Decision on the third item on the agenda: Update on the headquarters building renovation project

Record of decisions | 04 November 2014

Decision on the third item on the agenda: Update on the headquarters building renovation project

The Governing Body

(a) took note of the proposed additional requirements and costs associated with the granting of the building permit and the resulting reduced scope of the project required to retain the total cost approved in the 2010 plan while implementing necessary safety and environmental measures; and

(b) requested the Director-General to continue to explore options for additional financing beyond that approved in the comprehensive plan to enable the full scope of the project to be realized.

(Document GB.322/PFA/3, paragraph 28.)