Productive employment for poverty reduction
Employment-based works in
Madagascar
Since more than twenty years, NORAD
has been providing financial assistance to feeder road rehabilitation and
maintenance in the framework of its support to FIFAMANOR, an integrated
rural development programme on the highlands of Madagascar. By 1990, GOM and
NORAD, with technical assistance from the ILO's Employment-Intensive Investment
Programme, decided to shift construction technology from mechanised to
labour-based methods. Comparative studies on labour-based vs. mixed or fully
equipment-based construction methods have shown that the labour-based option has
three advantages:
· Financial costs are about 30 to 80 % lower;
· They generate 2 to 5 times more employment; and
· They save at least 30 % of foreign exchange requirements
compared to the more capital-intensive options.
The programme's impact on poverty
reduction is achieved through employment and income generation: as shown in the
following table, the monetisation of the rural economy resulting from a 1
million$ investment in feeder roads is about 4 times higher in the labour-based
approach (298,000$) than in the equipment-based approach (75,000$ only). The
temporary employment generated is also about 4 times higher
|
Method of implementation
|
Equipment-based
|
Labour-based
|
|
Part of investment going to labour cost for an investment
of 1 millions $
|
75,000 $
|
298,000 $
|
|
Number of mandays created
|
79800
|
316.900
|
|
Number of jobs created (average duration of employment: 5
months)
|
638
|
2535
|
Average labour cost per manday for road construction:
6582 Fmg or around 1 $/day (based on daily remuneration for unskilled labour:
6000 Fmg, Skilled labour: 10.000 Fmg, Headmen: 11.000 Fmg, Officer-in-charge:
15.000 Fmg; Current exchange rate: 7000 Fmg per dollar)
An injection of 1 million
$ into the feeder road sector through labour-based techniques increases GDP by
1.16 million, while the same investment made with equipment-based techniques
increases GDP by only 0,682 million. The impact of the labour-based approach on
household income and consumption is 2.5 times higher than for the
equipment-intensive approach. The relatively low multiplier effect of
equipment-based investment results from the high expenditure on imported goods;
with a large part of the investment being transferred abroad, the multiplier
effect on local production remains limited.
These remarkable results
of the labour-based approach can only be achieved through sustained efforts at
capacity-building at various levels, in particular in the small and medium sized
entreprise sector. And this is precisely what the NORAD/ILO programme in
Madagascar has set out to do.
In the feeder road sector,
for an investment of 1 million $, about 83 km of rural graveled roads can be
constructed (average cost/km 12,000$, without considering project overhead
costs). The GOM/NORAD/ILO project assigns contracts normally not exceeding 5 to
6 km per contract, which means that about 15 contracts can be awarded. As one
contractor can win more than 1 contract if he has the necessary capacity, we can
assume that in total, 10 contractors are awarded one or two contracts. The
following personnel is trained per contractor:
-
The manager in enterprise management (one week)
-
The officer-in-charge or site supervisor (minimum 4 weeks)
-
At least two headmen (4 weeks).
In summary, about 4
technical/managerial staff per contractor have to be trained in labour-based
methods. To these, on-the-job training of a workforce of 60 to 80 workers per
entreprise has to be added.
Training programmes for
technical and planning staff are organised on contract preparation and
supervision; this training is also open to local engineering consultants.
Moreover, the programme
has tested successfully various arrangements for feeder road maintenance under
communal responsibility; special training programmes for local government and
maintenance workers are also provided.
It should be
noted that the ILO training programmes do not only cover technical aspects, but
also managerial issues, including labour policies and practices, with aview to
simultaneously promote job creation and decent working conditions for the
labour force.
For the
building sector, and in particular school construction, supported by
NORAD/ILO in the framework of NORAD’s support to a UNICEF/FLM/GOM primary
education programme, the cost of a three class-room primary school is estimated
at 17.500$. Hence, for an investment of 1 million $, about 57 schools can be
constructed. Here again, depending on the workplan and the capacity of the
contractor, one contractor can obtain more than one contract, and one may assume
that in total about 40 contractors are involved in a 1 million $ investment
programme in school rehabilitation. Upfront training is required for:
-
Preparation of bids
-
Setting out and other technical aspects which need attention
-
Accountability
As these are
small-sized contractors, the manager is at the same time the officer-in-charge
of the construction. Normally, one technical/managerial staff per contractor is
trained. On-the-job training will be provided to a workforce of 20 to 25 workers
per contractor.
The table
below shows that the building sector, in this case school rehabilitation, can
also greatly contribute to reaching simultaneouly objectives of empoyment and
income generation, monetisation and poverty reduction.
|
Method of
implementation |
School construction
using local materials as much as possible
|
|
Part of investment going
to labour cost for an investment of 1 millions $
|
206.000
|
|
Number of mandays created*
|
190.700
|
|
Number of jobs created
(average duration of employment: 3 months)
|
2.540
|
2/3 are unskilled labour (at 6.000
Fmg/day) and 1/3 are skilled labourers (at 10.000 Fmg/day).
The
policies pursued by NORAD in close collaboration with ILO in the recently
approved new phase in the feeder road programme (4,3 million$), and with
ILO/UNICEF in the first phase of the new school rehabilitation programme (2,6
million $, covering 100 schools of a total of 300) reflect a comprehensive
approach to development which has proven on the ground that objectives such as
private sector development, job creation and decent working conditions,
monetisation and improved income distribution, decentralisation and
accessibility issues (both economic and social), local level capacity building
and governance, can be addressed effectively and simultaneously, with better
chances –if sustained in the medium term- of mutual reinforcement and
accelerated economic and social progress.
|