|
Regional Seminar Papers 1997
Annex 1
Supporting Labour Cost Data
The data in this Annex has been used to prepare the Figures 2 &
3 in the main text.
Figure 2 – Unskilled Labour Wage
Rates 1991 – Construction Sector
Europe & Selected Economically Developed Countries
January 1991 wage rates
|
Country
|
Local
Currency
|
Unskilled wage rate
Local currency
|
Exchange rate
US$1 =
|
Hourly wage rate
US$ equivalent
|
Daily wage rate
US$ equivalent*
|
|
Austria
|
Asch
|
70.20
|
10.6
|
6.62
|
46.36
|
|
Cyprus
|
C£
|
2.60
|
0.43
|
6.05
|
42.33
|
|
Czechoslovakia
|
Kcs
|
17.76
|
26.9
|
0.66
|
4.62
|
|
Denmark
|
Dkr
|
125.00
|
5.82
|
21.48
|
150.34
|
|
Finland
|
Fmk
|
45.90
|
4.93
|
9.31
|
65.17
|
|
France
|
FFr
|
31.38
|
5.14
|
6.11
|
42.74
|
|
Germany (West)
|
DM
|
18.13
|
1.51
|
12.01
|
84.05
|
|
Greece
|
Dr
|
1,029.00
|
160
|
6.43
|
45.02
|
|
Ireland
|
IR£
|
3.82
|
0.57
|
6.70
|
46.91
|
|
Italy
|
Lire
|
13,580.00
|
1137
|
11.94
|
83.61
|
|
Japan
|
Yen
|
1,438.00
|
134
|
10.73
|
75.12
|
|
Luxembourg
|
LFr
|
540.00
|
31.2
|
17.1
|
121.15
|
|
Malta
|
ML
|
1.33
|
0.3
|
4.43
|
31.03
|
|
Norway
|
Nkr
|
75.80
|
5.91
|
12.83
|
89.78
|
|
Portugal
|
Esc
|
260.00
|
135
|
1.93
|
13.48
|
|
Spain
|
Pta
|
700.00
|
95
|
7.37
|
51.58
|
|
Sweden
|
SKr
|
89.00
|
5.65
|
15.75
|
110.27
|
|
Switzerland**
|
SFr
|
13.97
|
1.27
|
11.00
|
77.00
|
|
Turkey
|
TL
|
397
|
3123
|
0.13
|
0.89
|
|
United Kingdom
|
£
|
3.54
|
0.518
|
6.83
|
47.84
|
|
United States
|
US$
|
17.10
|
1
|
17.10
|
119.70
|
|
Ref: Spon's European Construction
Costs Handbook, 1992 Edition
|
Notes
*Assumes a 7 hour day
** Semi-skilled labourer
The cost of employing labour can be more than doubled
by the mandatory and voluntary additional payroll costs.
The wage rates are usually quoted for work in the capital city.
Figure 3 – Average Daily Agricultural Wages, 1991
Table 1
Extracted From: Yearbook of Labour Statistics, 1994, ILO Geneva
|
|
Daily Wage Rate
Local Currency
|
Currency
|
1991 US$
Exchange Rate
|
Daily Wage Rate
US$ Equiv.
|
Notes
|
|
1. Africa
|
|
|
|
|
|
|
Botswana
|
8.48
|
Pula
|
2.09
|
4.1
|
1
|
|
Burundi
|
389
|
Francs
|
125
|
3.1
|
1,2
|
|
Egypt
|
5.67
|
Pounds
|
2.71
|
2.1
|
3,4
|
|
Ghana
|
424
|
Cedis
|
192
|
2.2
|
1,5
|
|
Kenya
|
49
|
Shillings
|
29.0
|
1.7
|
1
|
|
Malawi
|
1.76
|
Kwacha
|
2.89
|
0.6
|
1
|
|
Mauritius
|
81
|
Rupees
|
16.7
|
4.9
|
|
|
Seychelles
|
77.5
|
Rupees
|
5.43
|
14.3
|
1
|
|
Swaziland
|
45.8
|
Emalangeni
|
2.35
|
19.5
|
1,5,9
|
|
Tunisia
|
3.76
|
Dinars
|
0.994
|
3.8
|
|
|
Zimbabwe
|
8.13
|
Dollars
|
3.79
|
2.1
|
1
|
Table 2
Extracted From: Yearbook of Labour Statistics, 1994, ILO Geneva
|
|
Daily Wage Rate
Local Currency
|
Currency
|
1991 US$
Exchange Rate
|
Daily Wage Rate
US$ Equiv.
|
Notes
|
|
2. Asia – Pacific
|
|
|
|
|
|
|
Australia
|
64.5
|
Dollars
|
1.29
|
50.0
|
3
|
|
Azerbaijan
|
10.4
|
Roubles
|
1.85
|
5.6
|
1
|
|
Bahrain
|
6.36
|
Dinars
|
0.375
|
17.0
|
1
|
|
Bangladesh
|
45.7
|
Taka
|
31.7
|
1.4
|
8,9
|
|
China
|
5.68
|
Yuan
|
5.49
|
1.0
|
1
|
|
Fiji
|
11.0
|
Dollars
|
1.49
|
7.4
|
4
|
|
India
|
23.3
|
Rupees
|
25.9
|
0.9
|
|
|
Japan
|
6,995
|
Yen
|
138
|
50.7
|
|
|
Myanmar
|
25.4
|
Kyat
|
6.49
|
3.9
|
1
|
|
Phillipines
|
57.7
|
Pesos
|
25.9
|
2.2
|
|
|
Singapore
|
29.3
|
Dollars
|
1.83
|
16.0
|
1,4
|
|
Sri Lanka
|
51
|
Rupees
|
41.9
|
1.2
|
|
Table 3
Extracted From: Yearbook of Labour Statistics, 1994, ILO Geneva
|
Daily Wage Rate
Local Currency
|
Currency
|
1991 US$
Exchange Rate
|
Daily Wage Rate
US$ Equiv.
|
Notes
|
|
3. Americas
|
|
|
|
|
|
|
Barbados
|
39
|
Dollars
|
2.01
|
19.4
|
3
|
|
Bermuda
|
84.3
|
Dollars
|
1.00
|
84.3
|
7,8
|
|
Canada
|
117
|
Dollars
|
1.15
|
101.7
|
3,10
|
|
Costa Rica
|
661
|
Colones
|
127
|
5.2
|
1
|
|
Cuba
|
7.4
|
Pesos
|
0.770
|
9.6
|
1,5
|
|
Falkland Islands
|
13.7
|
Pounds
|
0.567
|
24.2
|
1,4
|
|
Paraguay
|
6,753
|
Guaranies
|
1,316
|
5.1
|
1
|
|
Peru
|
4.04
|
Nuevos Soles
|
0.80
|
5.1
|
1
|
|
Uruguay
|
6,141
|
Nuevos Pesos
|
2,100
|
2.9
|
1,4
|
Table 4
Extracted From: Yearbook of Labour Statistics, 1994, ILO Geneva
|
|
Daily Wage Rate
Local Currency
|
Currency
|
1991 US$
Exchange Rate
|
Daily Wage Rate
US$ Equiv.
|
Notes
|
|
4. Europe
|
|
|
|
|
|
|
Albania
|
26.5
|
Leks
|
6.01
|
4.4
|
1
|
|
Belarus
|
19.9
|
Roubles
|
1.85
|
10.8
|
1
|
|
Bulgaria
|
37.4
|
Leva
|
19.0
|
2.0
|
1
|
|
Croatia
|
315
|
New Dinar
|
23.3
|
13.5
|
1
|
|
Czechoslovakia
|
149
|
Koruna
|
31.4
|
4.7
|
1
|
|
Estonia
|
25.6
|
Kroons
|
13.6
|
1.9
|
6
|
|
Germany
|
89.7
|
Marks
|
1.82
|
49.3
|
7
|
|
Hungary
|
441
|
Florint
|
78.5
|
5.6
|
1
|
|
Ireland
|
20.3
|
Pounds
|
0.617
|
32.9
|
3,4
|
|
Latvia
|
1.56
|
Lats
|
0.656
|
2.4
|
6
|
|
Moldova
|
10.37
|
Roubles
|
1.85
|
5.6
|
1
|
|
Norway
|
356
|
Kroner
|
6.73
|
52.9
|
1,2
|
|
Poland
|
65,100
|
Zloty
|
11,611
|
5.6
|
1
|
|
Romania
|
255
|
Lei
|
63.1
|
4.0
|
1
|
|
Russian Federation
|
18.3
|
Roubles
|
1.85
|
9.9
|
1
|
|
Slovakia
|
148
|
Koruna
|
31.4
|
4.7
|
1
|
|
Spain
|
2724
|
Pesetas
|
113
|
24.1
|
|
|
Sweden
|
591
|
Kronor
|
6.58
|
89.8
|
7
|
|
Switzerland
|
135
|
Francs
|
1.55
|
87.1
|
7
|
|
Turkey
|
47283
|
Liras
|
4,668
|
10.1
|
|
|
Ukraine
|
7.66
|
Roubles
|
0.632
|
12.1
|
1,5
|
|
United Kingdom
|
31.8
|
Pounds
|
0.613
|
51.1
|
3
|
Notes
Exchange rates: Financial Times 20 August 1991, unless otherwise
indicated
- Monthly rates divided by 25
- 1987 data
- Weekly rate divided by 6
- 1990 data
- 1988 data
- 1993 data
- Hourly rates times 7
- 1989 data
- Skilled workers
- Forestry
Annex 2
Supporting equipment cost data
The data in this Annex has been used to prepare Figure 7 in the
main text. The costing method used for this example figure has been
developed for the MART equipment guidelines which are currently
under preparation.
The costing method is designed to include all cost components relating
to the ownership, operation and overheads components. The approach
may be used for any type of intermediate or sophisticated equipment.
The system allows the owner/user to make assumptions regarding
the many variables affecting the cost of a piece of equipment. It
must be appreciated that the actual overall costs will not be known
until the day the piece of equipment is actually sold or scrapped
(if adequate records have been kept throughout the equipment
ownership). Costing therefore depends on good record keeping and
a realistic appreciation and assessment of a range of important
historical, current and future factors.
The system intends to highlight the real costs of financing and
ownership which are neglected in many equipment management systems,
and which can dwarf operating costs in a high-cost-finance environment;
thus possibly adversely affecting management decisions on choice
of technology or equipment. Costs are particularly sensitive to
annual utilisation as Tables A & B show. Whereas many equipment
items are designed to achieve annual utilisation of 1,000 to 1,500
hours of work for economic ownership, significantly lower utilisation
can be extremely expensive and uneconomic. The system demonstrates
that, for most roadworks in developing countries, the operating
environment is particularly unfavourable to the use of sophisticated
plant.
The costing system should allow contractors to quickly assess the
affects of various assumptions or scenarios and how this will affect
their income, outgoings and profits.
For Figure 7, the costing system has been used to compare the costs
of a 120 hp motorgrader with a 100 hp 4WD agricultural tractor and
heavy towed grader. Both machines are capable of similar physical
performance as demonstrated by the Roads 2000 project in
Kenya (Reference 19). The motorgrader hourly physical output is
expected to be some 20% higher than the tractor and towed grader
combination. However, the higher availability and flexibility of
tractor use should allow higher utilisation and therefore much lower
unit work costs.
For the Annex 2 calculation example, the following assumptions
were made:-
|
Assumption
|
Motorgrader
|
Towed Grader
|
|
Finance Interest Charge
|
20% per annum
|
20% per annum
|
|
Purchase Cost assumed in Tables A & B
|
US$ 200,000
|
US$ 90,000
|
|
Actual Purchase Cost (adjustment)
|
US$ 195,000
|
US$ 88,000
|
|
Economic Life
|
12 years
|
10 years
|
|
Annual Utilisation (hours)
|
600 (e.g. 100 days @ 6 hours)
|
800 hours
|
Other annual utilisation assumptions were used to plot Figure 7.
COST CALCULATION 100 hp 4WD TRACTOR + TOWED GRADER (5t)
SHEET 1
TOTAL HOURLY CHARGE COMPRISES OWNERSHIP + OPERATING + OVERHEAD COSTS
OWNERSHIP COSTS COMPRISE:-
DEPRECIATION/REPLACEMENT (TABLE A1) PLUS FINANCE CHARGE (TABLE
B1, B2 OR B3)
ALL TABLE A & B COSTS IN US$/HOUR
COST NEW - US$ 90,000 (INCLUDING ALL TAXES, DUTIES, CIF &
DELIVERY CHARGES)
|
A1 – DEPRECIATION/REPLACEMENT CHARGE IN US$/HOUR
|
|
ECONOMIC LIFE
|
UTILISATION IN HOURS/YEAR
|
|
YEARS
|
200
|
400
|
600
|
800
|
1,000
|
1,200
|
1,400
|
1,600
|
|
1
|
450
|
225
|
150
|
113
|
90
|
75
|
64
|
56
|
|
2
|
225
|
113
|
75
|
56
|
45
|
38
|
32
|
28
|
|
3
|
150
|
75
|
50
|
38
|
30
|
25
|
21
|
19
|
|
4
|
113
|
56
|
38
|
28
|
23
|
19
|
16
|
14
|
|
5
|
90
|
45
|
30
|
23
|
18
|
15
|
13
|
11
|
|
6
|
75
|
38
|
25
|
19
|
15
|
13
|
11
|
9
|
|
7
|
64
|
32
|
21
|
16
|
13
|
11
|
9
|
8
|
|
8
|
56
|
28
|
19
|
14
|
11
|
9
|
8
|
7
|
|
9
|
50
|
25
|
17
|
13
|
10
|
8
|
7
|
6
|
|
10
|
45
|
23
|
15
|
11
|
9
|
8
|
6
|
6
|
|
11
|
41
|
20
|
14
|
10
|
8
|
7
|
6
|
5
|
|
12
|
38
|
19
|
13
|
9
|
8
|
6
|
5
|
5
|
|
B1 – FINANCE @
|
10%
|
FINANCE CHARGE IN US$/HOUR
|
|
ECONOMIC LIFE
|
UTILISATION IN HOURS/YEAR
|
|
YEARS
|
200
|
400
|
600
|
800
|
1,000
|
1,200
|
1,400
|
1,600
|
|
1
|
45
|
23
|
15
|
11
|
9
|
8
|
6
|
6
|
|
2
|
34
|
17
|
11
|
8
|
7
|
6
|
5
|
4
|
|
3
|
30
|
15
|
10
|
8
|
6
|
5
|
4
|
4
|
|
4
|
28
|
14
|
9
|
7
|
6
|
5
|
4
|
4
|
|
5
|
27
|
14
|
9
|
7
|
5
|
5
|
4
|
3
|
|
6
|
26
|
13
|
9
|
7
|
5
|
4
|
4
|
3
|
|
7
|
26
|
13
|
9
|
6
|
5
|
4
|
4
|
3
|
|
8
|
25
|
13
|
8
|
6
|
5
|
4
|
4
|
3
|
|
9
|
25
|
13
|
8
|
6
|
5
|
4
|
4
|
3
|
|
10
|
25
|
12
|
8
|
6
|
5
|
4
|
4
|
3
|
|
11
|
25
|
12
|
8
|
6
|
5
|
4
|
4
|
3
|
|
12
|
24
|
12
|
8
|
6
|
5
|
4
|
3
|
3
|
|
B2 – FINANCE @
|
20%
|
FINANCE CHARGE IN US$/HOUR
|
|
ECONOMIC LIFE
|
UTILISATION IN HOURS/YEAR
|
|
YEARS
|
200
|
400
|
600
|
800
|
1,000
|
1,200
|
1,400
|
1,600
|
|
1
|
90
|
45
|
30
|
23
|
18
|
15
|
13
|
11
|
|
2
|
68
|
34
|
23
|
17
|
14
|
11
|
10
|
8
|
|
3
|
60
|
30
|
20
|
15
|
12
|
10
|
9
|
8
|
|
4
|
56
|
28
|
19
|
14
|
11
|
9
|
8
|
7
|
|
5
|
54
|
27
|
18
|
14
|
11
|
9
|
8
|
7
|
|
6
|
53
|
26
|
18
|
13
|
11
|
9
|
8
|
7
|
|
7
|
51
|
26
|
17
|
13
|
10
|
9
|
7
|
6
|
|
8
|
51
|
25
|
17
|
13
|
10
|
8
|
7
|
6
|
|
9
|
50
|
25
|
17
|
13
|
10
|
8
|
7
|
6
|
|
10
|
50
|
25
|
17
|
12
|
10
|
8
|
7
|
6
|
|
11
|
49
|
25
|
16
|
12
|
10
|
8
|
7
|
6
|
|
12
|
49
|
24
|
16
|
12
|
10
|
8
|
7
|
6
|
|
B3 – FINANCE @
|
30%
|
FINANCE CHARGE IN US$/HOUR
|
|
ECONOMIC LIFE
|
UTILISATION IN HOURS/YEAR
|
|
YEARS
|
200
|
400
|
600
|
800
|
1,000
|
1,200
|
1,400
|
1,600
|
|
1
|
135
|
68
|
45
|
34
|
27
|
23
|
19
|
17
|
|
2
|
101
|
51
|
34
|
25
|
20
|
17
|
14
|
13
|
|
3
|
90
|
45
|
30
|
23
|
18
|
15
|
13
|
11
|
|
4
|
84
|
42
|
28
|
21
|
17
|
14
|
12
|
11
|
|
5
|
81
|
41
|
27
|
20
|
16
|
14
|
12
|
10
|
|
6
|
79
|
39
|
26
|
20
|
16
|
13
|
11
|
10
|
|
7
|
77
|
39
|
26
|
19
|
15
|
13
|
11
|
10
|
|
8
|
76
|
38
|
25
|
19
|
15
|
13
|
11
|
9
|
|
9
|
75
|
38
|
25
|
19
|
15
|
13
|
11
|
9
|
|
10
|
74
|
37
|
25
|
19
|
15
|
12
|
11
|
9
|
|
11
|
74
|
37
|
25
|
18
|
15
|
12
|
11
|
9
|
|
12
|
73
|
37
|
24
|
18
|
15
|
12
|
10
|
9
|
100 hp 4WD TRACTOR + TOWED GRADER (5t) sheet 2
| |
CONVERSION TO
DAILY CHARGE RATE |
|
|
|
| |
|
INTEREST RATE ASSUMED
20% |
| |
OWNERSHIP COSTS |
|
|
|
|
| |
|
|
|
|
|
| C |
ADJUSTMENT FOR ACTUAL
COST OF PURCHASE |
|
|
|
|
| |
Selected Depreciation/replacement
charge (US$/hr) from Table A1 |
11 |
(C1) |
|
|
| |
Selected Finance
charge (US$/hr) from Table B1, B2 or B3 |
12 |
(C2) |
|
|
| |
Actual purchase/replacement
cost in US$ |
88,000 |
(C3) |
|
|
| |
Assumed number of
operating hours per day |
6 |
(C4) |
local currency
|
| |
DAILY OWNERSHIP
COST = (C1 + C2) x C4 x C3 / 90,000 = |
US$/day |
134.9 |
|
(C) |
| |
|
|
|
|
|
| D |
ADJUSTMENT FOR EXPECTED
RESIDUAL/SCRAP VALUE (IF ANY) |
|
|
|
|
| |
Assumed Residual/Scrap
Value in US$ |
5,000 |
(D1) |
|
|
| |
Assumed Economic
Life in years |
10 |
(D2) |
|
|
| |
Assumed Utilisation
in Hours/Year |
800 |
(D3) |
local currency
|
| |
ADJUSTMENT FOR SCRAP
VALUE = (D1 x C4) / (D2 x D3) |
US$/day |
3.8 |
|
(D) |
| |
SUB-TOTAL FOR OWNERSHIP COSTS |
131.2 |
|
(X) |
| |
OPERATING COSTS |
|
|
|
|
| E |
SPARES & CONSUMABLES |
|
|
|
|
| |
Either predict daily
costs from past records or select from the following:- |
|
|
|
|
| |
Select percentage
of spares and consumables per year compared to machine cost
new, |
|
|
|
|
| |
Suggested value
between 5% and 12% (usually increases with age) |
8 |
% (E1) |
local currency
|
| |
DAILY COST OF SPARES
= 0.01 x C3 x C4 x E1 / D3 |
US$/day |
52.8 |
|
(E) |
| |
|
|
|
|
|
| F |
SERVICING AND REPAIR
(WORKSHOP LABOUR COSTS) |
|
|
|
|
| |
Either predict daily
costs from past records or select the following:- |
|
|
local currency
|
| |
Suggested value
between 25% and 100% of (E) |
US$/day |
13.2 |
|
(E) |
| |
|
|
|
|
|
| G |
FUEL & LUBRICANTS |
|
|
|
|
| |
Cost of fuel per
litre (add between 2 and 5% to cover lubricant costs |
0.4 |
(G1) |
|
|
| |
Assumed fuel consumption
in litres per hour |
15 |
(G2) |
local currency
|
| |
DAILY FUEL COST
= C4 x G1 x G2 |
US$/day |
36.0 |
|
(G) |
| H |
OPERATORS (DAILY
COSTS)
|
|
|
|
| |
|
Wages |
Allowances |
Other |
|
|
|
| |
Operator |
12 |
8 |
3 |
|
|
|
| |
Assistant |
10 |
8 |
3 |
|
|
|
| |
Banksman |
6 |
- |
- |
|
local currency |
| |
Subtotals |
28 |
16 |
6 |
US$/day |
50.0 |
(H) |
| |
|
SUB-TOTAL FOR
OPERATING COSTS |
152.0 |
(Y) |
| OVERHEADS (& PROFIT) |
|
|
| Predict from past records to
include:- |
|
|
| Offices, Workshops, Tools &
other Facilities |
|
|
| Supervisory, management and
clerical personnel |
|
|
| Supervision and support vehicles |
|
|
| Stores and other stock |
|
|
| Insurances |
|
|
| Banking and other finance charges
not relating to the equipment item |
|
|
| Admin, training, safety or other
overhead costs |
|
|
| Risk, late payment and other
contingency items |
|
|
| Profit |
|
local currency |
| SUB-TOTAL
FOR OVERHEADS AND PROFIT |
100.0 |
| |
|
local currency |
| TOTAL COST TO BE CHARGED
= X + Y + Z |
US$/day |
383.2 |
NOTES
1. Finance charge (overleaf) calculated by the formula:-
| C2 = ((N + 1) / 2N) x Purchase
Price x Interest rate expressed as a decimal |
| Hours per year |
| Where N = number of years (economic
life) |
| Ref: costs2bb |
COST CALCULATION 120 Hp MOTORGRADER
SHEET 1
TOTAL HOURLY CHARGE COMPRISES OWNERSHIP + OPERATING + OVERHEAD
COSTS
OWNERSHIP COSTS COMPRISE:-
DEPRECIATION/REPLACEMENT (TABLE A1) PLUS FINANCE CHARGE (TABLE
B1, B2 OR B3)
ALL TABLE A & B COSTS IN US$/HOUR
COST NEW – US$ 200,000 (INCLUDING ALL TAXES, DUTIES, CIF &
DELIVERY CHARGES)
|
A-1 – Depreciation/Replacement Charge in US$/Hour
|
|
Economic Life
|
Utilisation in Hours/Year
|
|
Years
|
200
|
400
|
600
|
800
|
1,000
|
1,200
|
1,400
|
1,600
|
|
1
|
1,000
|
500
|
333
|
250
|
200
|
167
|
143
|
125
|
|
2
|
500
|
250
|
167
|
125
|
100
|
83
|
71
|
63
|
|
3
|
333
|
167
|
111
|
83
|
67
|
56
|
48
|
42
|
|
4
|
250
|
125
|
83
|
63
|
50
|
42
|
36
|
31
|
|
5
|
200
|
100
|
67
|
50
|
40
|
33
|
29
|
25
|
|
6
|
167
|
83
|
56
|
42
|
33
|
28
|
24
|
21
|
|
7
|
143
|
71
|
48
|
36
|
29
|
24
|
20
|
18
|
|
8
|
125
|
63
|
42
|
31
|
25
|
21
|
18
|
16
|
|
9
|
111
|
56
|
37
|
28
|
22
|
19
|
16
|
14
|
|
10
|
100
|
50
|
33
|
25
|
20
|
17
|
14
|
13
|
|
11
|
91
|
45
|
30
|
23
|
18
|
15
|
13
|
11
|
|
12
|
83
|
42
|
28
|
21
|
17
|
14
|
12
|
10
|
|
B1 – Finance @
|
10%
|
Finance Charge in US$/Hour
|
|
Economic Life
|
Utilisation in Hours/Year
|
|
Years
|
200
|
400
|
600
|
800
|
1,000
|
1,200
|
1,400
|
1,600
|
|
1
|
100
|
50
|
33
|
25
|
20
|
17
|
14
|
13
|
|
2
|
75
|
38
|
25
|
19
|
15
|
13
|
11
|
9
|
|
3
|
67
|
33
|
22
|
17
|
13
|
11
|
10
|
8
|
|
4
|
63
|
31
|
21
|
16
|
13
|
10
|
9
|
8
|
|
5
|
60
|
30
|
20
|
15
|
12
|
10
|
9
|
8
|
|
6
|
58
|
29
|
19
|
15
|
12
|
10
|
8
|
7
|
|
7
|
57
|
29
|
19
|
14
|
11
|
10
|
8
|
7
|
|
8
|
56
|
28
|
19
|
14
|
11
|
9
|
8
|
7
|
|
9
|
56
|
28
|
19
|
14
|
11
|
9
|
8
|
7
|
|
10
|
55
|
28
|
18
|
14
|
11
|
9
|
8
|
7
|
|
11
|
55
|
27
|
18
|
14
|
11
|
9
|
8
|
7
|
|
12
|
54
|
27
|
18
|
14
|
11
|
9
|
8
|
7
|
|
B2 – Finance@
|
20%
|
Finance Charge in US$/Hour
|
|
Economic Life
|
Utilisation in Hours/Year
|
|
Years
|
200
|
400
|
600
|
800
|
1,000
|
1,200
|
1,400
|
1,600
|
|
1
|
200
|
100
|
67
|
50
|
40
|
33
|
29
|
25
|
|
2
|
150
|
75
|
50
|
38
|
30
|
25
|
21
|
19
|
|
3
|
133
|
67
|
44
|
33
|
27
|
22
|
19
|
17
|
|
4
|
125
|
63
|
42
|
31
|
25
|
21
|
18
|
16
|
|
5
|
120
|
60
|
40
|
30
|
24
|
20
|
17
|
15
|
|
6
|
117
|
58
|
39
|
29
|
23
|
19
|
17
|
15
|
|
7
|
114
|
57
|
38
|
29
|
23
|
19
|
16
|
14
|
|
8
|
113
|
56
|
38
|
28
|
23
|
19
|
16
|
14
|
|
9
|
111
|
56
|
37
|
28
|
22
|
19
|
16
|
14
|
|
10
|
110
|
55
|
37
|
28
|
22
|
18
|
16
|
14
|
|
11
|
109
|
55
|
36
|
27
|
22
|
18
|
16
|
14
|
|
12
|
108
|
54
|
36
|
27
|
22
|
18
|
15
|
14
|
|
B3 – Finance @
|
30%
|
Finance Charge in US$/Hour
|
|
Economic Life
|
Utilisation in Hours/Year
|
|
Years
|
200
|
400
|
600
|
800
|
1,000
|
1,200
|
1,400
|
1,600
|
|
1
|
300
|
150
|
100
|
75
|
60
|
50
|
43
|
38
|
|
2
|
225
|
113
|
75
|
56
|
45
|
38
|
32
|
28
|
|
3
|
200
|
100
|
67
|
50
|
40
|
33
|
29
|
25
|
|
4
|
188
|
94
|
63
|
47
|
38
|
31
|
27
|
23
|
|
5
|
180
|
90
|
60
|
45
|
36
|
30
|
26
|
23
|
|
6
|
175
|
88
|
58
|
44
|
35
|
29
|
25
|
22
|
|
7
|
171
|
86
|
57
|
43
|
34
|
29
|
24
|
21
|
|
8
|
169
|
84
|
56
|
42
|
34
|
28
|
24
|
21
|
|
9
|
167
|
83
|
56
|
42
|
33
|
28
|
24
|
21
|
|
10
|
165
|
83
|
55
|
41
|
33
|
28
|
24
|
21
|
|
11
|
164
|
82
|
55
|
41
|
33
|
27
|
23
|
20
|
|
12
|
163
|
81
|
54
|
41
|
33
|
27
|
23
|
20
|
Ownership, operating and overhead costs are calculated on sheet
2:-
COST CALCULATION 120 Hp MOTORGRADER
SHEET 2
CONVERSION TO DAILY CHARGE RATE
|
|
INTEREST RATE ASSUMED
20% |
| |
OWNERSHIP COSTS |
|
|
|
|
| C |
ADJUSTMENT FOR ACTUAL
COST OF PURCHASE |
|
|
|
|
| |
Selected Depreciation/replacement
charge (US$/hr) from Table A1 |
28 |
(C1) |
|
|
| |
Selected Finance
charge (US$/hr) from Table B1, B2 or B3 |
36 |
(C2) |
|
|
| |
Actual purchase/replacement
cost in US$ |
195,000 |
(C3) |
|
|
| |
Assumed number of
operating hours per day |
6 |
(C4) |
local currency
|
| |
DAILY OWNERSHIP
COST = (C1 + C2) x C4 x C3 / 200,000 = |
US$/day |
374.4 |
|
(C) |
| |
|
|
|
|
|
| D |
ADJUSTMENT FOR EXPECTED
RESIDUAL/SCRAP VALUE (IF ANY) |
|
|
|
|
| |
Assumed Residual/Scrap
Value in US$ |
10,000 |
(D1) |
|
|
| |
Assumed Economic
Life in years |
12 |
(D2) |
|
|
| |
Assumed Utilisation
in Hours/Year |
600 |
(D3) |
local
currency |
| |
ADJUSTMENT FOR SCRAP
VALUE = (D1 x C4) / (D2 x D3) |
US$/day |
8.3 |
|
(D) |
| |
SUB-TOTAL FOR OWNERSHIP
COSTS |
366.1 |
|
(X) |
| |
|
|
|
|
|
| |
OPERATING COSTS |
|
|
|
|
| |
|
|
|
|
|
| E |
SPARES & CONSUMABLES |
|
|
|
|
| |
Either predict daily
costs from past records or select from the following:- |
|
|
|
|
| |
Select percentage
of spares and consumables per year compared to machine cost
new, |
|
|
|
|
| |
Suggested value
between 5% and 12% (usually increases with age) |
8 |
% (E1) |
local
currency |
| |
DAILY COST OF SPARES
= 0.01 x C3 x C4 x E1 / D3 |
US$/day |
156.0 |
|
(E) |
| |
|
|
|
|
|
| F |
SERVICING AND REPAIR
(WORKSHOP LABOUR COSTS) |
|
|
|
|
| |
Either predict daily
costs from past records or select the following:- |
|
|
local
currency |
| |
Suggested value
between 25% and 100% of (E) |
US$/day |
39.0 |
|
(E) |
| |
|
|
|
|
|
| G |
FUEL & LUBRICANTS |
|
|
|
|
| |
Cost of fuel per
litre (add between 2 and 5% to cover lubricant costs |
0.4 |
(G1) |
|
|
| |
Assumed fuel consumption
in litres per hour |
18 |
(G2) |
local
currency |
| |
DAILY FUEL COST
= C4 x G1 x G2 |
US$/day |
43.2 |
|
(G) |
| |
|
|
|
|
|
| H |
OPERATORS
(DAILY COSTS) |
|
|
|
|
|
|
|
|
|
Wages |
Allowances |
Other |
|
|
|
|
|
|
Operator |
12 |
8 |
3 |
|
|
|
|
|
|
Assistant |
- |
- |
- |
|
|
|
|
|
|
Banksman |
6 |
- |
- |
|
|
local currency |
|
|
Subtotals |
18 |
8 |
3 |
US$/day |
29.0 |
|
(H) |
|
|
|
|
SUB-TOTAL FOR OPERATING COSTS |
267.2 |
|
(Y) |
|
OVERHEADS
(& PROFIT) |
|
|
|
| |
Predict from past records to include:- |
|
|
|
| |
Offices, Workshops, Tools & other Facilities |
|
|
|
| |
Supervisory, management and clerical personnel |
|
|
|
| |
Supervision and support vehicles |
|
|
|
| |
Stores and other stock |
|
|
|
| |
Insurances |
|
|
|
| |
Banking and other finance charges not relating to the equipment
item |
|
|
|
| |
Admin, training, safety or other overhead costs |
|
|
|
| |
Risk, late payment and other contingency items |
|
|
|
| |
Profit |
|
local currency |
| |
SUB-TOTAL FOR OVERHEADS AND PROFIT |
200.0 |
|
| |
|
|
local currency |
|
TOTAL COST
TO BE CHARGED = X + Y + Z |
US$/day |
833.3 |
|
NOTES
1 Finance charge (overleaf) calculated by the formula:-
| C2 = ((N + 1) / 2N) x Purchase
Price x Interest rate expressed as a decimal
|
| |
Hours per year |
| Where N = number
of years (economic life) |
| |
Ref: costs1bb
|
Annex 3
Manufacturer's details
Arthur Garden Engineering
Galion House, Douglas & Dumphries Roads, Heavy Industrial Sites,
Harare, Zimbabwe.
Tel: Int + 263 4 754272
Fax: Int + 263 4 754274
Colas Limited
Rowfant, Crawley, West Sussex, RH10 4NF, UK.
Tel: Int. + 44 (0) 1342 711000 Fax: Int. + 44 (0) 1342 711198/99
e-mail: StevenStJ@colas-ltd.demon.co.uk
The Phoenix Engineering Company Ltd
Phoenix Works, Chard, Somerset, TA 20 1JE, UK.
Tel: Int. + 44 (0) 1460 63531/2/3
Fax: Int. + 44 (0) 1460 67388
Reynolds International Inc
P O Box 550, McAllen, Texas 78505, USA.
Tel: Int + 1 210 687 7500
Fax: Int. + 1 210 630 5263
Simba International Ltd
Woodbridge Road, Sleaford, Lincolnshire, NG34 7EW, UK.
Tel: Int. + 44 (0) 1529 304654
Fax: Int. + 44 (0) 1529 413468
TBF Thompson (Engineering) Ltd
6-10 Killyvalley Road, Garvagh, Coleraine, Co. Londonderry, Northern
Ireland, BT51 5JZ, UK.
Tel: Int. + 44 (0) 12665 58771
Fax: Int. + 44 (0) 12665 58906
Tinto
Hästt Zimbabwe, No 6 Nuffield Road, P O Box 2356, Harare,
Zimbabwe.
Tel: Int + 263 4 756445/9
Fax: Int + 263 4 64726, 754333/6; 757000/3;
Turbomech
Cooper Motor Corporation, Agricultural Division, P O Box 30135,
Nairobi, Kenya.
Tel: Int + 254 2 544505
Fax: Int + 254 2 542543
Development
of Appropriate Compaction Equipment for Labour-based Gravelling
Operations
Carl-Eric Hedström, Chief Technical Advisor, Labour-Based
Component, Roads Training School, Roads Department, Zambia
Background
The Labour-based Road Improvement and Maintenance Project in the
Northern Province of Zambia was transferred to Lusaka in June 1994.
This project had been operational in Northern Province for about
seven years under a NORAD supported Agricultural and Rural Development
Programme.
The main objectives were to demonstrate and establish labour-based
methods of road construction and maintenance by improving access
to agriculturally productive areas in Northern Province.
The type of roads worked on were in most cases unclassified low
traffic volume roads with a four metre carriageway. Compaction was
achieved through a combination of natural consolidation and traffic
compaction, or in exceptional cases by very light rollers for initial
compaction.
However, in Lusaka, the Labour-based Project is part of a NORAD
supported Road Sector Programme. It operates under the auspices
of the Roads Department on classified roads, whose specification
and traffic loads in most cases require compaction of the gravel
layer.
The Challenge
The project operates a fleet of tractor-towed light equipment for
road works. This equipment includes tractor-towed trailers (designed
in Kenya with support from ASIST2), water bowsers
(from Tinto Ltd) and compaction rollers (project designed). When
we commenced our operations in Lusaka we borrowed pedestrian vibrating
rollers from the Provincial Road Engineer (PRE) in Lusaka. These
rollers had been left behind by an earlier phased-out labour-based
project. We also immediately placed an order for two new pedestrian
vibrating rollers, assuming that this type of equipment must be
well tested since it is widely used on labour-based projects. However,
after only six months of use, they started having frequent breakdowns.
These were caused by the unfamiliarity of the operators with the
precision of operation and maintenance required, and a concomitant
shortage of mechanics who were familiar with the complexity of the
machine. A great deal of down time was also spent awaiting the arrival
of spare parts ordered from Europe or South Africa at exorbitant
prices for quick delivery. It should be understood that we do not
have a country agent for this equipment and consequently there is
neither a stock of spare parts nor mechanics in Zambia acquainted
with pedestrian vibrating rollers.
It thus became very clear to the labour-based project staff that
an alternative to this machine needed to be investigated.
On the one hand, they recognised that a pedestrian vibrating roller
provides a lot of flexibility to the work planner, and its use can
be justified under certain circumstances. This is especially true
when the agricultural tractor concept for towing of trailers, water
bowsers etc. is not an option due to haulage distances beyond the
economical use of tractors and trailers; or when the tractor would
only be used for towing a roller. The pedestrian vibrating roller
can also be justified on steep gradients, or when particular soil
types cannot be economically compacted without a vibrating roller.
But on the other hand, since Zambia is predominantly flat and blessed
with reasonably good natural soils (except for areas in Western
and North-western Provinces, which have very difficult sandy soils
of the type often found in Botswana), pedestrian vibrating rollers
were not considered essential. This is especially true for gravelling
works on a contractor development programme where durability is
essential in order to allow the emerging contractor to meet production
targets and to be able to repay the equipment loan in a reasonable
period of time.
The experiences outlined above are apparently also shared by other
labour-based practitioners. They are areas of concern in many other
countries and were very clearly expressed in a paper presented at
the Fifth Regional Seminar for Labour-based Practitioners held in
Ghana in April, 1996 by Henry Danso from the Department of Feeder
Roads, Koforidua, Ghana. In his paper entitled Factors influencing
the output of labour-based contractors in Ghana he states:
Frequent Breakdown of Rollers:
In most rural areas, the back-up services required to minimise
the problems posed by the frequent breakdown of the vibratory
rollers are not available. Where mechanics are available, they
are not adequately equipped to deal with the problem. This,
coupled with the non-availability of spares on the market within
the vicinity of the sites, has resulted in utilisation rates
falling below 50%, thus affecting the performance of the contractor.
In some instances, the breakdown of rollers leads to suspension
of earthworks and gravelling for more than two months.
Meeting the Challenge
Needless to say we share the views of Eng Danso on this subject,
and hence the need to develop an alternative to pedestrian vibrating
rollers. In our Contractor Development Programme for rehabilitation
contractors, we are using the platform method for rehabilitation
works3. This means that compaction
is sometimes required at four stages, subgrade, plug, camber formation,
and gravelling. If 100% gravelling is required on a five metre wide
carriageway, and if the production target is 2km per month, then
1,500m3 of gravel will have to be compacted per month
in addition to the subgrade, plug, and camber formation. This totals
15,000m3 of gravel per year (ten months of production).
In a project where the repayment period for a fleet of equipment
on loan to the contractor has been set at four years, this amount
of gravelling totals 60,000m3 over the four years. Moreover,
in this scenario, it is assumed that no piece of equipment will
be replaced during this four year period. Hence the need for well
designed, very durable and appropriate equipment.
Admittedly, one has to be a much better work planner when using
tractor-towed dead-weight rollers which have to share tractor time
with trailers and bowsers, than if one has a number of pedestrian
vibrating rollers at one's disposal. But with good daily planning
of the use of the tractor, it is possible to maintain a good production
even with a tractor-towed roller, if the tractor-shared operations
are well planned. This means watering very late in the afternoon
up to sunset in order for the gravel to retain its moisture over
the night. Rolling then starts early in the morning with an ideal
moisture content. Thereafter, the tractor is used for hauling of
gravel, that is during the middle of the day. However, if the natural
gravel contains sufficient moisture, it should be heaped along the
road and not spread. In this way the gravel will retain its moisture
while a sufficient quantity of material is piled up to justify bringing
along the roller.
Roller design parameters
We were thus determined to design a tractor-towed dead-weight roller
with good production capacity. It had to be very robust and with
a higher weight to width roller ratio (linear load) than we had
earlier seen used on labour-based projects. We had in mind a ratio
of 3 tonnes per metre drum width. This would give a total ballasted
weight of about 4.5 tonnes and, when empty, a weight of 1.5 tonnes.
This would make it easy to transport.
We should like to mention here that the inspiration to design and
locally manufacture this type of roller came from the Training Modules
from Thailand, and from CTP 64 Pilot project on labour-based
road construction and maintenance in Thailand – Compaction
by labour compatible equipment by Lars Karlsson.
Roller (1): Single drum
The first roller was designed with the following dimensions/specifications:
|
Function
|
Dead-weight roller to be pulled by a 60 - 70 hp agricultural
tractor. In mountainous areas the tractor should preferably
be equipped with four-wheel drive. In undulating terrain it
is sufficient to improve traction by filling the rear tyres
with water (75%) and by ballasting the front of the tractor
using front-end weights or water.
|
|
Overall design
|
A hollow steel roller mounted in a frame, with a towing bar
attached, and with a steel bucket sitting on top of the frame
|
|
Transportation
(Mode of transport)
|
Shipping weight is 1,700kg
Can be loaded onto the ASIST-promoted trailer; or transported
on a specially built low-bed trailer as used for pedestrian
vibrating-rollers; or by attached transport wheels (currently
under design); or of course on a truck.
|
|
Operating weight
|
Empty is 17,00kg; ballasted with water in the drum is 2,600kg;
and fully ballasted with water and stone is approximately
4,500kg.
The ‘bucket over a drum' design feature allows for a number
of weight combinations, and an initial pass can be made with
a lower weight, thus avoiding material being pushed in front
of the steel drum.
|
|
Volume of bucket
|
Approximately 1.2m3. Ballasted with soil this
gives an added weight of about 2 tonnes.
|
|
Drum dimensions
|
Single drum diameter is 1,000mm and width is 1,200mm; volume
is 0.94m3. Manufactured from 20mm thick steel plate.
The drum can be ballasted with water, which gives an added
weight of 940kg.
|
|
Compaction characteristics
|
Static linear load (empty) = 1.4 tonne/m
Static linear load (filled with water) = 2.2 tonne/m
Static linear load fully ballasted = 3.87 tonne/m
|
|
Manoeuvrability
|
Outer turning radius when tractor is attached is rather large
(about 4.25m) which means turning on a typical feeder road
is time consuming and difficult if the side slopes are not
used. Therefore, the drawbar arrangement of Roller (2), with
a detachable drawbar which can be fixed at both front and
rear ends is to be preferred. Working speed is maximum 3km/hour.
Transport speed (towed) is maximum 10km/hour
|
|
Manufacturing and cost
|
The roller was locally manufactured in Lusaka by a mechanical
engineering firm. The cost was US$ 3,705 including development
costs (but not including project staff costs). This roller
was delivered in April 1995 and has been in operation ever
since, without any breakdown. Hence the design parameters
seem appropriate for its purpose.
|
|
Performance (Mechanical)
|
The roller has fulfilled all expectations when it comes to
achieved compaction results. This proves that the chosen linear
load was correctly assumed. Its durability has also been exemplary
as it has been virtually maintenance free for two years. The
only parts which eventually would have to be replaced are
the bearings. However, if they are regularly greased they
should last for some years if not towed at too high a speed
from the site of operations to the camp.
|
|
Performance indicators
(Compaction achieved)
|
Testing method: as per BS 1377 - 1990 modified procedures
and methods (sand replacement method/Modified Proctor).
General soil characteristics: sandy lateritic gravel, with
a rather high proportion of fines (A-2-4).
Relative density (compaction) achieved in production: five
to six passes gave on average 96 - 99%. We have, however,
quite often achieved relative densities of over 100%, and
we can safely conclude that five to six passes (fully ballasted)
should suffice to achieve the required compaction of 93 -
94% Modified Proctor.
|
|
|
Note: It is our opinion that, as a rule of thumb,
95% Standard Proctor would be sufficient for most climatic
conditions (100% for extremes). This could be the specified
rate of compaction on labour-based gravel roads with this
type of roller, until revised standards based on further research
for intermediate equipment are available.
|
|
Research
|
Our comparison tests between the dead-weight Roller (1) and
a one tonne pedestrian vibrating roller showed that the pedestrian
vibrating roller achieved a higher density (by about 5%-10%)
on this type of soil (a sandy lateritic soil with a high proportion
of fines). However, the dead-weight roller has also met compaction
rates well within the required margin.
This project is not yet in a position to present compaction
results/analyses obtained from research under controlled conditions.
Our test results are obtained from production testing, and
we are not sure to what extent traffic has influenced the
results. However, the combined compaction effort of equipment,
construction traffic and public traffic is what we should
be measuring. Furthermore, compaction research has been carried
out using similar types of roller at Kisii Training Centre
by students from Switzerland and Kenya over the past two years.
Their research reports are available from the ILO/ASIST Technical
Enquiry Service in Nairobi4.
|
Roller (2) Double drum
The second roller was designed based on the same basic compaction
parameters but with rather different features as explained below:
|
Function
|
A double drum dead-weight roller to be pulled by a
60 - 70hp agricultural tractor. It has an increased width
compared to Roller (1) to match the track width of the tractor.
This is to reduce the number of parallel passes and make compaction
of edges on dykes and embankments easier and safer when using
a tractor-towed roller. For improved tractor traction, refer
to the specifications of Roller (1) above.
|
|
Overall design
|
A pair of hollow steel rollers mounted in a frame, with a
detachable towing bar (can be attached at front or rear),
and with a steel bucket sitting on top of the frame.
|
|
Transportation
(Mode of transport)
|
Shipping weight is 1,600kg
Can be transported on an ASIST-promoted trailer partly filled
with soil or on a specially built low-bed trailer of the type
normally used for pedestrian vibrating-rollers, or on trucks.
Attaching transport wheels is also an option.
|
|
Operating weight
|
Empty is 1,600kg; filled with water 2,700kg; fully ballasted
4,500kg.
|
|
Volume of bucket
|
Approximately 1m3.
|
|
Drum dimensions:
|
Double drum, diameter is 900mm, width of each drum is 850mm.
Volume of one drum is 0.54m3, two drums give 1.08m3.
Manufactured from 12mm thick steel plate. The drums can be
ballasted with water, which gives an added weight of 1080kg.
|
|
Compaction characteristics
|
Static linear load (empty) is 942kg/m
Static linear load (filled with water) is 1576kg/m
Static linear load fully ballasted is 2635kg/m.
|
|
Manoeuvrability
|
Turning radius improved by the use of two drums which can
turn in opposite directions. Otherwise refer to Roller (1)
above.
Working speed and transport speed are the same as for Roller
(1) above.
Stability greatly improved with increased width.
|
|
Special features
|
This roller has been designed with a number of special features,
such as:
A detachable drawbar which can be mounted at both ends (front
and back) of the roller to be used in special circumstances
such as when turning the roller on high embankments or on
a dyke. This manoeuvre can be very difficult and dangerous.
With this special feature, which adds very little to the total
cost of the roller, the drawbar can be detached and mounted
on the other end and the roller pulled in the reverse direction.
|
|
|
A special feature of this roller is the provision for towing
the roller off-set behind the tractor (as shown in Figure
1 below) thus allowing the rear wheel of the tractor to run
safely 50cm inside the edge of, for example, an embankment.
This arrangement still allows adequate compaction of the full
width of the embankment. This feature would be even more advantageous
if the tractor were fitted with a quick release hitch of
the swivelling type.
|
|
|
|
|
|
Note: The system of off-setting tractor towed farm implements
is common and well tested in the Agricultural Sector.
|
|
Manufacturing and cost
|
The roller was locally manufactured in Lusaka by the same
mechanical engineering firm as for Roller (1).
The cost was US$ 4,857 including development costs (but not
including project staff costs).
The roller was delivered in October 1995 and has been in
operation ever since. However, this roller developed a bearing
problem and it was concluded that the bearing was under-dimensioned
for the weight of the roller when fully ballasted. This fault
was therefore corrected and the roller has not developed any
further problems during the one-and-a-half years of its operation.
|
|
Performance (Mechanical)
|
Durability has also been exemplary for this roller, as for
Roller (1). However, Roller (1) must be considered more reliable
and less likely to develop any mechanical problems than Roller
(2), a design with double drums, longer axle and a rather
more complicated bearing arrangement.
|
|
Performance indicators
(Compaction achieved)
|
Compaction density is slightly reduced compared to Roller
(1) since the linear load is less, due to increased width
of the roller, although the total weight is the same (about
4.5 tonnes). Obviously, the wider roller reduces the number
of parallel passes required. However, the reduced compactive
effect increases the number of passes required per line by
at least one. This type of roller can be used for most types
of material (except for clean sands, clays and oversize rock)
and should therefore be suitable for gravelling operations.
However, it is rather light for a static roller. Hence the
moisture content should be carefully monitored and should
be close to optimal to achieve maximum compaction.
|
|
Recommendation
|
For those who intend to invest in dead-weight rollers and
are looking for an appropriate design, we would recommend
Roller (1), the single drum roller. However, it should be
modified to include the drawbar arrangement of Roller (2),
and eventually an increased drum width of 1,500mm. Although
this will reduce compaction efficiency, 3tonnes/m would
be sufficient for most soils normally used for gravelling.
|
Future Plans
We are also in the process of designing the following equipment:
- A low-bed trailer for transporting dead-weight rollers, of the
same type as often used for transporting of pedestrian vibrating
rollers.
- Transport wheels attached to the dead-weight rollers which can
be folded up when not in use, as shown in Figure (2) below.
- A roller of the pad foot type, also to be provided with a vibration
mechanism. However, the vibration would not be produced by a small
petrol or diesel engine mounted on the roller, but by using the
tractor's PTO combined with a specially designed eccentric to
provide the vibration.
- A specially designed semi-low-bed trailer with drop sides to
be towed by a flatbed truck for the transport of tractors, rollers,
water bowsers, trailers etc. to our demonstration sites some distance
from Lusaka.

Summary
This article is not meant to be a contribution to the debate on
whether we need compaction equipment or not. Nor do we want to disparage
other methods since we do appreciate that adequate compaction can
be obtained in many different ways. The purpose of this article
is to enlighten managers of rehabilitation contractor training programmes,
and other labour-based practitioners, who have already decided that
they need compaction equipment, about an alternative to the pedestrian
vibrating-roller concept, in the shape of the dead-weight rollers
described above.
As I mentioned earlier, we are not yet in a position to back up
our development engineering work on appropriate equipment with complementary
research since our tests were carried out on a production site.
However, this should not give you sleepless nights, if you consider
purchasing a dead-weight roller of the type described, since research
carried out elsewhere, together with our production test results,
provides sufficient guarantee of usefulness. This should be especially
true for those of you who are engaged in training labour-based rehabilitation
contractors. Such contractors typically have to produce about two
kilometres of full rehabilitation of a feeder road per month, including
50% gravelling, in order to be able to repay the loan for equipment.
Such loans may range from US$100,000 to US$150,000 over a four to
five year period, and therefore a labour-based contractor is in
dire need of equipment which is durable and which has low maintenance
costs. To achieve a high rate of production, a roller should obviously
to be matched with an agricultural tractor of a make widely available
in the country of operation, with spare parts in stock and trained
mechanics locally available (and not just in the capital city).
Furthermore, as indicated by David Stiedl in his article on compaction
equipment in ASIST Bulletin No. 3 of August 1994, the way
specifications are written has to be adapted to this type of appropriate
compaction equipment (although this also applies to the pedestrian
vibrating roller). This means that the required compaction rate
described in the literature as BS- or AASHTO- should also be described
in a more empirical way as for example the number of passes required
with a given linear load for a given type of soil. This type of
specification has already been introduced in Kenya for labour-based
applications ,and is being introduced in Zambia. This means a change
from performance specifications to method specifications and thus
places more responsibility on the engineer. Relaxation of standards
is an issue which shall have to be addressed by a successful contractor
development programme, introducing intermediate technology equipment.
Otherwise an emerging labour-based rehabilitation contractor will
not be in a position to get his work approved and receive his monthly
pay cheque when he is out of the protective environment of the project.
Seven dead-weight rollers based on the design of Roller (1) are
being manufactured here in Lusaka, at a cost of US$ 3,259 per roller,
for another ILO-managed labour-based project in the country. The
only difference in design is that the width of the drum has been
increased to 1,500mm. This is an ideal width for a five metre wide
carriageway since it requires only four parallel bands with sufficient
overlapping, at five passes per band, to be rolled. This roller
can be transported on an ASIST-promoted trailer if a special low-bed
trailer is not available.
All tractor-towed equipment used here in Zambia (apart from graders)
is locally manufactured by mechanical engineering firms, thus providing
the industry with an additional market. However, their existence
is seriously threatened since they receive fewer orders from the
mines nowadays, and many contractors bring in their equipment duty
free under the privileges of donor-funded programmes. This situation
has had an adverse effect on our development efforts.
On the other hand, we have received very encouraging moral support
in our development efforts from ILO/ASIST in Nairobi. We are also
very glad that MART, through their Equipment Challenge, has initiated
a design competition for appropriate equipment. One of the categories
is tractor-towed dead-weight rollers, which clearly indicates the
need for this type of equipment.
References
Karlsson, Lars. 1987. Pilot project on labour-based road construction
and maintenance in Thailand. Compaction by labour compatible equipment.
CTP 64. Geneva, ILO
Stiedl, David. 1994. Compaction equipment. What is appropriate
for labour-based works? ASIST Bulletin No. 3, August 1994.
Danso, Henry. 1996. Factors influencing the output of labour-based
contractors in Ghana. Paper presented at Fifth Regional Seminar
held in Accra, Ghana in April 1996.
Andersson, Claes-Axel, Beusch, Andreas and Miles, Derek.1996. Road
maintenance and regravelling (ROMAR) using labour-based methods.
Handbook. Intermediate Technology Publications

Hand
Tools in Urban Infrastructure Project in Addis Ababa
Tesfaye Kunbi, CARE Ethiopia, PO Box 4710, Addis Ababa, Ethiopia
Ethiopia is one of the least developed countries in the world.
Constant urban migration to the capital of Addis Ababa over the
past few years has resulted in an increasing number of urban residents
living in extreme poverty. The Municipal Council of Addis Ababa
estimates the current urban population at 3.0 million inhabitants.
The majority of the city's population reside in severe slum conditions,
lacking adequate housing and the provision of basic services (e.g.
potable water, sanitation, roads, health facilities, etc). The present
day economy offers little employment opportunities, especially for
unskilled labourers, and although food is readily available in the
capital, most families in marginal communities experience food deficits
due to the lack of adequate income required to meet their basic
food requirements.
The Community Infrastructure Development/Urban-Food-For-Work Programme
was developed by CARE Ethiopia in 1993 in an effort to address the
needs of the urban poor, specifically the lack of primary infrastructure
and excessive unemployment within marginal urban communities in
Addis Ababa. The programme consists of a series of community based
public work projects utilising a food-for-work model in order to
provide improved basic services and generate short term employment
opportunities for residents living in less economically favoured
neighbourhoods within the city limits. The project undertakes the
construction of access roads and the provision of sanitation facilities
and water supply as these are main concerns of target groups. A
socio-economic survey of the total households in a community, targeted
as beneficiary of the project is undertaken. This is followed by
a task force committee for site selection. This task force is mainly
composed of representatives from the municipality of Addis Ababa,
the Commission for Disaster Prevention and Preparedness and CARE.
The committee having gone through the economic survey results, and
visited the target communities, come up with lists of communities
to be addressed by the project. The involvement of community members
through labour-inputs is encouraged, alternatively a 5 - 10% financial
contribution to the cost of construction materials is recommended.
This is only to ensure that residents feel that they own the built
infrastructure.
After having completed the basic documents like project design
and cost estimation, budget allocation and sources, etc., the parties
to be involved sign the agreements.
Project communities are encouraged to enrol the workforce from
their own communities, however, if this is not possible, it is advised
employ from neighbouring residential communities. The main actor
besides CARE in the intervention is the Infrastructure Development
Committee.
The committee takes over duties like management of project finance
materials, and liaison of the project with government offices.
The construction materials required are provided by suppliers.
Tenders for supply of construction materials to project sites are
issued and evaluated by all parties involved in the project.
Workforces are paid based on the group outputs. There are fixed
work targets set for every activity. Out of the group earnings skilled
worker earn three rations, semi-skilled two rations and unskilled
workers one ration day. One ration is equivalent to 3.5 kg of wheat
and 175 gms of vegetable oil.
When project activities come to a close, the basic necessary tools
are handed over to the committee to be used for maintenance purposes.
A maintenance fund continues to be raised by community welfare associations
and every household in the community. The project has built over
80kms of stone paved roads with an average width of 4.5m, 65 communal
latrines to be used by 1,560 households, and eighth developed springs.
CARE is working along with local non-governmental organisations
as partners with the aim of building their capacity. About 135 unskilled
labourers have been promoted to skilled grade.
The urban food-for-work project is entirely funded by USAID. USAID
allocates resources in the form of commodities (wheat and vegetable
oil). Part of the vegetable oil is monetized to cover costs for
construction materials, salaries and other expenses. The problems
encountered are as follows.
To acquire a plot of land for an on-site sanitation scheme has
become very difficult, owing to the government's policy on land
ownership. Land is government property in Ethiopia. Facilitation
of land permits in government offices has become a big challenge
to the project.
After having set up the maintenance schedule and method, the project
phases out. It is observed that committee members neglect their
duties and as a result maintenance responsibilities are not respected.
The project life in a single communities is up to one year only.
The project participants, numbering around 215 become unemployed
again, after the project phases out. Only a small number (2%) has
success in obtaining jobs on other related activities.
The projects being undertaken in these marginal communities involve
the application of hand tools to a higher degree, owing to the fact
that construction of the infrastructure works (access roads, communal
latrines, spring developments, clinics, etc) are labour intensive.
Only in exceptional cases are mechanical machinery, like concrete
vibrators, rollers, water pumps, etc., applied.
The hand tools that are commonly used in the activities are shovels,
pickaxes, crow bars, hammers, saws, wheelbarrows, etc. These tools
are manufactured in local factories. Their life span ranges from
one to two years. Some of these tools (especially shovels and wheelbarrows)
are found not to be hard enough to stand up to the anticipated service
conditions nor ductile enough not to crack.
Investigations at local manufacturing factories revealed good reasons
behind every cracked die, every spelled cutting edge, and every
broken chisel. Once in a while, it is true that tools failures are
caused by defective steel. But hazardous tool design, improper grinding
and mechanical factors play a far greater role. Most frequent of
all are failures due to faulty heat treatment.
It is highlighted that factors like good design, sound tool steel
of the proper grade, correct heat treatment, proper grinding and
proper application of the tools contribute to successful tool making.
These fundamentals are like the links of a chain; a deficiency in
any one of the elements, or links, leads to trouble. Each of the
above mentioned factors must be given proper attention in order
to achieve the best possible tool performance.
The cost of hand tools is about 3% of the total project, so a small
investment in this element has a substantial impact on the productivity.
Labour productivity is mainly influenced by effectiveness of organisation,
supervision of labour-based activities, motivation of the workforce
and the quality and efficiency of the tools used.
The quality of hand tools is entirely based on three factors: (a)
efficiency (b) strength of the tool and (c) wear and durability.
Investigations made in Kenya have shown that construction quality
tools as compared with farm quality tools are more productive possibly
because they were 25% lighter than the farm type. The main parameters
involved are shape, size, weight and finish of the tool.
The strength of the farm tools was found to be inferior, mainly
because of the lack of hardening of the steel. Using the correct
grade of steel, medium-carbon, which allows hardening all the way
throughout the tool (not just surface hardening) is important in
achieving the strength to resist impact blows. The parameters are
shape, size, material and heat treatment.
Another factor affecting labour productivity is the wear and damage
of the cutting edges and working surfaces of the tools.
Workers benefit from having good quality hand tools in being able
to complete work with less effort and in less time. They are also
likely to be less fatigued and suffer fewer injuries such as blisters
and muscles strains. There are, of course, significant benefits
from reduced medical costs for the work force.
The following recommendations are made to promote the use of improved
hand tools:
- create greater awareness of the importance of good quality hand
tools to labour-based road works, particularly with procurement
staff.
- present specifications in a more concise and readily accessible
form. They also need to be backed up by simple tests that can
be carried out on site to check that the tools comply with the
specs. These consist of: a visual check on shape, dimensions and
furnishings, as well as a blacksmith's test to identify the steel
used
- co-ordinate markets within countries so that demand is sufficient
to encourage ready availability of better quality tools.
I will now make a few points about some of the hand tools that
we are using.
Axes
The lighter the axe is, the easier it is to use and since accuracy
is more important than weight for most cutting jobs, the weight
should not exceed 1kg. Axes are the tools of specialists, and a
compromise in quality and or design can be disastrous.
We have in certain parts of the city compensated for the use of
own axes. Pre-delivery check and bending tests are essential to
weed out sub-standard brands.
Crowbars
‘Fake" crowbars made of reinforcement rods or other mild steel
should not be considered for heavy construction work. Good quality
(hexagonal) crowbars of a good steel grade are recommended.
Handrammers
Handramming has proved to be very difficult to control and is only
recommended in connection with culvert laying or very small foundation
works.
Shovels
The locally produced shovels proved totally inadequate with a blade
that could easily be bent by hand. It is recommended that shovels
be fitted with wooden handles of suitable length. The length of
the handle for throwing or loading of trucks, should be at least
1.2m.
Although specifications are useful, it is sometimes not possible
to carry out the necessary testing before delivery, and in such
cases one has to rely on well-proven brand names/manufacturers.
The procurement of tools should be done well before the start of
a project. This makes it necessary to provide separate (and faster)
funding for the tools. This will also call for secure storage of
the tools and it is recommended that a strict stores inventory system
is enforced.
Hand
Tools in Labour-based Works: Some Notes for Consideration
Yaw A. Tuffour, Department of Civil Engineering, University
of Science and Technology, Kumasi, Ghana
Summary
Lack of good quality and adequate supply of hand tools on labour-based
work sites is a common problem that bedevils many labour-based construction
projects. Hand tools constitute the driving force for productivity
in labour-based works and are often the most critical items to consider
when it comes to the progress of construction. Compared with the
investment in capital equipment in capital-intensive works, the
capital outlay for investment in hand tools in labour-based works
represents only a small proportion of the total project cost. Ironically,
however, it is in hand tools that many labour-based practitioners
and contractors hardly direct any investments because the supply
of tools and capital provision for their supply are not perceived
as important issues. In this paper, issues pertaining to hand tools
in regard to quality, supply and management and the importance of
hand tools in labour-based works in general are discussed.
Introduction
In labour-based construction, hand tools are the major items employed
by labour for productivity. Whereas it is possible to construct
roads using labour and hand tools without equipment, it does not
appear possible to do so with labour and equipment without hand
tools (Makoriwa, 1993). In effect, hand tools represent the driving
force for productivity in labour-based construction. A unique aspect
of labour-based construction is that compared to the investment
in capital equipment for capital-intensive works, the capital outlay
for investment in hand tools for labour-based works represents only
a small proportion of the total project cost.
Fortunately for labour-based works, hand tools do not usually pose
procurement problems because unlike capital equipment which for
developing countries must be imported specifically for the construction
industry and under special order, hand tools employed on labour-based
works are simple tools developed primarily for the agricultural
sector and which for many developing countries may be locally purchased.
In some developing countries with an intermediate technology base,
hand tools may be easily manufactured by local artisans. Although
hand tools are crucial to the successful execution of labour-based
works, many practitioners and contractors associated with labour-based
construction technology do not appear to give hand tools the attention
that they deserve.
The progress of labour-based projects can be slowed down if construction
problems associated with hand tools are persistently ignored or
left unresolved. In a study of the performance of selected labour-based
contractors in Ghana, some of the major factors observed to hamper
progress of construction at various contractor sites related to
hand tools. On some construction sites, it was common to find tools
questionable quality, tools with broken handles or tools in a completely
worn-out state being used. The most serious tool problem requiring
urgent attention related to supply. It was not uncommon to find
workers chasing after tools at the beginning of the workday.
On one contractor site, inadequate supply of tools compelled workers
to supplement tools on site with hand tools brought from their homes.
Obviously, in situations where there is a lack of such goodwill
and co-operation on the part of workers, worker output could be
very low as a good proportion of workers spend a significant proportion
of the available man-hours idling or waiting for a given type of
hand tool to become available. Even on some construction sites where
most of the tools were found in a satisfactory state or were available
in sufficient quantities, there was no evidence of a proper set-up
for effective tool management. Such situations could easily give
rise to problems such as tool loss and pilfering which would call
for frequent replacement and replenishment of stock. In a typical
case, for example, a contractor kept his tools in a private kitchen
in one of the villages along the construction route. This allowed
pilfering of tools to go unnoticed and unchecked as workers who
went for the tools at the beginning of the day were not accountable
to anyone for their return at the end of the day. This seemingly
isolated case epitomises the general lack of appreciation of the
importance and relevance of hand tools in labour-based works and
the need to take the issue of hand tools very seriously.
Despite the direct and obvious link between hand tools and productivity,
many labour-based practitioners have failed to direct the needed
investments to hand tools. In this paper, the issue of hand tools
is discussed. The focus is on tool quality and quantity. Some titbits
on general tool management are presented to help labour-based practitioners
practise effective and efficient tool management for their works.
Tool Quality and Supply
Quality and quantity are two attributes that rarely go together
in many real life situations, but when it comes to hand tools in
labour-based works, it is important and necessary that tools of
the right quality be in the right quantities at the right time.
Tool condition is usually placed in three quality rating categories,
namely; excellent (T3), satisfactory but needing some attention
for improvement (T2), and unsatisfactory or defective needing replacement
(T1). An indication of the tool supply situation can be obtained
through the tool availability ratio defined as the ratio
of the number of tools available for a given task to the number
of labourers assigned to that task. The ratio in a sense measures
the probability that a worker assigned to a particular task will
have the necessary tool to work with as and when required. Obviously,
the tool supply situation in respect of a given tool for a given
activity is satisfactory if the tool ratio is at least unity. In
gang work with several sub-activities, such as for example, excavation
and loading of gravel, which requires several different hand tools
to execute, the tool ratio concept must be interpreted to mean the
availability of all the needed tools for all the sub-activities
such that each and every worker within the gang or group will have
a tool to work with as and when needed.
Table 1 provides an overview of the general tool situation on a
number of labour-based construction sites in Ghana. A tool situation
worse than that provided by the table is unlikely to result in productive
output on site and may require intervention on the part of management
to raise productivity levels. In the case of tool quality, simple
interventions like smoothening of handles and sharpening of tool
heads may be all that is needed to restore tool quality and improve
worker efficiency and output. In many cases, this action is seldom
carried out allowing tool quality to deteriorate to unacceptably
poor levels.
Neglect of tool quality and stock replenishment are likely to result
in the following major costs to both the worker and his employer
(labour-based contractor):
- increased worker fatigue
- low worker efficiency
- low productivity
- poor quality work
- reduced worker earnings
- increased worker time input
- increased idle time
- disruption of work schedule
- reduced flexibility associated with piece- and task-work systems
in accommodating other worker obligations and interests such as
farming activities.
- delay in project completion.
In the case of loss of the flexibility associated with the task-
and piecework systems, labour-based activities in areas with predominantly
agricultural activities could lose out to agricultural activities
for labour during periods of intense and heightened farming activities.
Experience shows that labour in such areas is only willing to accommodate
labour-based activities alongside their farming commitments in so
far as the system of work contract between the worker and the contractor
in the labour-based works pays on the basis of "finish-and-go" rather
than "by-day". If due to poor quality and non-availability of the
right tools at the time when they are needed workers will have to
spend a greater part of the day on their piecework or taskwork to
the detriment of their farming commitments, or if at the end of
the work they feel fatigued and exhausted, they are unlikely to
consider their participation in the labour-based works as of any
benefit to either their short- or long-term interests.
Table 1. A typical tool situation on labour-based site in Ghana
|
Activity
|
Recommended tools
|
Tools in use
|
R1
|
Tool condition
|
|
Bush clearing
|
Cutlass, sharpening stone
|
Cutlass
|
1
|
T2
|
|
Grubbing
|
Hoe, cutlass, spade, bolster rake, headpan, pickaxe/mattock
|
Hoe
Headpan
Rake
|
1
0.46
0.36
|
T2
|
|
Filling of gullies, depressions, etc.
|
Shovels, hand rammer, wheelbarrow, mattock/pickaxe
|
Mattock
Spade
Headpan
|
0.93
0.93
0.56
|
T2
|
|
Cut widening
|
Shovel, spade, pickaxe/mattock
|
Mattock, Spade/shovel
|
1
0.81
|
T2
|
|
Ditching/Sloping
|
Pickaxe/mattock, ditch/slope template, spade, string
|
Mattock
Spade/shovel
|
1
0.74
|
T2
|
|
Camber formation
|
Spade, pickaxe/mattock, rake, pegs, watering can, sledge
hammer, camber board, wheelbarrow, spirit level
|
Spade
Rake
|
1
0.5
|
T2
|
|
Gravel excavation
|
Shovel, pickaxe/mattock, fork hoes, ranging poles
|
Mattock/pickaxe, Spade/shovel
|
1
1
|
T2
|
|
L-H-O of gravel
|
Shovel
|
Shovel
|
0.93
|
T2
|
|
Gravel spreading
|
Spade, watering can, rakes, pegs, strings, spirit level,
hand rammer, camber board, wheelbarrow
|
Spade/shovel
Rake
|
0.81
0.53
|
T2
|
R1=Tool ratio-defined
as the number of tools available for task to number of workers assigned
on task. R<1 indicates insufficient quantity of tools
T1: Both tool handle and tool
head are worn out. Replacement required.
T2: Condition of tool is such
that sharpening of head or smoothening of handle will greatly improve
its efficiency.
T3:Excellent condition, virtually no defect
visible.
Tool Management
Labour-based works may be executed much more efficiently and successfully
if proper and effective tool management is practised. The essence
of tool management is to ensure that the right type of tool in the
right condition is available at the right time for executing a given
activity. Improper tool management may create supply problems and
impede the speed of the construction. In some cases, it may require
additional investment in tools as the available stock is depleted
through theft from lack of proper control and care.
For proper tool management, it may be necessary to assign the responsibility
of hand tools for site activities to a supervisor or personnel who
may be designated the tools manager. The tools manager must be charged
with the following responsibilities:
- keeping a daily record of tools issued out for site activities
and returned at the end of the work day
- keeping a periodic inventory of tools
- drawing up a programme for the quantity and type of tools required
at all stages of construction
- advising on the storage arrangements to protect wooden tool
handles from fungi and termite attack
- providing a periodic update of the state of tools regarding
both quality and quantity for the attention of the contractor
- monitoring the rate of tool wear, breakage, and loss
- establishing preferences of the local labour in the use of the
different types of hand tools
- identifying and providing a list of changes needed to be made
in future orders of hand tools regarding, for example, brand and
type
- where tool replenishment or replacement is anticipated he must
pass the information on to the contractor for purchases to be
carried out ahead of time of anticipated need
- drawing up a programme for periodic restoration of or improvement
in the quality of tools through sharpening of tool head and smoothening
of handles
Because labour-based activities are organised under supervisors
and gang leaders, it is considered much more efficient to deal with
supervisors and/or gang leaders rather than the individual workers
regarding matters of hand tools for the daily activities. Supervisors
or their gang leaders must be responsible for signing for tools
for co-workers within their gang or under their supervision and
ensuring their return to the tool manager at the end of each work
day. The incidence of tool theft can be minimised considerably if
the cost of a missing tool is charged against the supervisor or
the workers within a gang responsible for the missing tool. This
policy must be made clear to all workers by the tool manager, or
the contractor or his representative on site to ensure full co-operation
of all workers in controlling tool loss and theft. There must be
a buffer stock of tools so that damaged tools can be replaced immediately
when necessary and/or losses catered for to avoid disruption of
certain site activities.
Tool managers must not deal directly with individual workers unless
a worker has some useful information to provide for the general
attention of the tool manager in regard, for example, to the difficulty
of use of a given brand and type of tool, which information may
be useful for guiding future investments in tools.
Why the Low Investments in Hand Tools?
Non-availability of good quality tools on the local market, incompetent
purchasing officers and importation restrictions are some of the
reasons put forward to explain the low investment in hand tools
or the deplorable state of hand tools on many labour-based construction
sites (Makoriwa, 1993). Even though some of these reasons may be
tenable in certain cases, in most cases, the main reason for the
hand tool situation seems to be the fact that the supply of tools
and capital provision for their supply are not perceived as important
issues (Howe, 1988). This appears to explain why, for example, some
years after embracing the labour-based technology, a number of countries
with the potential to manufacture hand tools comparable in quality
to those from overseas sources have not formulated any coherent
strategy for the manufacture of hand tools locally and continue
to depend on overseas sources for supply.
There appears to be another dimension to the problem of low investment
in hand tools; it is thought that perhaps the types of work contracts
practised in labour-based works (most of which are task- or piece-rate
systems) in themselves do not provide adequate incentive for the
employer/contractor to invest adequately in hand tools. After all,
for such types of contracts, the onus of getting the job accomplished
in order to earn the associated benefits (wage) is on the labourer.
It is very easy in such cases for the contractor to shirk his moral
responsibility of facilitating the execution of the contract (in
this case a taskwork or piecework) for the worker by ensuring that
the right set of tools is made available to the worker at the right
time.
According to Howe (1988), the general problem of low investments
in hand tools may be addressed by creating a greater awareness at
all levels of how crucial good quality tools in sufficient quantities
are to road improvement and maintenance by the labour-based technology.
An effective way to do this is to organise national workshops on
the subject periodically. Whatever the case, it must be clear to
all labour-based contractors and practitioners that there are no
alternatives to investments in hand tools in the labour-based technology
and that such investments serve the interests of such stakeholders
better.
Conclusions
This paper looked at the investment in hand tools by labour-based
contractors/practitioners. It noted and discussed the effects of
tool quality and quantity on productivity and the general progress
of labour-based works. Basic aspects of tool management were presented
for the consideration of labour-based contractors and practitioners.
The poor investments in hand tools characterising the labour-based
industry are attributed to the fact that the supply of tools and
capital provision for their supply are not perceived as important
issues by stakeholders in the industry. It is also thought that
because the type of work contract practised in labour-based works
is mostly task- or piece-rate systems, there is very little incentive
for the contractor to provide the necessary tools to facilitate
the execution of the contracted activities by the labour-based worker.
To address these problems, it is thought that a greater awareness
needs to be created of the importance of investments in hand tools
in labour-based works through local and national workshops on the
matter. Finally, it is stressed to all stakeholders in the industry
that there are no alternatives to hand tools in labour-based technology.
References
Howe, J. 1988. Ghana feeder roads project construction hand
tools study. World Employment Programme, CTP 86, ILO, Geneva
Makoriwa, C. 1993. Hand tools and equipment- The current scene.
Report of Proceedings, 3rd Regional Seminar on Labour-based
Technology, Harare, Zimbabwe, October 1993. ILO, Nairobi
Footnotes
1
Force account: Road authority carrying out works using its own permanent
manpower and equipment fleet.
2 See Designs and specifications for a standard
trailer and hitch for labour-based works, ILO/ASIST, 1996
3 This involves forming a
level platform (the subgrade) before excavating the drains, and
the inner and outer slopes, to build up the road pavement in stages.
The first stage is to form a "plug" in the centre of the road by
excavating material from the side drains. This plug will generally
be half the height (at the centre) of the final camber.
4 ILO/ASIST Technical Enquiry
Service, PO Box 60598, Nairobi, Kenya; Tel +254-2-560941; Fax+254-2-566234;
E-mail: iloasist@iloasist.or.ke
|