexity,
location, time constraints, desired level of quality and resources
inputs. Proper management of the planning and decision process is
therefore extremely important, as it determines proper implementation
of the construction phase.
Due to the investment involved in road networks, it is important
and appropriate to consider managing it in a businesslike manner.
That would allow roads construction and maintenance management issues
to be termed as getting the right materials, equipment and people
to the right place to carry out the right work at the right time
and cost.
For general practice, practitioners need to be conversant with:
- handling and management of labour, equipment and other factors
that affect productivity;
- general construction outputs and environmental factors that
dictate deploying particular types of tools and equipment prior
to project take off; and
- reliable and proper co-ordination with manufacturers of tools
and equipment. Their experiences of technical problems encountered
should be provided as feedback so that manufacturers can be exposed
to actual needs in prevailing conditions for development and testing.
Management of tools
Management of tools requires acceptable organisational set up co-ordinating
all key stakeholders. LBT practitioners should keep large stock
of tools, and think carefully about tools they intend to procure.
Based on practical experience, it should always be possible to estimate
actual requirements, possible losses, and the quality of tools which
would be durable according to environmental conditions. This might
be expensive but will be worth it in terms of long term benefits.
In order to keep track of tools, it is essential to set up simple
tools planning and reporting systems. The information from records
should be used to monitor and analyse costs, durability and condition
of different batches of tools for purposes of improvement and setting
a sustainable trend for future purchases and utilisation. Unfortunately,
from studied projects, this does not seem to be the case in practice.
Broken, damaged and worn out items should be replaced or sharpened
(where applicable) in the course of work execution. For the purpose
of ensuring longer life, control of misuse or theft of tools, proper
handling, storage and maintenance deserve emphasis.
For the tools to be deployed, the implementers:
- should be conversant with specific tools requirement in respect
of different activities including designs, specifications and
criteria of selection;
- should know the source of tools (suppliers and, or manufacturers)
within the project locality;
- should know and adopt proper procurement procedures and set
up of main and site stores; and
- should observe effects of different types of tools on labourers'
productivity
Observed practice on tools management aspects revealed:
- During procurement, specification and design of tools are not
observed to suit roadwork conditions. The procurement system of
buying from cheapest quoted price contributes to poor quality
tools, although this is not quantified. Also, it has been observed
that some procurement officials cannot appreciate practical differences
between some tools, they are committed to prices only. For example,
the difference between mattocks and pickaxes was not clear to
some purchasers. The purchaser assumed the two tools are for the
same work.
- Verification of quality of tools is not done due to lack of
testing facilities.
- Local manufacturers are not encouraged to produce tools specifically
for roadworks. Requirements at regional, zonal or national level
are not co-ordinated to give an indication of the demand potential.
Management of equipment
For equipment deployed: effective, efficient and reliable implementation
can be achieved if key stakeholders are conversant with the following
issues:
- different types of equipment required and available for the
project and criteria to be used for selection;
- productivity and output rate of available equipment (rated and
actual as per the existing conditions);
- modes of acquisition available and associated responsibilities
in risk sharing;
- operator knowledge and training required; and
- proper scheduling of activities and monitoring utilisation to
avoid paying for pieces which are idling unnecessarily on the
sites.
Observed practice indicated the existence of a low level of availability
and utilisation of equipment. This was attributed to lack of spare
parts, poor maintenance, insufficient planning and co-ordination
plus misuse of the programme equipment.
Mixing of Labour and Equipment Operations
In LBT there exists an issue of optimum combination of equipment
and labour operations for required project delivery timing and quality
achievement.
The mixing of labour and equipment operations depends on the activity
sequence, construction output and labour and equipment input levels.
General practise of LBT indicates that many activities are executed
exclusively by labour using non mechanical tools such as hoes, spades,
shovel and wheelbarrows while for activities which cannot be performed
efficiently and effectively by labour such as haulage and placing
of materials, equipment is deployed.
The concept of mixing is twofold: labour to work with the equipment
on the same category of work or labour working on activities preceding
or following those performed by deploying equipment.
The question of mixing operations done under LBT in roadworks,
is dependent on the sequence of work activities and technological
input. Approaching optimum mixes of operations that require labour
input exclusively and those that deploy equipment solely, could
be a complicated aspect. However, key issues to observe are labour
outputs, equipment outputs and construction output. Gang size and
co-ordination between performers of different activities, contributes
to decisions of optimum level to be achieved, apart from type of
equipment and tools deployed.
General observations shows that it would require about 25 labourers
to support a 5 five tonne flat truck, hauling about 29 m3
of firm soil per eight hours day over an average condition haul
distance of 1.5 km, for excavating, loading, unloading and spreading
[Gichaga and Parker, 1988, pp 133]. This concept can be the basis
for management decisions, for instance to hire on the basis of the
critical labour and equipment input to ensure effective output,
seeking always to approximate the maximum achievable output or optimum.
Observed practice in Tanzania is that normally a combination of
tipper trucks (seven tonne) and tractor trailers is used for haulage
of gravel whereas excavation, loading and spreading is done by labour.
However, sufficient quantification of practical data is missing,
weakening the argument for advocating adoption of similar practices
in other places. The method appears to be efficient but it should
be supported by field data and analysis stating surrounding limitations.
Discussion of Observations
- Non observance of quality of tools during procurement and weak
emphasis on testing the same on delivery could be attributed to
ignorance of practitioners about the impact of good tools on labourers
output. Also, lack of encouragement of local manufacturers does
not give room to practitioners to specify sources of tools and
thereby monitor performance and participate in development, improvements
and testing. Continuance of such practice could lead to problems
such as, discouraging labourers, increasing costs due to increment
in work days required and making the technology unsustainable.
- Procurement procedures which allow purchasers who are not conversant
with site working conditions also contribute to non compliance
with actual requirements. Losses incurred in this fashion could
be significant if the technology were to be adopted nation-wide.
- Co-ordination among manufacturers and supervisors, together
with training of users, would allow development and simplification
of the technology.
- The logical approach on costing of tools and equipment for each
activity is vital to establish a basis for budgeting, monitoring
and evaluation of the implementation;
- Shortcomings exist in the practical implementation of deploying
tools and equipment on costing and management. Also, awareness
is lacking about impacts that can be realised with a proper mix
labour and equipment operations in practice.
Recommendations
- Labour-based technology for road construction, rehabilitation
and maintenance in developing countries such as Tanzania is appropriate.
Scientific interventions should target deployment of quality tools
with emphasis on local manufacturing, towards application of the
technology nation-wide. Potential needs at regional, zonal and
national levels should be co-ordinated. Local manufacturers should
be approached and encouraged to improve product quality with the
target of satisfying roadworks site conditions without abandoning
normal customers. Promotion of the technology at macro level should
involve making it sustainable. Based on field studies it was found
necessary to:
- standardise at zonal level, local environmental conditions
affecting selection of tools and equipment, together with practical
output rates;
- prepare guidelines on logical approaches to selection criteria
and costing of tools and equipment; and
- document and publish the established and acceptable approaches
and standards as a handbook for practitioners.
- Deployment of tipper trucks (seven tonnes) for haulage of material
has shown acceptable performance making the equipment acceptable
for LBT. However, performance data such as output rates, costing
approach and management should be quantified for development and
sustainability. Practitioners such as contractors, require advice
and guidelines on appropriate approaches to be adopted during
implementation especially on choosing between available haulage
alternatives.
- A data collection and banking system should be established.
Emphasis should be given to output rates, cost of inputs as monitored
during implementation, tools and equipment losses and damages.
- Awareness seminars should also include:
- importance of tool quality, selection criteria and costing.
With elaboration on the effects of selection and quality on
productivity hence person days required, implying costing.
- emphasis on procurement procedures which observe good quality
together with cost constraints.
- involvement of local tools manufacturers to enlighten them
on labour-based technology in roadworks site conditions.
References
Anderson, C, A. Beusch and D. Miles (1996) Road maintenance
and regravelling (ROMAR) using labour-based methods, Workbook. ILO,
Geneva
Beusch, A. and de Veen, J. J. (1991) Course notes: International
course for engineers and managers for labour based road construction
and maintenance programmes. ILO, Geneva
Coukis, B (1983) Labour based construction programmes, a practical
guide for planning and management. World Bank, Washington, D.C.
Gichaga, F. J. N and Parker, A (1988) Essentials of highway
engineering; with reference to warm climates. Macmillan, London
ILO (1988) Guide to tools and equipment for labour based road
construction and maintenance. ILO, Geneva
Kilagwa, T. T. (1996) The economics of labour based construction
and maintenance of rural roads in Tanzania: A dissertation report.
University of Dar es salaam, Dar es Salaam
Ministry of Works, ATU (1995) Estimated potential for the use
of labour based methods in road works in Tanzania. Ministry
of Works, Dar es Salaam
ILO (1993) Labour-based technology; A review of current practice,
seminar proceedings report and papers, Harare, 27th September
- 1st October 1993 ILO, Geneva
Equipping
Trained Labour-based Contractors — The Ghanaian Experience
E. N. K. Ashong (BSC, MSC, MGhIE), National Co-ordinator, Department
of Feeder Roads, Accra, Ghana
Introduction
The issue of whether or not to equip trained labour-based contractors
looks to have been put to rest with the acceptance of the fact that
trained labour-based contractors need some basic equipment. The
source of this equipment is the subject of argument.
The consensus which looks to be that of the majority now is that
trained contractors should be equipped but "appropriately." What
is considered "appropriate" can vary from country to country and
even from region to region within the same country. Certain key
points need to be considered in determining the degree of "appropriateness"
of equipment packages. Apart from physical/terrain considerations,
issues such as the performance of the existing construction industry
and the equipment back-up services need to be given serious consideration.
The matrix will be incomplete without a serious look at the pay-back
period vis-à-vis the need for continuous "flow" of work for
the contractor and the application of "fair" schedule of rates.
Based on the experience gained in Ghana since 1986 with a starting
number of seven equipped contractors, this paper intends to look
at the managerial aspect of the problem with a view to making salient
recommendations that will go a long way to avoid and alleviate the
problems encountered.
The Argument
There are two schools of thought on the issue of equipment supply
to labour-based contractors. The first group's argument can be summarised
thus:
"Trained labour-based contractors should be 'thrown' straight into
the competitive environment, like all other contractors to fend
for themselves. The success in such an environment is a real measure
of success."
The other group's argument can also be summarised thus:
"The development of a successful and sustainable labour-based programme
should be systematic and every new step must be totally evaluated
to optimise the chances of success. Being a new technology, there
is a need to guide and guard the contractors in the early formative
years in terms of capacity building, and technical/managerial competence."
Ghana belongs to the second group. The Ghana labour-based programme
started in 1986. Up to date 93 contractors have been trained out
of which 56 have been equipped.
The Status of the Ghana Programme
The Ghana programme started in 1986 with technical support of the
ILO. Initially seven contractors were trained in the technology
and supplied with the following pieces of equipment at a total cost
of US$150,000 on loan, recoverable in four years with interest.
This interest is applied to the original loan at the prevailing
banking rules and regulations.
- 3 tractors
- 6 trailers
- 1 tipper truck*
- 1 towed water bowser
- 1 pedestrian roller
- 1 chain-saw
- A set of hand tools
* Hired by the contractor from a pool and released
eventually to the contractor after the completion of the Trial Contract
and during the execution of the first Standard Contract.
The subsequent equipment packages included a pick-up and a tipper
truck which were released to each contractor from the onset.
Table 1: Regional distribution of labour-based contractors
|
SN
|
Region
|
Total trained
|
Total equipped
|
Total non-equipped
|
|
1
|
Greater Accra
|
4
|
-
|
4
|
|
2
|
Eastern
|
15
|
10
|
5
|
|
3
|
Volta
|
8
|
6
|
2
|
|
4
|
Central
|
9
|
3
|
6
|
|
5
|
Western
|
10
|
7
|
3
|
|
6
|
Ashanti
|
10
|
9
|
1
|
|
7
|
Brong-Ahafo
|
11
|
9
|
2
|
|
8
|
Northern
|
10
|
6
|
4
|
|
9
|
Upper-East
|
8
|
3
|
5
|
|
10
|
Upper-West
|
8
|
3
|
5
|
|
Total
|
93
|
56
|
37
|
One trained contractor has been expelled for non-performance. The
programme, which started on a pilot basis in the Western Region
and on a demonstration basis in Ashanti and Brong-Ahafo Regions,
is now nation-wide.
Table 2: Rate of equipment supply
|
Year
|
No of contractors trained
|
Cumulative no of contractors trained
|
No of contractors equipped
|
Cumulative no. of contractors equipped
|
Cumulative no of non-equipped contractors
|
|
1987
|
6
|
6
|
3
|
3
|
3
|
|
1988
|
7
|
13
|
4
|
7
|
6
|
|
1989
|
16
|
29
|
12
|
19
|
10
|
|
1990
|
6
|
35
|
2
|
21
|
14
|
|
1991
|
6
|
41
|
5
|
26
|
15
|
|
1992
|
14
|
55
|
-
|
26
|
29
|
|
1993
|
16
|
71
|
-
|
26
|
45
|
|
1994
|
10
|
81
|
28
|
54
|
26
|
|
1995
|
12
|
93
|
-
|
54
|
38
|
|
1996
|
-
|
93
|
2
|
56
|
36
|
|
1997
|
-
|
93
|
-
|
56
|
36
|
Table 3: Support for equipment
|
Year
|
No. of sets
|
Donors
|
|
1987/1989
|
21
|
World Bank
|
|
1991
|
5
|
Ghana Government
|
|
1994
|
16
|
DANIDA
|
|
1994
|
12
|
USAID
|
|
1996
|
2
|
IFAD
|
Table 2 shows how the Ghana programme has been ‘prodding' on with
equipment supply to trained contractors and the arrears required.
Table 3 indicates that only 8.9% of the equipment supply so far
is from Ghana Government source. This shows a high degree of donor-driven
equipment supply.
Factors Affecting the Contractors' Equipment
Loan Recovery
Each equipped labour-based contractor is supposed to re-pay the
equipment loan with interest in four years. The assumption is that
the contractor will be guaranteed continuous work within this loan
recovery period. Due to budgetary constraints in a developing economy
like Ghana, this condition has been very difficult to fulfil. The
contractors' performance in terms of the servicing of equipment
loan is affected by the actions of a tripartite group made up of
the contractor himself, the client and the loan management bank.
The roles played by this group towards the speedy recovery of the
equipment loan are summarised in Figure 1. Some few explanations
may throw more light on some of the issues summarised in figure
1.
Only time tested equipment should be procured
Competitive tendering has led to the procurement of 'unknown' pieces
of equipment which have led to very low outputs. In every country
there are some familiar and tested brands for every type of equipment.
Selective tendering should be used as much as possible in order
to take advantage of such experience.
Equipment adequacy
The tipper truck contributes about 32% of the equipment loan but
does not contribute significantly towards physical output since
it is basically used for the long distance haulage of basic inputs
like cement, fuel and iron roads. The tipper should either be replaced
by a less expensive low-bed truck or the contractors should be assisted
to procure the tipper truck after a period of two years within which
the contractors' loan servicing performance would have been determined
and the size of the original loan would have been reduced drastically.
Maintenance of proper construction management practices
The actions of the contractor should always be geared towards optimum
productivity and hence speedy servicing of the equipment loan. The
following are samples of bad construction management practices:
- use of worn-out tools
- long delay in servicing of equipment
- diversion of money meant for salaries and wages
Figure 1: Contributory factors for speedy equipment loan recovery
|
The Client
|
The Contractor
|
Loan Management Bank
|
|
Selection and training of contractors
|
Continuous production of at least 1.5km of gravel road per
month
|
Assessment of financial capability of contractors
|
|
|
|
|
|
Procurement of equipment
|
Maintenance of proper construction management practices
|
Interest rates fixed at acceptable level
|
|
|
|
|
|
Equipment adequacy
|
Maintenance of equipment
|
Supply of adequate information on loan recovery to the client
and contractor
|
|
|
|
|
|
Prompt payment
|
Establishment of private credit facilities
|
Monitoring of equipment management and maintenance
|
|
|
|
|
|
Ensuring continuous work for the contractor
|
Need for a strong association for interest protection and
addressing common problems
|
Favourable conditions for collateral and guarantees
|
Years of experience have shown that the following can further enhance
speedy loan recovery:
- Denomination of the loan in the currency of the beneficiary
country instead of that of the donor;
- Procurement of only time tested equipment; and
- Quarterly interest application instead of monthly.
- To date, 26 contractors should have finished paying for their
equipment loans. Despite the numerous initial problems created
by the above itemised factors, about 70% of this number have finished
paying back the loan with the first completing in a record time
of three years. The outstanding 30% have small balances to clear.
The Way Forward
There are currently 36 contractors yet to be equipped. There are
110 political districts in Ghana. Decentralisation of governance
to the local/district level is being pursued vigorously in Ghana.
The Department of Feeder Roads (DFR) is one of the targeted agencies
to be decentralised. The vision of DFR is to evolve a district-based
sustainable maintenance strategy with equipped labour-based contractors
as the executors. There are 102 rural and 8 Urban/Metropolitan political
districts in Ghana. It is envisaged that DFR will have on the average
one labour-based contractor per district to be in charge of routine/recurrent
maintenance works. Thus eventually 110 contractors, will be trained
in the technology. The following are the emerging problems:
- Moving the number of trained contractors from 93 to 110, that
is training 17 more contractors
- Equipping the current outstanding 36 contractors and the additional
17
DFR does not intend to train more new contractors until the problems
with the equipping the outstanding 36 contractors appropriately
have been solved. The current capacity is adequate for the maintenance
works since the contractors who have finished paying for the equipment
can be engaged to work in more than one district. The training will
now concentrate on maintenance and management.
The outstanding 36 contractors need to be equipped appropriately
to execute routine/recurrent maintenance. The Ghanaian labour-based
contractors are going to be classified into three groups based on
equipment holding and the type of work to be executed. The recommended
equipment packages listed below were arrived at taking cognisance
of the fact that DFR's main thrust for the immediate future is maintenance.
The classification will ensure:
- healthy competition in both quality and performance
- early loan repayment
- maximum utilisation of limited funds
- larger coverage of contractors implying more coverage of the
road network to be maintained.
The level of equipment supply should depend on the network condition
mix of the country and the thrust of the road authority's operations.
Ghana started from level one because at the inception of the programme,
the condition of the network required massive rehabilitation works.
The rehabilitation backlog has been cleared appreciably and the
thrust of DFR's operation now is maintenance and the stabilisation
of the existing network hence we can now afford to equip from level
three. The recommendation therefore will be to look at your problem
and equip contractors accordingly.
An incentive element is built into this approach because contractors
at the lower level can either be assisted with further equipment
to move up to the next level or they can privately augment their
equipment holding to move up. On the other hand, due to non-performance
and equipment loss, contractors can be demoted.
The "appropriate" equipment for each class is as follows:
Level one:
This level of contractors can handle any type of rehabilitation
and maintenance contracts.
Current package for equipped contractors so far:
- 3 tractors
- 6 trailers
- 2 pedestrian rollers
- 1 water bowser
- 1 tipper truck
- 1 pick-up
- towed grader**
Minimum number of trained supervisors: 3
The cost of this package is about US$150,000.
** To be procured later by contractors.
Level two:
This level of contractors will handle routine/recurrent and periodic
maintenance contracts. The recommended equipment holding is as follows:
- 2 tractors
- 2 trailers
- 1 bowser
- 1 pick-up
- 1 towed grader
- 1 pedestrian roller
The cost of the package is about US$70,000.00
Minimum number of trained supervisors: 2
Level three:
This level of contractors will handle only routine/recurrent maintenance
contracts. The recommended equipment holding is as follows:
- 1 tractor
- 1 trailer
- 1 pedestrian roller
- 1 motorbike
The cost of the package is about US$30,000.
Most countries do not have local contractors and works are executed
mainly by foreign contractors. Ghana at the inception of the programme
had a vibrant construction industry dominated by local contractors
and therefore taking the bold decision to involve the private sector
in the programme instead of using direct labour was considered not
too risky. Most countries are still using direct labour for labour-based
works despite the clearly identified attendant problems. The creation
of a vibrant core of local contractors can be started cautiously
using small scale labour-based contractors.
Setting Up of Plant Pools
Ghana has enormous experience in the performance and contribution
of plant hiring companies although this experience is largely limited
to capital-intensive contractors. All the large government owned
and privately established plant hiring companies have folded up
and some are now using the remnants of their equipment stock to
execute contracts directly. The reasons for the failure of these
companies are numerous, the principal among them being:
- non-payment by contractors;
- large overheads
- acquisition of equipment by contractors due to high hire charges
by hiring companies;
- a temptation on the part of the hiring companies to enter the
construction industry; and
- high cost of haulage of equipment over long distances.
DFR has indirectly established a protected plant pool for the non-equipped
contractors. This category of contractors are the only ones allowed
to hire DFR equipment. The hiring cost of the equipment is deducted
at source from payments for work done. This system has worked well
till now because the non-equipped contractors are awarded contracts
for the installation of culverts and the approach fillings. The
scramble for equipment even in this system can be intensive.
Experience from other countries, like Tanzania shows that plant
pools have not helped in the establishment of labour-based programmes
because other stakeholders like capital-based contractors and farmers
have increased the scramble for equipment to the disadvantage of
the small-scale labour-based contractors. The situation becomes
aggravated by the fact that the labour-based contractors need to
ensure continuous work to keep up the morale of the workers, especially
the casuals. Where resources are available, consideration should
be given to the setting up of a protected plant pool as a supplementary
equipment source to the current situation of a direct supply of
equipment loans to trained labour-based contractors. The advantage
is that the cost of hiring of any piece of equipment can be deducted
at source by the client.
Conclusion
Trained labour-based contractors need equipment. The source of
equipment can be: the client through equipment loans, outright ownership
by the contractor or through protected plant pools. The equipment
package should be "appropriate" for the work available in order
not to overburden small-scale contractors with limitless loans.
Labour-based programmes should be designed in such a way as to ensure
an optimum mixture of equipment package instead of over-equipping
contractors making them to feel that the programme is just a "safe
haven" for the acquisition of equipment for other works.
Labour-based
Programme: Uganda Country Paper
Eng. W. E. Musumba, Principal Executive Engineer, Road Maintenance
Contracts, Ministry of Works, Transport and Communications, P O
Box 10, Entebbe, Uganda
Background
The Government of Uganda has since 1986 reconstructed/rehabilitated
a sizeable portion of its entire road network which necessitated
the putting in place of an effective road maintenance system to
protect the investment. The government has as one of it's highway
network policies "the development of the local construction industry
as a measure of ensuring a sustainable road network". The government
has endorsed the labour based contracting option as one of its appropriate
technologies.
The paper discusses some of the labour-based projects that are
currently being or have been recently undertaken by government.
The paper looks at the enabling environment provided by the government
and how the implementers have been equipped in undertaking the different
labour based projects/programmes.
A number of projects deploying labour-based technology are discussed.
The use of this technology now has a firm foothold in Uganda as
is evidenced by a number of such projects currently under design
implementation or design.
Introduction
Since 1986 the Government of Uganda has reconstructed/rehabilitated
60% of the main roads and 20% of the feeder roads at a total cost
of over US$300 million. There was therefore mounting pressure to
have this enormous investment protected. In 1992, under the auspices
of the Road Maintenance Initiative, an in-depth analysis of problems
related to road maintenance was undertaken. This led to the formulation
of revised policies and strategies which now form the basis on which
the contracting option was adopted for roadworks. The government's
medium-term highway network policy is the following:-
- The provision of an efficient, safe and sustainable main roads
network as a support for accelerated integrated development and
consolidation of peace and national unity.
- The development of the local construction industry as a measure
of ensuring a sustainable road network.
- To undertake alleviation programmes.
The government has adopted a deliberate policy of increased use
of the contracting option with the target of contracting 80% of
all roadworks by the year 2000. It was however noted that the local
contracting industry was ill-equipped and could only develop gradually
through affirmative action by government. Further experience had
shown that potential small scale contractors lacked experience in
quoting and tendering generally and hence it became extremely difficult
from them to break into the market. The adoption of Fixed Unit Rates
(FUR) was therefore found to be a most feasible approach.
The objective of the contracting initiatives is to develop in the
local contracting industry a sustainable capacity for roadworks
using small scale contractors. Both the Ministry of Works, Transport
and Communications, and the Ministry of Local Government have embraced
the policy of use of contractors as the most cost effective means
of handling roadworks.
The Ministry of Planning and Economic Development has also co-ordinated
various pilot projects with the aim of creating employment and alleviating
poverty. A number of such projects are discussed.
The Labour-based Contracting Programme (LBCP)
Basis
The policy of the Ministry of Works, Transport and Communications
(MOWTC) is to increasingly use private contractors for cost effective
and efficient operations. The old policy, which was highly dependent
on force account operations, had several constraints which the increased
use of contractors aims at minimising.
Project data
The Labour-based Contracting Programme (LBCP) is financed by the
Government of Uganda. Over US$3.0 million is annually budgeted for
the programme. The annual turnover for a typical lengthman contractor
(maintenance of 2km) currently stands at US$360.
The LBCP which started in January 1993, is an ongoing routine activity
budgeted for annually under the road maintenance recurrent budget.
Project activities
The programme targets all the manual routine maintenance activities
that are normally carried out on both paved and unpaved (gravel)
roads. The list of activities includes the removal of obstructions,
drainage repairs, filling of potholes and grubbing (for unpaved
roads only), vegetation control and tree planting.
Equipping of contractors
Initially, tools were provided to the contractors. With the liberalisation
of our economy, the contractors are responsible for provision of
their own tools, which are readily available. The Ministry, however,
still provides expensive tools like wheelbarrows to interested contractors.
The contractors are encouraged to have the following handtools:-
- Wheelbarrow
- Hoes
- Shovels/spades
- Rakes
- Slashers
Fixed Unit Rate Mechanised Contracting Programme
Basis
According to the new maintenance strategies, all routine mechanised
maintenance will ultimately (by the year 2000) be carried out by
contract. Another strategy is that aimed at capacity building of
local contractors. This programme was started to answer to the two
above strategies.
Project data
This is an annual programme whereby the government of Uganda allows
a percentage of the budget equivalent to at least US$3 million.
This programme is intended to be a short term stop gap, which will
eventually give way to local competitive bidding.
Programme activities
This programme is targeted at developing contractors to carry out
routine mechanised maintenance. Activities include the following;
grading, drainage repairs, spot regravelling of unpaved roads, pothole
patching and shoulder repairs for paved roads.
Equipping of contractors
In an effort to offer affirmative support to the emerging contractors,
MOWTC adopted a policy whereby contractors can now hire idle equipment
to the contractors. Those in a position to repair broken down equipment
can repair and hire the same and utilise the equipment for a given
period to offset the costs. Contractors are at the same time encouraged
to acquire their own equipment.
The Uganda Transport Rehabilitation Project
Basis
The policy direction for the Ministry of Local Government (MOLG)is
more less the same as that of Ministry of Works, Transport and Communications
(MOWTC), with different targets for attaining local contracting
capacity. The Ministry has among its objectives to introduce labour-based
methods of road maintenance and feeder roads rehabilitation wherever
cost-effective.
Project data
This is a component of the Feeder Roads Component of the Transport
Rehabilitation Project. It is financed by the International Development
Association (IDA), Nordic Development Fund (NDF), and Government
of Uganda (GOU). The value of the works is US$8.7millon over a four
year period starting in 1995. The annual turnover for a typical
contractor is in the range of US$240,000 for rehabilitation works
of about 20 - 25 km.
Project activities
The relevant project activities include rehabilitation of 680km
and maintenance of 880km of feeder roads in four districts of Mbale,
Kapchorwa, Tororo and Pallisa of Eastern Uganda. The project proposes
to use labour-based methods in combination with light equipment
like farm tractors, trailers, pickups, motorcycles, pedestrian rollers
etc.
Technical assistance (TA) has been provided to steer the programme.
Notable in the TA team are local expert staff and this provides
another area of local capacity building.
Equipping
This project attempts to address the main constraint facing contractors,
lack of equipment. The project has procured the necessary equipment
and tools. A financing/leasing company has been formed and will
be responsible for the leasing of the equipment. The leasing company
will also be linked to the banking system, which will handle payments
and provide working capital to contractors. This leasing arrangement
has been a highly motivating factor for the aspiring contractors.
Each contractor has been equipped with the following:-
1 pick-up
1 tractor with trailer
1 tipper
1 set of culvert mould
2 double drum rollers
The African Development Bank (ADB) Rural
Feeder Road Rehabilitation and Maintenance Project.
Basis
Basically all feeder roads projects are required to apply effective
routine maintenance on the rehabilitated roads.
Project data
The Project is financed by African Development Bank (ADB) (US$24.0
million) and Government of Uganda (GOU) (US$16.0millon). About 20%
of the above funds is meant for manual routine maintenance.
Project activities
Labour-based routine maintenance of 2400km of rehabilitated roads.
Activities include removal of obstruction, drainage maintenance,
pothole filling, grubbing and vegetation control.
Equipping of contractor
The project provides the required tools, which include wheelbarrows,
hoes, shovels, rakes, slashers, etc. Decentralised payments are
made.
Re-Integration of Demobilised Soldiers Programme
(RDSP)
Basis
The overriding aim of the project is to give demobilised soldiers
a chance to be integrated in society through acquisition of skills
and gainful employment.
Project data
The funding is through a grant of DM4.0 million from the Government
of Germany.
Project activities
The demobilised soldiers were formed into labour units responsible
for opening and rehabilitating of feeder roads in ten districts.
Activities include reshaping, selective regravelling, provision
of concrete culverts and follow up maintenance.
Equipping of hired labour
The labour units are equipped with the necessary tools. Individuals
are given the necessary skills in road rehabilitation, maintenance
and fabrication of culverts.
MPED/ILO Labour Intensive Projects
Background
In Uganda, the ILO has also been instrumental in promoting labour-based
programmes. This was initiated in 1981 under the Ministry of Planning/ILO
Labour-Intensive Special Public works Programme (LISPWP). The Labour
Intensive Works Unit (LIWU) was established in the Ministry to pilot
and promote the various LISPWP projects.
LIWU is currently led by the Under Secretary of MPED as its Chairperson
and a National Co-ordinator for the day to day operation of the
unit. Technical personnel from other government departments are
co-opted into the unit according to the needs of each particular
project.
Some of the projects implemented by LIWU are discussed below.
Multi-Sectoral Project in Karamoja
This employment creation and infrastructure building capacity was
implemented between 1985 and 1995 with a breakdown during the 1986-87
war. The project involved the building of schools, markets, the
construction of boreholes and afforestation works with funding from
UNDP (for the technical assistance) and the Government of the Netherlands
for the investments (about US$9 million). During the first phase,
implementation started in the districts of Moroto and Kotido, later
on all investments were concentrated in Kotido district. Local people
provided the local materials and served as unskilled labour on all
the construction works. Some were trained on-the-job to do some
skilled jobs like carpentry and masonry.
Rehabilitation Project in Luwero District
This was an emergency relief programme implemented in Semuto sub-country,
one of the most war-affected areas in the Luwero Triangle. It was
a quick intervention project designed to help people resettle in
their homes. It involved construction of schools, co-operative stores
and roads, protection of water points, and promotion of agroforestry
funded by UNDP. One other important element promoted in this project
was banking of mandays in exchange for building materials and opening
up of agricultural fields.
Promoting Local Building Materials Project
This was a research programme funded by the Austrian Government
to test the use of improved local building materials in a few selected
villages both outside and within the above mentioned project areas.
The research conducted involved development of stabilised soil sun-dried
bricks and the use of papyrus for roofing.
Southwest Feeder Road Project (1986-94)
The UNCDF/UNDP funded project involved the rehabilitation of over
600km of feeder roads in six districts. The rehabilitation of the
feeder roads was done mainly by equipment intensive methods. However,
operations like culverting were done by small local contractors.
Maintenance was also contracted out to small contractors.
Masulita Development Project
The integrated rural-development project was designed to reactivate
the local economy of another war-ravaged area using the experiences
of the Luwero project. The situation at the beginning of the project
was that of an area with impassable, overgrown roads, poor hygiene
standards with limited and seasonal sources of drinking water, a
high number of uneducated teenagers and, a general lack of facilities
to improve the agricultural production. Therefore, the project was
designed to improve accessibility to and within the area, to boost
the income of the population and to provide primary health-care.
The project's outputs include: feeder roads, protected water points,
easier access to credit for the poor, and improved hygiene. The
project used a community-based approach, and many of the community's
workers have acquired trade skills in carpentry, masonry, road reconstruction
and maintenance works. These workers simultaneously boosted their
income through the wages earned and can now access credit to improve
their productive activities. A quantified analysis reveals that
over 80,000 days of paid employment had been created by 31/07/97
and Ushs102,409,570 paid in wages to the local workers. In addition,
Ug Shs 25 million was spent on buying local materials from the area.
These included sand, hard core, timber and murram.
Experiences and Recommendations
Experiences from the different projects indicates that prospects
for the labour based technology are bright. However, it is apparent
that the following need attention:
- At the moment, the implementing agencies are apparently initiating
projects on their own. There is need for co-ordination between
the different implementing agencies, especially in areas of policy
and training.
- Equipping of the implementers even with simple tools is still
a major problem. Hardly any leasing/plant hire pool exists in
this country. The impact equipping arrangement under the Uganda
Transport Rehabilitation Project is yet to be assessed. Future
projects should address this critical area.
- Related to the problem of equipping is the use of wrong tools,
evident in most projects. For example, when should a shovel be
used instead of a spade. Training components should be a must
in all projects.
- Because of lack of co-ordination the documentation is basically
agency specific. Standard labour based management guidelines should
be developed.
- There is limited continuity. Projects are initiated and implemented
but there is hardly any follow-up thereafter.
It is hoped that the new project, Support to Labour-Policy Promotion
Initiative, will address most of the above issues. The project aims
at achieving the following:-
- Labour-based approaches are integrated into the national planning
process and a policy adopted.
- Technical and administrative capacity to implement labour-based
works is created in the public and private sector through training
and the development of manuals and guidelines.
- Knowledge on labour-based works for employment generation is
increased among decision makers and the general public.
- Labour-based techniques and use of local resources is further
researched and developed.
Conclusion
Labour-based technology has definitely taken hold in Uganda. The
programme has been received with particular enthusiasm by the operatives.
The labour based approach offers much needed extra income to the
operatives, especially rural dwellers, and inculcates a sense of
ownership resulting in a protective attitude towards the infrastructure.
The Uganda programmes have a very high level of funding by the
government, which is increased gradually over the years. This augers
well for the sustainability of the small scale contracting programmes.
Indeed the implementation of the already declared privatisation
programme of government will ensure more opportunities for the contracting
private sector.
Implementation of the recommendations cited above would definitely
improve on the quality and content of the future labour-based projects.
References
Road maintenance management guidelines August, 1993
Four year main road maintenance programme June, 1994
Four Year Main Road Maintenance Programme First Annual Progress
Report. April, 1995
Intech Beusch & Co. 1993. Labour based contract maintenance
programme orientation course for district engineer Intech Beusch
& Co. April, 1993
Ministry of Works, Transport and Communication (MOWTC) Works
contract (Labour-based)
Proposal for contractor training support, MOWTC. Dec. 1993
Transport Rehabilitation Project Feeder Roads Component. Implementation
manual Oct. 1994
Strategy for rural feeder roads rehabilitation and maintenance
March, 1992
Technical consulting mission in support of the labour intensive
works unit under MPED October 1996
|